834.01 DESCRIPTION . This work consists of providing straight or circular granite curbing at the
locations indicated on the Plans or as directed by the Engineer, all in accordance with these Specifications. The two basic types of curbing are described as follows:
834.02 MATERIALS . Granite curb for bridges shall conform to the requirements of Subsection
834.04 METHOD OF MEASUREMENT. "Vertical Face Granite Curb Straight,” "Vertical Face
Granite Curb Circular,” "Slope Face Granite Curb Straight,” and "Slope Face Granite Curb Circular" will be measured (along the front arris of the curb) by the number of linear feet of such curbing actually installed in accordance with the Plans and/or as directed by the Engineer.
834.05 BASIS OF PAYMENT . The accepted quantities of "Vertical Face Granite Curb Straight,”
"Vertical Face Granite Curb Circular,” "Slope Face Granite Curb Straight,” and "Slope Face Granite Curb Circular" will be paid for at their respective contract unit prices per linear foot as listed in the Proposal. The prices so-stated constitute full and complete compensation for all labor, materials and equipment, and all incidentals required to finish the work, complete and accepted by the