945.02MATERIALS. Not applicable

RI · 2024 Standard SpecificationsBook pages 624625View official source ↗

9−92 Contractor shall request a disbursement from the Force Account amount. Each such request must include a detailed account for each particular “unit” of completed emission retro-fit work as defined above under Subsection 944.04.1. Payment of a disbursement request from the Force Account constitutes full and complete compensation for all labor, materials, equipment, tools and incidentals for completing the stated units of emission control retrofits as required to finish the work, complete and accepted by the Engineer.

944.05.1 Costs Not Included In This Item.

All costs associated with the implementation of the DERP including training costs inventory lists, retaining the qualified retro-fit installer, Statement of Intent to Comply Documentation of Post Retro-fit Installation, Program Documentation and Logs, monthly summary reports to the Engineer, and the addition and removal of equipment used in this work, will not be paid for separately. Costs thereof shall be included in the Contractor’s overhead costs for performing the work of the Contract. SECTION 945 REMOVAL OF TRAFFIC SIGNAL EQUIPMENT

945.01 DESCRIPTION. This work consists of removing and either disposal or salvaging of existing

traffic signal equipment, as called for on the Plans. Traffic signal equipment to be removed may include, but is not limited to, traffic signal wire and cable; mast arm, span, and pedestal poles with or without foundations; traffic signal cabinets with or without foundations; traffic detectors and pedestrian pushbuttons; controllers, relays, and associated equi pment housed inside traffic signal cabinets; and traffic signal heads. Removal of existing handholes, manholes, conduit, and risers associated with a traffic signal will be paid for under the appropriate individual and separate pay item.

945.02 MATERIALS. Not applicable.

945.03 Construction Methods.

945.03.01 General. Where traffic signal equipment is to be removed from an intersection that will

remain open to traffic and be controlled by a new or improved traffic signal implemented as part of the Contract, the Contractor shall minimize the amount of time that a traffic signal is not operational and actively controlling traffic at the intersection, and the Contractor shall plan for and schedule the work accordingly. Unless otherwise approved by the E ngineer, the Contractor’s schedule shall provide for the new or improved traffic signal to be operational before the end of the same working day when the existing traffic signal is turned off. An appropriate number of Trafficpersons and other temporary traffic control devices, as approved by the Engineer and as may be shown on the Plans, must be used to safely control traffic at such intersections when the traffic signal is not operational. The Contractor shall avoid damaging existing equipment and materials that are to remain in place while removing traffic signal equipment. Damage that occurs due to the action or inaction of the Contractor shall be repaired by the Contractor at no additional cost to the State. When a gap or opening remains on an existing-to-rema in pole after the removal of traffic signal equipment, the Contractor shall cover such openings using a knockout seal or other appropriate 9−93material in order to provide a secure closure of the opening to the satisfaction of the Engineer. There will be no separate payment for this work. Unless otherwise indicated on the Plans, a Plan callout to remove and dispose the foundation of a traffic signal pole or cabinet shall require the removal of the foundation, including all reinforcement, ground rods, and conduit/wiring within, to a minimum depth of twenty-four (24) inches below the finished grade surrounding the foundation, with the remaining portion of the foundation to remain buried in place. The resulting excavated areas shall be backfilled with suitable material, compacted, and finished in accordance with the applicable Sections of these Specifications so that the patched areas will match existing conditions to the satisfaction of the Engineer.

945.03.02 Removal and Di sposal of Traffic Signal Equipment. All existing traffic signal equipment

to be removed and disposed will be identified on the Plans, and all such designated equipment shall, upon removal, be legally disposed of.

945.03.03 Removal and Salvaging of Traffic Signal Equipment. All existing traffic signal

equipment to be removed and salvaged will be listed in a table on the Plans. The delivery address and contact person information for all such salvaged equipment will also be provided on the Plans. All pieces of equipment to be salvaged shall be tagged by the Contractor, with each tag identifying the Contract number, the intersection or location from which the equipment was removed, the date that the equipment was removed, and a description of the name and/or type/function of the equipment. The Contractor shall call the contact person to coordinate the delivery of the salvaged equipment, and no delivery shall be scheduled prior to confirming an acceptable date/time with such contact person. All salvaged traffic signal equipment shall be delivered to the address noted on the Plans. The Contractor shall obtain a written receipt(s) for all equipment that has been received at the delivery address and submit such to the Engineer to allow for processing of payment(s).

945.04 METHOD OF MEASUREMENT . “Remove and Dispose Traffic Signal Equipment” and

“Remove and Salvage Traffic Signal Equipment” do not require a measurement for payment. The lump sum unit of measure will be used and included in the Contract where these items are specified.

945.05 BASIS OF PAYMENT . “Remove and Dispose Traffic Signal Equipment” and “Remove and

Salvage Traffic Signal Equipment” w ill be paid for in accordance with Section 109.07 of the Standard Specifications and at the Contract lump sum price as listed in the Proposal. The price constitutes full and complete compensation for all labor, materials, equipment, and all incidentals required to finish the work, complete and accepted by the Engineer.