Highway Monuments
611.1DESCRIPTION
1 This section describes the requirements for furnishing and installing highway monuments.
611.2MATERIALS
1 Provide materials in accordance with the following: Material Subsection Admixtures 801.4 Aggregate for Concrete 803 Curing Materials 802.1 Fly Ash 801.2 Joint Materials 807 Portland Cement 801.1 Reinforcing Steel 811.1 Water 814.1 2 Provide highway monument posts of precast, reinforced concrete with installed pre- approved tablets. 3 Use class B concrete in accordance with Subsection 513.4.4, Mix Design, but with the substitution of type V portland cement. 4 Ensure right angles are fabricated with a ¾ inch [19 mm] chamfer.
611.3EQUIPMENT—V acant
611.4CONSTRUCTION
11.4.1 General 1 Do not remove monuments until approved by the engineer. 2 Notify the engineer seven calendar days prior to commencing the installation of the highway monuments. 3 Coordinate with the engineer so that they are present during the installation of highway monuments.
Highway Monuments SECTION 611 4 Install highway monuments within staked reference points and hold them in true position during placement. Set monuments plumb with the designated post length above ground and backfill firmly tamped into place.
611.5MEASUREMENT and PAYMENT
1 The engineer will measure Highway Monuments by the each. 2 The department will pay as follows: Pay Item Pay Unit Measure to the Nearest Pay to the Nearest Highway Monuments EA [Ea] EA [Ea] EA [Ea]
Get an email when 611 changes
Wyoming revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.