430-1 Description.
Furnish and install drainage pipe and end sections at the locations called for in the Plans. Furnish and construct joints and connections to existing pipes, catch basins, inlets, manholes, walls, etc., as may be required to complete the work. Obtain pipe culverts and drainage products from a plant that is currently on the Department’s Production Facility Listing. Producers seeking inclusion on the list shall meet the requirements of Section 105. At the beginning of each project, submit a notarized certification statement to the Engineer in accordance with Section 6. The Quality Control Manager’s stamp or label on each product indicates certification that the product was fabricated in conformance with the P roducer QC Plan, the Contract, and this Section. Ensure that each shipment of drainage products to the project site is accompanied with a QC signed or stamped delivery ticket providing the description and the list of the products. When the Producer Qualit y Control Program is suspended by the Department, accept responsibility of either obtaining products from a plant with an approved Quality Control Program, or await re -approval of the plant. The Engineer will not allow changes in Contract Time or completio n dates as a result of the plant’s loss of qualification. Accept responsibility for all delay costs or other costs associated with the loss of the plant’s qualification. Construct structural plate pipe culverts or underdrains in accordance with Sections 435 and 440. For pipe culverts installed by jack & bore, install in accordance with Section 556.
430-2 Materials.
430-2.1 Pipe: Meet the following requirements:
Concrete Pipe ................................ ................................ .........Section 449 Steel Pipe ................................ ................................ ...............556-2.1 Round Rubber Gaskets ................................ .......................... Section 942 Resilient Connec tors* ................................ ............................ Section 942 Corrugated Steel Pipe and Pipe Arch ................................ .....Section 943 Corrugated Aluminum Pipe and Pipe Arch ........................... Section 945 Corrugated Polyethylene Pipe ................................ ................ Section 948 Steel Reinforced Polyethylene Ribbed Pipe .......................... Section 948 Steel Reinforced Polyethylene Corrugated Pip e .................... Section 948 Corrugated Polypropylene Pipe ................................ .............Section 948 Corrugated Polyvinyl Chloride (PVC) Pipe .......................... Section 948 Fiberglass Reinforced Polymer Pipe ................................ ......Section 948 Metal Grates ................................ ................................ ...........Section 962 *Use resilient connector products listed on the Department’s Approved Produ ct List (APL).
430-2.2 Joint Materials: Use joint materials specified in 430 -7 through 430 -9 according
to type of pipe and conditions of usage. FY 2023-24 Return to Table of Contents
430-2.3 Mortar: Use mortar composed of one part Portland cement and two parts of
clean, sharp sand, to which mixture the Contractor may add hydrated lime in an amount not to exceed 15% of the cement content. Use mortar within 30 minutes after its preparation.
430-2.4 End Treatments: Meet the requirements of Section 425-3.1. For precast end
treatments, meet the requirements in 449 -1. Use the concrete Class designated in the Plans and Standard Plans, and as specified in Section 346 and 347.
430-2.5 Grates: Use metal grati ngs that meet the requirements of 962 -8.
430-2.6 Filter Fabric: Use a Type D -3 filter fabric meeting the requirements specified in
Section 985, and listed on the Department’s Approved Product List (APL).
430-3 Type of Pipe to be Used.
430-3.1 General: Prior to the preconstruction conference, submit to the Engineer which
optional pipe material from the optional materials tabulation sheet will be used. Once a pipe material is selected, do not change pipe materials without approval of the Engineer. When the Plans designate a type (or types) of pipe, use only the type (or choose from the types) designated. As an exception, when the Plans designate reinforced concrete pipe as Class S, Class I, Class II, Class III and Class IV, the Contractor may use non -reinforced concrete pipe up to and including 36 inch in diameter.
430-3.2 Side Drain: If the Plans do not designate a type (or types) of pipe, the Contractor
may use either a minimum Class I concrete pipe, corrugated steel pipe, corrugated aluminum pipe, corrugated high-density polyethylene pipe, steel reinforced polyethylene ribbed pipe, polypropylene pipe, or PVC pipe. If one of the metal types is chosen, use the minimum gage specified in Section 943 for steel pipe or Section 945 for aluminum pipe. Alternatively, w hen metal pipe is allowed and no future maintenance concerns exist , the Contractor may propose the pipe gage based on the Department’s Drainage Manual and Culvert Service Life Estimator for approval by the Engineer. When extending existing pipes, construct the pipe extensions of the same size and kind as the existing pipe. Extensi ons of existing pipes, whose materials are no longer produced, shall be extended with the most similar pipe material available. Non-reinforced concrete pipe may also be substituted for concrete pipe in side drains, subject to the provisions of 430 -3.1.
430-4 Laying Pipe.
430-4.1 General: Lay all pipe, true to the lines and grades given, with bells upgrade and
spigot end fully entered into the bell. When pipe with quadrant reinforcement or circular pipe with elliptical reinforcement is used, install the p ipe in a position such that the manufacturer’s marks designating “top” and “bottom” of the pipe are not more than five degrees from the vertical plane through the longitudinal axis of the pipe. Do not allow departure from and return to plan alignment and g rade to exceed 1/16 inch per foot of nominal pipe length, with a total of not more than 1 inch departure from theoretical line and grade. Take up and relay any pipe that is not in true alignment or which shows any settlement after laying at no additional e xpense to the Department. Do not use concrete pipe with lift holes except round pipe which has an inside diameter in excess of 54 inches or any elliptical pipe. Repair lift holes, if present, with hand -placed, stiff, non -shrink, 1-to-1 mortar of cement and fine sand, after first washing out the hole with water. Completely fill the void created by the lift hole with mortar. Cover the repaired area with a 24 inch by 24 inch piece of filter fabric secured to the pipe. FY 2023-24 Return to Table of Contents Follow the manufacturer’s instructi ons, to secure the filter fabric to the pipe, until the backfill is placed and compacted. Do not cut or drill into or through the corrugations or ribs of plastic pipe except when necessary to meet the dimensional requirements shown in the Plans. When installing pipes in structures, construct inlet and outlet pipes of the same size and kind as the connecting pipe shown in the Plans. Use the same pipe material within each continuous run of pipe. Extend the pipes through the walls for a distance beyond th e outside surface sufficient for the intended connections, and construct the concrete around them neatly to prevent leakage along their outer surface as shown on Standard Plans, Index 425-001. Keep the inlet and outlet pipes flush with the inside of the wa ll. Resilient connectors as specified in 942 -3 may be used in lieu of a masonry seal. Furnish and install a filter fabric jacket around all pipe joints and the joint between the pipe and the structure in accordance with Standard Plans, Indexes 425-001 and 430- 001. Use fabric meeting the physical requirements of Type D -3 specified in Section 985. Extend the fabric a minimum of 12 inches beyond each side of the joint or both edges of the coupling band, if a coupling band is used. The fabric must have a mini mum width of 24 inches, and a length sufficient to provide a minimum overlap of 24 inches. Secure the filter fabric jacket against the outside of the pipe by metal or plastic strapping or by other methods approved by the Engineer. Meet the following mini mum joint standards: Table 430-1 Pipe Application Minimum Standard Storm and Cross Drains Water-tight Gutter Drain Water-tight Side Drains Soil-tight When rubber gaskets are to be installed in the pipe joint, the gasket must be the sole element relied on to maintain a tight joint. Soil tight joints must be watertight to 2 psi. Water-tight joints must be water -tight to 5 psi unless a higher pressure rati ng is required in the Plans. When laying pipes that pass through mechanically stabilized earth (MSE) reinforced fill , connect the portion of the pipe within the wall to the external portion of the pipe run only after the full height of the wall supported embankment is in place. When Wall Zone Pipes are shown in the Plans, meet the following requirements :
430-4.2 Trench Excavatio n: Excavate the trench for storm and cross drains, and side
drains as specified in Section 125.
430-4.3 Foundation: Provide a suitable foundation, where the foundation material is of
inadequate supporting value, as determined by the Engineer. Remove the u nsuitable material and replace it with suitable material, as specified in 125 -8. Where in the Engineer’s opinion, the removal and replacement of unsuitable material is not practicable, he may direct alternates in the design of the pipeline, as required to provide adequate support. Minor changes in the grade or alignment will not be considered as an adequate basis for extra compensation. Do not lay pipe on blocks or timbers, or on other unyielding material, except where the use of such devices is called fo r in the Plans.
430-4.4 Backfilling: Backfill around the pipe as specified in 125 -8 unless specific
backfilling procedures are described in the Contract Documents.
430-4.5 Plugging Pipe: When existing pipe culverts are to be permanently placed out of
service, fill them with flowable fill that is non -excavatable, contains a minimum 350 pounds per cubic yard of cementitious material and meets the requirements of Section 121 and/or plug them with masonry plugs as shown in the Plans. Install masonry plugs tha t are a minimum of 8 inches in thickness, in accordance with Standard Plans, Index 430-001. When proposed or existing pipe culverts are to be temporarily placed out of service, plug them with prefabricated plugs as shown in the Plans. Install prefabricat ed plugs in accordance with the manufacturer’s recommendations. Do not fill or construct masonry plugs in any pipe culvert intended for current or future service.
430-4.6 End Treatment: Place an end treatment at each storm and cross drain, and side
drain as shown in the Plans. Sod around end treatments in accordance with Standard Plans, Index 570-001.
430-4.6 1 U-Type Concrete Endwalls: Construct in accordance with the Plans
and Standards Plans, Indexes 430-010 through 430 -012 and Index 430-090.
430-4.6 2 Flared End Sections: Construct in accordance with the Plans and
Standard Plans, Index 430-020. Use precast flared end sections only.
430-4.6 3 Mitered End Sections: Construct in accordance with the Plans and
Standard Plans, Indexes 430-021 and 430 -022. Construct mitered end sections for corrugated high-density polyethylene (HDPE) pipe, polypropylene (PP) pipe, steel reinforced polyethylene ribbed (SRPE) pipe and polyvinyl-chloride (PVC) pipe as specified in Section 948 and as detailed in the Standard Plans.
430-4.6 4 Straight and Winged Concrete Endwalls: Construct in accordance
with the Plans and Standard Plans, Indexes 430-030 through 430 -040. Provide end treatm ents for corrugated polyethylene pipe, polypropylene pipe, and PVC pipe as specified in Section 948, or as detailed in the Plans.
430-4.7 Metal Pipe Protection: Apply a bituminous coating to the surface area of the
pipe within and 12 inches beyond the con crete or mortar seal prior to sealing, to protect corrugated steel or aluminum pipe embedded in a concrete structure, such as an inlet, manhole, junction box, endwall, or concrete jacket. Ensure that the surface preparation, application methods (dry film thickness and conditions during application), and equipment used are in accordance with the coating manufacturers’ published specifications. Obtain the Engineer’s approval of the coating products used. FY 2023-24 Return to Table of Contents
430-4.8 Pipe Inspection: For pipes installed under the roadway, inspection is to be
conducted when backfill reaches 3 feet above the pipe crown or upon completion of placement of the stabilized subgrade. For pipe installed within fills, including embankments confined by walls, inspection is to be conducte d when compacted embankment reaches 3 feet above the pipe crown or the finished earthwork grade as specified in the Plans. Prior to conducting the inspection, submit to the Engineer a video recording schedule for videoing, dewater installed pipe, and remov e all silt, debris , and obstructions. Submit pipe videoing and reports to the Department for review prior to the continuation of paving. For pipe 48 inches or less in diameter, submit to the Engineer the video files and reports using low barrel distortion video equipment with laser profile technology, non -contact video micrometer and associated software. For all pipe types, provide a Pipe Observation Summary Report for each pipe run that includes:
430-4.8 1 Video Report: Provide video files via digital media (DVD, flash drive,
or other) or by online digital distribution with a minimum standard resolution of 720 x 480. Use a camera with lighting suitable to allow a clear picture of the en tire periphery of the pipe. Center the camera in the pipe both vertically and horizontally and be able to pan and tilt to a 90 degree angle with the axis of the pipe and rotating 360 degrees. Use equipment to move the camera through the pipe that will not obstruct the camera’s view or interfere with proper documentation of the pipe’s condition. The video image shall be clear, focused, and relatively free from roll, static, or other image distortion qualities that would prevent the reviewer from evaluatin g the condition of the pipe. The video will include identification before each section of pipe filmed. The identification will include the project number, the structure number corresponding to the structure number in the Plans for the project, size of pipe , the date and time, and indicate which pipe is being filmed if multiple pipes are connected to the structure. Notes should be taken during the video recording process. Submit these notes along with the video. Move the camera through the pipe at a speed not greater than 30 feet per minute. Mark the video with the distance down the pipe. The distance shall have an accuracy of one foot per 100 feet. Film the entire circumference at each joint. Stop the camera and pan when FY 2023-24 Return to Table of Contents necessary to document and measure defects. Position the camera head perpendicular to all defects requiring measurement by the video micrometer.
430-4.8 2 Reinspection: At any time after reviewing the submitted pipe
inspection reports, the Engineer may direct additional inspections. If no defects are observed during the reinspection, the Department will pay for the cost of the reinspections in accordance with 4-3. If defects are observed, the reinspection and all work performed to correct the defects will be done at no cost to the Departme nt. Acceptance of all replacements or repairs will be based on video documentation of the completed work prior to Final Acceptance.
430-5 Removing Existing Pipe.
If the Plans indicate that existing pipe is to remain the property of the Department, collect and stack along the right -of-way all existing pipe or pipe arch so indicated in the Plans to be removed, or that does not conform to the lines and grades of the proposed work and that is not to be re-laid, as directed by the Engineer. Take care to prevent damage to salvageable pipe during removal and stacking operations.
430-6 Placing Pipe Under Railroad.
430-6.1 General: Construct pipe culverts under railroad tracks in accordance with the
requirements of the railroad company. Perform all the shoring under the tracks, and sheeting and bracing of the trench, required by the railroad company or deemed necessary by the Engineer in order to ensure safe and uninterrupted movement of the railroad equipment, at no expense to the Depart ment.
430-6.2 Requirements of the Railroad Company: Install pipe using methods required
by the railroad company and shown in the Contract Documents. When the general method of installation required by the railroad company is indicated in the Plans, do n ot alter such method, or any other specific details of the installation which might be indicated in the Plans, without receiving approval or direction from the railroad, followed by written approval from the Engineer.
430-6.3 Notification to Railroad Company: Notify the railroad company and the
Engineer at least ten days prior to the date on which pipe is to be placed under the railroad tracks.
430-6.4 Placing Pipe by Jacking: Obtain the Engineer’s and the railroad company’s
approval of the d etails of the jacking method to be used, when placing pipe through the railroad embankment, before the work is started.
430-6.5 Use of Tunnel Liner: When the railroad company requires that a tunnel liner be
used for placing the pipe in lieu of the jacking method, the Department will pay for the tunnel liner material separately in cases where the Contract Documents do not require the use of a tunnel liner. For these cases the Department will reimburse the Contractor for the actual cost of the liner, deliver ed at the site. The Department will base such cost on a liner having the minimum gage acceptable to the railroad.
430-7 Specific Requirements for Concrete Pipe.
430-7.1 Sealing Joints : Seal the pipe joints with round rubber or profile gaskets meeting
the requirements of Section 449. Ensure that the gasket and the surface of the pipe joint, including the gasket recess, are clean and free from grit, dirt , and other foreign matter, at the time the joints are made. In order to facilitate closure of the joint, application of a vegetable soap lubricant immediately before closing of the joint will be permitted. Prelubricated gaskets may be FY 2023-24 Return to Table of Contents used in lieu of a vegetable soap lubricant when the lubricating material is certified to be inert with respect to the rubber m aterial.
430-7.2 Laying Requirements for Concrete Pipe with Rubber Gasket Joints: Do not
allow the gap between sections of pipe to exceed 5/8 inch for pipe diameters of 12 inches through 18 inches, 7/8 inch for pipe diameters of 24 through 66 inches, and 1 inch for pipe diameters 72 inches and larger. Where minor imperfections in the manufacture of the pipe create an apparent gap in excess of the tabulated gap, the Engineer will accept the joint provided that the imperfection does not exceed 1/3 the circum ference of the pipe, and the rubber gasket is 1/4 inch or more past the pipe joint entrance taper. Where concrete pipes are outside of these tolerances, replace them at no expense to the Department. Do not apply mortar, joint compound, or other filler to t he gap which would restrict the flexibility of the joint.
430-7.3 Field Joints for Elliptical Concrete Pipe: Use either a preformed plastic gasket
material or an approved rubber gasket to make a field joint.
430-7.3 1 Plastic Gasket: Meet the following requirements when field joints are
made from preformed plastic gasket material:
430-7.3 1.1 General: Install field joints in accordance with the
manufacturer’s instructions and the following:
430-7.3 1.2 Material: Meet the requirements of 942 -2.
430-7.3 1.3 Joint Design: Ensure that the pipe manufacturer submits
details to the Engineer regarding configuration of the joint and the amount of gasket material required to affect a satisfactory seal. Do not brush or wipe joint surfaces which are to be in contact with the gasket material with a cement slurry. Fill minor voids with cement slurry.
430-7.3 1.4 Primer: Apply a primer of the type recommended by the
manufacturer of the gasket material to all joint surfaces which are to be in contact with the gasket material, prior to application of the gasket material. Thoroughly clean and dry the surface to be primed.
430-7.3 1.5 Application of Gasket: Apply gasket material to form a
continuous gasket around the entire circumference of the leading edge of the tongue and the groove joint, in accordance with the detail shown on Standard Plans, Index 430-001. Do not remove the paper wrapper on the exterior surface of the gasket material until immediately prior to joining of sections. Apply plastic gasket mater ial only to surfaces which are dry. When the atmospheric temperature is below 60ºF, either store plastic joint seal gaskets in an area above 70ºF, or artificially warm the gaskets to 70ºF in a manner satisfactory to the Engineer.
430-7.3 1.6 Installatio n of Pipe: Remove and reposition or replace any
displaced or contaminated gasket as directed by the Engineer. Install the pipe in a dry trench. Carefully shape the bottom of the trench to minimize the need for realignment of sections of pipe after they are placed in the trench. Hold to a minimum any realignment of a joint after the gaskets come into contact. Prior to joining the pipes, fill the entire joint with gasket material and ensure that when the pipes are joined there is evidence of squeeze -out of gasket material for the entire internal and external circumference of the joint. Trim excess material on the interior of the pipe to provide a smooth interior surface. If a joint is defective, remove the leading section of pipe and reseal the joint.
430-7.3 2 Rubber Gasket: Meet the following requirements when field joints are
made with profile rubber gaskets:
430-7.3 2.1 General: Install field joints in accordance with the
manufacturer’s instructions and the following: FY 2023-24 Return to Table of Contents
430-7.3 2.2 Material: Meet the requirements of 942 -4.
430-7.3 2.3 Joint Design: Ensure that the pipe manufacturer submits
details to the Engineer regarding configuration of the joint and gasket required to effect a satisfactory seal. Do not apply mortar, joint compound, or other fill er which would restrict the flexibility of the gasket joint.
430-7.4 Requirements for Concrete Radius Pipe:
430-7.4 1 Design: Construct concrete radius pipe in segments not longer than
4 feet (along the pipe centerline), except where another length is called for in the Contract Documents. Join each segment using round rubber gaskets. Ensure that the pipe manufacturer submits details of the proposed joint, segment length and shape for approval by the Engineer, prior to manufacture.
430-7.4 2 Pre-Assembly: Ensure that the manufacturer pre -assembles the entire
radius section in his yard, in the presence of the Engineer, to ensure a proper fit for all parts. At the option of the manufacturer, the Contractor may assemble the pipe without gaskets. Consecutively number the joints on both the interior and exterior surfaces of each joint, and make match marks showing proper position of joints. Install the pipe at the project site in the same order as pre -assembly.
430-8 Specific Requirements for Corrug ated Metal Pipe.
430-8.1 Field Joints :
430-8.1 1 General: Make a field joint with locking bands, as specified in
Article 9 — of AASHTO M36 and AASHTO M196M for aluminum pipe. For aluminum pipe,
fabricate bands from the same alloy as the culvert sheeting. When existing pipe to be extended is helically fabricated, make a field joint between the existing pipe and the new pipe using one of the following methods:
430-8.1 2 Side Drain, Storm and Cross Drain, and Gutter Drains: Where
corrugated metal pipe is used as side drain, storm and cross drain, or gutter drain, use a rubber or neoprene gasket of a design shown to provide a joint as specified in 430 -4. Use a gasket of one of the following dimensions:
430-8.1 3 Alternate Joint: In lieu of the above -specified combination of locking
bands and flat gaskets, the Contractor may make field joints for these pipe installations by the following combinations:
430-8.1 3. Use mastic material to seal the area of band overlap.
The minimum joint performance standards specified in 430 -4.1 apply.
430-8.2 Laying and Shape Requirements for Corrugated Metal Pipe: Install pipe
using either a trench or open ditch procedure. Check pipe shape regularly during backfilling to verify a cceptability of the construction method used. Pipe deflected 5% or more of the certified actual mean diameter of the pipe at final inspection shall be replaced at no cost to the Department. Deflection measurements are taken at the point of smallest diamete r on the corrugations.
430-9 Specific Requirements for Steel Reinforced Polyethylene Ribbed Pipe, Corrugated
High-Density Polyethylene Pipe, Polypropylene Pipe, and Polyvinyl Chloride (PVC) Pipe.
430-9.1 Sampling Requirements: Submit a sample of each pipe material and diameter
used on each project to the Engineer a minimum of two weeks prior to the installation, provided that the pipe meets all of the following:
430-9.2 Field Joints: Use gasketed joints to seal side drain, and storm and cross drain.
Use gaskets meeting the requirements of Section 449. Ensure that the pipe manufacturer provides a joint design approved by the Engineer before use.
430-9.3 Installation Requirements Including Trenching, Foundation and Backfilling
Operations: Check structure shape regularly during backfilling to verify acceptability of the construction method used. Replace pipe deflected 5% or more of the certified actual mean diameter of the pipe at final inspection at no cost to the Department.
430-10 Desilting Pipe or Concrete Box Culvert.
Desilt pipe culvert and concrete box culvert as des ignated in the Plans.
430-11 Method of Measurement.
430-11.1 New Pipe Installed by Excavation or Trenching: The quantity of storm and
cross drain pipe, storm drain trench, side drain and gutter drain pipe, installed by pipe culvert optional material - excavation or trenching, to be paid for will be plan quantity, in place and accepted. The plan quantity will be determined from the inside wall of the structure and from station/offset location for end treatments as shown in the Plans, along the centerline of the pipe. Adjustment to bid quantities, prices and payment will not be allowed for increases, decreases , or changes in material or installation requirements due to the use of any optional pipe materials. If adjustments are required due to Plan errors or omissions or authorized field changes, the plotted material and not the material elected would be used to establish new pay quantities. Pipe sizes other than round (elliptical/arch) are summarized and paid for using equivalent round pipe diameter.
430-11.2 New Pipe Installed by Jack & Bore: The quantity of storm and cross drain
pipe, storm drain trench, side drain and gutter drain pipe, installed by pipe culvert optional material - jack & bore, to be paid for will be the plan quantity, in place and accepted. The measurement and payment will be the plan quantity length of the casing or carrier pipe installed by jack & bore. Carrier pipe installed through/inside the casing is paid for as pipe culvert optional material – excavation or trenc hing.
430-11.3 End Treatment : The quantity of all end treatments to be paid for will be the
number completed and accepted. For mitered end sections , the measurement will be per each end of pipe. Sod will be paid for in accordance with Section 570.
430-12 Basis of Payment.
430-12.1 General: Prices and payments will be full compensation for all work specified
in this Section, including all excavation except the volume included in the items for the grading work on the project, and except for other items spec ified for separate payment in Section 125; all backfilling material and compaction; disposal of surplus material; and all clearing and grubbing outside of the required limits of clearing and grubbing as shown in the Plans. No separate payment will be mad e for bituminous coating, concrete collars, or concrete jackets. No payment will be made for failed bore paths, injection of excavatable flowable fill, products taken out of service, or incomplete installations. Payment will include all work and FY 2023-24 Return to Table of Contents materials necessary for jack & bore, including boring, backfilling, flowable fill, and restoration materials necessary for a complete and accepted installation. No payment will be made for jack & bore until a Bore Path Report has been submitted to the Engineer.
430-12.2 Removing Existing Pipe: When existing pipe is removed and replaced with
new pipe approximately at the same location, the cost of excavating and removing the old pipe and of its disposal will be included in the Contract unit price for clearing and grubbing.
430-12.3 Site Restoration: The cost of restoring the site, as specified in 125 -11, that is
disturbed, solely for the purpose of constructing pipe culvert, will be included in the Contract unit price for the pipe culvert, unless designated speci fically to be paid for under other items.
430-12.4 Plugging Pipes: The cost of temporarily plugging a pipe culvert, either
proposed or existing, will be incidental to the contract unit price for new pipe culvert. The cost of filling and/or plugging an e xisting pipe culvert that is to be permanently placed out of service will be paid for at the contract unit price for filling and plugging pipe, per cubic yard. Price and payment will be full compensation for flowable fill, masonry, concrete, mortar, and al l labor and materials necessary to complete the work. When the project includes no quantities for new pipe culverts, and temporary plugs are required for existing pipe culverts, the cost will be considered as extra work, in accordance with 4 -3.5.
430-12.5 Desilting Pipe: Desilting pipe will be paid for at the contract unit price per foot
for each pipe desilted. Price and payment will be full compensation for furnishing all equipment, tools and labor, disposal of silt and debris, and all incidentals neces sary for satisfactorily performing the work.
430-12.6 Desilting Concrete Box Culverts: Price and payment will be full
compensation for all work required.
430-12.7 Flared End Sections: Price and payment will be full compensation for all
concrete, reinforc ement, toe walls, and all work and materials required.
430-12.8 Mitered End Sections: Price and payment will be full compensation for all
materials, pipe, grates when required, fasteners, reinforcing, connectors, anchors, concrete, sealants, jackets and coupling bands, and all work required.
430-12.9 U-Type Endwalls : Price and payment will be full compensation for all
materials concrete, reinforcement, grate, baffles, accessories , and all work required. Fencing, when called for in the Plans, will be paid for under Fencing, Type B, per foot. Rip rap will be paid for in accordance with Section 530.
430-12.10 Straight and Winged Endwalls : Price and payment will be full compensation
for all concrete, reinforcement, grate, accessories , and all wor k and materials required.
430-12.11 Railroad Requirements: Where pipe culvert is constructed under railroad
tracks, the Contract unit price for the pipe culvert will include the costs of any jacking operations and the operation of placing the pipe by use of a tunnel liner, (except as specified for unanticipated tunnel liner, in 430 -6.5, where reimbursement is to be made for such unanticipated liner), and all other work necessary to meet the requirements of the railroad company, excluding the costs of watch man or flagman services provided by the railroad company, except as provided below. The Department will reimburse the Contractor for the actual costs of any trestle bridge work which is performed by the railroad’s forces, as billed to him by the railroad , less the value of any salvage materials derived there from, whether such salvage materials are retained by FY 2023-24 Return to Table of Contents the railroad company or by the Contractor. When the work of shoring and bracing is to be performed by the railroad, such fact will be stipulated in the Contract Documents and the Contractor will be required to pay to the railroad the amount of such costs, which amount will be reimbursed to him by the Department. The Contract unit price for the pipe culvert shall include the costs of all other work of shoring and bracing.
430-12.12 Payment Items: Payment will be made under:
Item No. 430 - 17- Pipe Culvert Optional Material - Excavation or Trenching - per foot. Item No. 430 - 18- Pipe Culvert Optional Material - Jack & Bore - per foot. Item No. 430 - 94- Desilting Pipe - per foot. Item No. 430 - 96- Polyvinyl Chloride Pipe - per foot. Item No. 430 - 98- Mitered End Section - each. Item No. 430 -200- Flared End Sections - each. Item No. 430 -400- Winged Concrete Endwalls - each. Item No. 430 - 5- Straight Concrete Endwalls - each. Item No. 430 - 6- U-Type Concrete Endwalls - each. Item No. 430 -830- Filling and Plugging Pipe - cubic yard. Item No. 430 -950- Desilting Concrete Box Culvert - per cubic yard. FY 2023-24 Return to Table of Contents SECTION 431 PIPE LINER
431-1 Description.
Rehabilitate drainage pipe by installing a pipe liner in accordance with the requirements of this Section. The Plans will indicate the location of the pipe to be rehabilitated, the material composition and the alternate liner types that may be used to reha bilitate the pipe, and the method of liner installation.
431-2 Materials.
Meet the requirements of Section 948.
431-3 Pre-installation Requirements.
Prior to installing the pipe liner, inspect the host pipe and ensure that it is clean, dry and stable. Inspect the host pipe by means of closed circuit television. The closed circuit television inspection may be augmented by a visual inspection in which persons enter a host pipe to inspect it, at no additional cost to the Department. Obtain written approval f rom the Engineer prior to allowing persons to enter a host pipe. Furnish all equipment necessary to inspect, remove silt and other debris, and dewater the host pipe to the satisfaction of the Engineer. Seal cracks and joints using an approved chemical grou t of either acrylamide base gel, acrylic base gel, urethane base gel, or urethane base foam. Place flowable fill as directed by the Engineer to maintain the stability of the host pipe.
431-4 Installation Methods.
431-4.1 General: Install the liner using o ne of, or a combination of, the following
methods: sliplining, inverting, pulling/pushing, spiral winding, paneling, coating, or bursting. Seal or grout the annular space between the interior of the host pipe and the exterior of the liner according to the liner manufacturer’s written instructions.
431-4.2 Sliplining: Use either polyethylene, high density polyethylene, polyvinyl
chloride, fiberglass, steel or aluminum pipe liner. Install the liner by joining discrete lengths, panels or segments of the pipe liner in a manhole or other access point and inserting the liner into the host pipe.
431-4.2 1 Polyethylene: Install polyethylene pipe liner in accordance with
ASTM F585. The manufacturer’s written instructions may be substituted for ASTM F585 with written permission from the Engineer.
431-4.2 2 High Density Polyethylene: Install high density polyethylene pipe
liner in accordance with ASTM F585. The manufacturer’s written instructions may be substituted for ASTM F585 with written permission from the Eng ineer.
431-4.2 3 Polyvinyl Chloride: Install polyvinyl chloride pipe liner in accordance
with ASTM F1698.
431-4.2 4 Fiberglass, Steel or Aluminum: Install fiberglass, steel or aluminum
pipe liner in accordance with the manufacturer’s written instructio ns.
431-4.2 5 Steel Reinforced Polyethylene Ribbed Pipe: Install reinforced pipe
liner in accordance with ASTM F585. The manufacturer’s written instructions may be substituted for ASTM F585 with written permission from the Engineer.
431-4.3 Inverting: Install a resin impregnated felt tube pipe liner into the host pipe, and
cure in place, in accordance with ASTM F1216. FY 2023-24 Return to Table of Contents