B
HomeLibrariesCopilotSearchProjectsBookmarks
FeedbackHelp Desk
Libraries
Building Codes
Code LibraryIBC — BuildingIRC — ResidentialIFC — FireIPC — PlumbingIMC — MechanicalIFGC — Fuel GasIECC — EnergyNEC — ElectricalModel Codes
Specifications
CSI SpecificationsDOT SpecsTransit SpecsUSACE
Standards
TransportationRailroadFire SafetyAccessibilityStructural
Tools & References
DiagramsAssembliesProductsCalculatorsChecklistsPermits
PricingLog in
General

1047. A statement detailing the VECP’s effect on the contract completion date.

WY · 2021 Standard SpecificationsBook pages 00View official source ↗
8.A description of previous use or testing of the same or a similar VECP and the

circumstances and results. If submitted on another department project, indicate the date, project number, and the action taken by the department.

9.When asked in writing, provide within ten calendar days of the date of request any

additional information needed by the department. The department will consider the contractor’s failure to do so as cause for rejection. 104.3.5 Payment 1 The department will use a “Contract Amendment” (Form E-61) to incorporate changes

resulting from an adopted VECP and to authorize payment. Payment will be determined and made as follows:

1.As appropriate, the department will change pay item quantities, add new pay

items, eliminate pay items, or change pay item unit prices, as agreed.

2.The department will pay the contractor 55 percent of the net savings realized,

calculated as the difference between the total contract amount with and without the VECP.

Control of Work

105.1Authority of the Engineer

The engineer will decide all questions regarding the quality and acceptability of materials, work, rate of progress, cooperation between contractors, and interpretation and fulfillment of the contract. The engineer may not pay for work done contrary to the contract or deemed unacceptable. The engineer may change quantities or eliminate pay items as warranted by the project conditions. The engineer does not have authority to amend the contract without implementing a “Contract Amendment” (Form E-61) in accordance with Subsection 104.2, Contract Amendments. 2 The engineer may suspend the work wholly or in part in accordance with Subsection

108.5.2, Engineer-Ordered Suspensions.

105.2Working Drawings

105.2.1 General 1 Provide and submit to the engineer for approval working drawings in sufficient detail to

control and complete the work. Working drawings supplement the contract; their approval does not relieve the contractor of responsibility for completion of the work as specified. The work and costs of preparing and obtaining approval for working drawings is incidental to the related pay items in the contract. 105.2.2 Shop Drawings 1 When specified, the department requires the contractor’s fabricator to submit shop

drawings. Drawings may be sent by email or mail. The Specified Program or Engineer Title Wyoming Department of Transportation 5300 Bishop Boulevard Cheyenne, WY 82009-3340 2 The department requires shop drawings to show dimensions, sizes of materials, and

other information and data necessary to make and erect the work. Provide drawings on paper sized approximately 11 in × 17 in [280 mm × 430 mm]. Submit two complete sets of advance shop drawings for each structure or fabricated item on the project, with any deviation from the contract requirements identified clearly as such. Note any deviation from the contract in the transmittal letter, and forward a copy of the letter to the engineer and the contractor. Ensure that each drawing shows the name of the structure (if applicable), road route, station, Wyoming project number, county, structure number (if applicable), and the department drawing number (if applicable).

Control of Work

Source: Wyoming Standard Specifications for Road and Bridge Construction, 2021 Edition. Pages 00 of 771.