B
HomeLibrariesCopilotSearchProjectsBookmarks
FeedbackHelp Desk
Libraries
Building Codes
Code LibraryIBC — BuildingIRC — ResidentialIFC — FireIPC — PlumbingIMC — MechanicalIFGC — Fuel GasIECC — EnergyNEC — ElectricalModel Codes
Specifications
CSI SpecificationsDOT SpecsTransit SpecsUSACE
Standards
TransportationRailroadFire SafetyAccessibilityStructural
Tools & References
DiagramsAssembliesProductsCalculatorsChecklistsPermits
PricingLog in
General

108108.10 Termination on Public’s Behalf

WY · 2021 Standard SpecificationsBook pages 00View official source ↗

1 The department may at any time, by written notice, terminate all or part of the contract

when the department determines it in the public’s interest to do so. Before such termination, the engineer may require the completion of unaffected parts in accordance with the contract. 2 When all or part of the contract is terminated, the department will pay the pay item price

for the actual number of units completed or will compensate the contractor for actual costs incurred for work not started or completed. The department will purchase from the contractor acceptable materials obtained but not used, at the actual costs shown by receipted bills and cost records and delivered as designated by the engineer. Give the engineer access to all books, cost records, correspondence, and papers necessary to determine the relevant prices and amounts. 3 The department intends in this provision to provide for an equitable settlement with the

contractor. The department will not pay for loss of anticipated profits under this provision. Termination does not relieve the contractor or the surety of its liability for just claims arising out of work performed. Under termination, title to all property accruing to the commission vests immediately in the state of Wyoming. Execute and deliver all necessary papers to the engineer.

90

Measurement and Payment

109.1Measurement of Quantities

109.1.1 Standards 1 The department will measure pay items in the units of measure specified in the contract

using methods of measurement and computation that meet generally recognized good engineering practice. Units of the U.S. customary system of weights and measures are defined in 15 U.S. Code, Section 205. Units of the metric system, or SI (the International System of Units), and the standard of practice for its use, are provided in IEEE/ASTM SI 10. 109.1.2 Symbols for Bid and Pay Items 1 The following table shows the symbols used in these Standard Specifications, in the

“Proposal” (Form E-91), and elsewhere in the contract to indicate the units in which the department will measure bid and pay items: Table 109.1.2-1 Unit Symbols for Bid and Pay Items For Contracts Specified in: Inch-Pound Units (U.S. Customary System)

For Contracts Specified in: SI (International System) Units (Metric)

Bid or Pay Unit

Symbol

Bid or Pay Unit

Symbol

acre

ACRE

hectare

ha

cubic foot

CF

cubic meter

m

cubic yard

CY

cubic meter

cubic yard hour

CYHR

cubic meter hour

m m3h

cubic yard mile

CYMI

cubic meter kilometer

m3km

each

EA

each

Ea

force account

$$

force account

$$

gallon

GAL

liter

L

thousand gallons

MG

cubic meter

M3

hour

HR

hour

H

CRWH

crew hour

Crwh

pound

LB

kilogram

Kg

foot

FT

meter

m

crew hour

91

Measurement and Payment

Source: Wyoming Standard Specifications for Road and Bridge Construction, 2021 Edition. Pages 00 of 771.