Pay Unit
Measure to the Nearest
Pay to the Nearest
Remove Ped Signal Indication
EA [Ea]
EA [Ea]
EA [Ea]
Reset Ped Signal Indication
EA [Ea]
EA [Ea]
EA [Ea]
Ped Instruction Sign _____
EA [Ea]
EA [Ea]
EA [Ea]
Ped Detector
EA [Ea]
EA [Ea]
EA [Ea]
Louvered Backplate _____ Mast Arm Framework
EA [Ea] EA [Ea]
EA [Ea] EA [Ea]
EA [Ea] EA [Ea]
Post Top Framework Side Bracket Framework
EA [Ea] EA [Ea]
EA [Ea] EA [Ea]
EA [Ea] EA [Ea]
Remove Framework Reset Framework _____Luminaire
EA [Ea] EA [Ea] EA [Ea]
EA [Ea] EA [Ea] EA [Ea]
EA [Ea] EA [Ea] EA [Ea]
Remove _____ Luminaire Reset _____ Luminaire
EA [Ea] EA [Ea]
EA [Ea] EA [Ea]
EA [Ea] EA [Ea]
Saw Cut Loop Detector Prefab Loop Detector Microloop Detector
EA [Ea] EA [Ea] EA [Ea]
EA [Ea] EA [Ea] EA [Ea]
EA [Ea] EA [Ea] EA [Ea]
Microwave Detector Loop Detector Sealant
EA [Ea] GAL [L]
EA [Ea] gal [L]
EA [Ea] GAL [L]
701.5.2 Referenced Sections for Direct Payment 1 The engineer will pay for electrical power from the time of turn-on to the completion
of the contract.
When specified, the engineer will measure and pay for Drilled Shaft Foundations in accordance with Section 506, Drilled Shaft Foundations.
619
Signs, Delineators, and Reference Markers
702.1DESCRIPTION
1 This section describes the requirements for providing and installing permanent roadside
and overhead signs, delineators, and markers.
702.2MATERIALS
1 Provide materials in accordance with the following:
Materials
Subsection
Bolts and Fasteners Delineator Posts Epoxy Mastic Paint Galvanized Coating High-Strength Bolts and Fasteners Overhead Sign Supports Retroreflectors Roadway Sign Supports Timber Sign Posts Sheet Aluminum For Sign Panels Signs and Traffic Devices Structural Steel Retroreflective Sheeting
816.8 816.5 809.10 815.14 815.2 816.7 816.3 816.6 816.10 816.1 816 815.1 816.4
2 For permanent signs, provide sheet aluminum 0.125 in [3 mm] thick.
For main load-carrying tension members at least ½ in [12 mm] thick, provide in accordance with the notch toughness requirements in Subsection 815.1, Structural Steel. 4 The department specifies dimensioned timber posts by nominal sizes and will accept
American Lumber Standard dressed sizes as minimum net sizes.
702.3EQUIPMENT
1 Ensure that the concrete batch plant and mixers meet the requirements of Subsection
513.3, Equipment.
702.4CONSTRUCTION
702.4.1 Reference Markers
Install reference markers at the locations staked.
620
Provide reference post panels
Signs, Delineators, and Reference Markers