Epoxy Resin Injection

627.1DESCRIPTION

1 This section describes the requirements for furnishing and injecting epoxy resin for repairing cracks, delaminations, and voids in portland cement concrete.

627.2MATERIALS

1 Provide materials in accordance with the following:

Materials Subsection Epoxy Resin 810.6

627.3EQUIPMENT

1 Use a handgun or pressure pot for injection. With the engineer’s approval, a machine capable of metering and mixing components to within 1 percent of specified properties and injecting resin may be used. Provide instruments to periodically check nozzle pressure.

627.4CONSTRUCTION

1 Work in accordance with and give the engineer a copy of the epoxy resin manufacturer’s recommendations.

2 During injection, maintain a nozzle pressure of from 10 psi to 25 psi [70 kPa to 170 kPa].

3 Clean repair surfaces of deposits detrimental to adhesion.

4 Alter void areas at the surface as necessary to allow installation of injection ports or tees. Space ports or tees to completely and efficiently fill voids. Once in place, seal the void surface with a fast-setting cement paste mixture or epoxy mortar.

5 After the resin obtains its initial cure, remove ports, tees, and seal without marring the concrete surface. Clean adjacent areas.

627.5MEASUREMENT and PAYMENT

1 The engineer will measure Epoxy Resin Injection as a complete unit, by the gallon [liter], or by the foot [meter]. Measurement by the foot [meter] will be along the surface of the crack, delamination, or void.

Epoxy Resin Injection SECTION 627 2 The department will pay as follows: Pay Item Pay Unit Measure to the Nearest Pay to the Nearest Epoxy Resin Injection GAL, FT, LS [L, m, LS] gal, 0.1 ft, LS [L, 0.05 m, LS] GAL, FT, LS [L, 0.5 m, LS]

Referenced in this section

Get an email when 627 changes

Wyoming revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Wyoming Standard Specifications for Road and Bridge Construction, 2021 Edition. Pages 601–0 of 771. View official source ↗