General Provisions (00100-00999)

623MONUMENTS

ME · 2020 Standard SpecificationsBook pages 551552View official source ↗

6-81

625.02 Materials Materials shall meet the requirements specif ied in the following

Sections of Division 700 - Materials: Copper Tubing 712.32 Non-metallic Pipe, Flexible 712.33 Non-metallic Pipe, Rigid 712.34 Metallic Pipe 712.341

625.03 General This work shall be done with as little interru ption of water service

as possible. Ample notification shall be given to the users of the water before any disruption of water service.

625.04 Sleeve Pipe for sleeves shall be metallic or non-metal lic rigid and be laid on

a firm foundation at the line and grade designated. When the p ipe installation is in a trench all excavating and backfilling shall be in accordance with Sect ion 206 - Structural Excavation. After installation of the pipe, special care shall be taken to protect the pipe from heavy hauling equipment loads, rocks or any other damage caused by the Contractor's work. All pipe broken from such causes shall be removed and replaced at the Contractor's expense. Pipe sleeves to be placed in concrete shall be supported durin g placement of concrete. Special care shall be taken while placing and compac ting concrete around the sleeves to prevent voids around t he outside of the sleeves. En ds of the sleeves shall be capped with end plates until the water pipes are installed thro ugh the sleeves.

625.05 Water Pipe Water pipe shall be copper tubing or non-me tallic flexible pipe,

as called for. After the sleev e has been placed, the water pip e shall be inserted into the sleeve and connected to the existing pipes at each end. All co nnections to existing pipes shall be done in accordance with recognized plumbing practices. Necessary fittings, adapters, and reducers shall be furnished a s required.

625.06 Method of Measurement Pipe sleeve, copper tubing, and non-metallic pipe

will be measured by the linear foot.

625.07 Basis of Payment The accepted quantities of pipe sleev e, copper tubing and

non-metallic pipe will be paid for at the contract unit price p er linear foot for the types and sizes specified complete in place, which payment will be compen sation for furnishing and installing all necessary fittings, for connecting to existing s ystems and for capping the ends of the pipe sleeve. Excavation will not be paid for separately but will be conside red included in the work of the contract items. Payment will be made under: 6-82 Pay Item P a y U n i t 625.081 ¾ inch Copper Tubing Linear Foot 625.082 1 inch Copper Tubing Linear Foot 625.083 1¼ inch Copper Tubing L i n e a r F o o t 625.084 1½ inch Copper Tubing Linear Foot 625.085 1¾ inch Copper Tubing L i n e a r F o o t 625.086 2 inch Copper Tubing Linear Foot 625.101 ¾ inch Non-metallic Pipe-Flexible Linear Foot 625.102 1 inch Non-metallic Pipe-Flexible L i n e a r F o o t 625.103 1¼ inch Non-metallic Pipe-Flexible Linear Foot 625.104 1½ inch Non-metallic Pipe-Flexible L i n e a r F o o t 625.105 1¾ inch Non-metallic Pipe-Flexible L i n e a r F o o t 625.141 2 inch Pipe Sleeve Linear Foot 625.142 3 inch Pipe Sleeve Linear Foot 625.143 4 inch Pipe Sleeve Linear Foot 625.144 6 inch Pipe Sleeve Linear Foot 625.145 8 inch Pipe Sleeve Linear Foot SECTION 626 - FOUNDATIONS, CONDUIT , AND JUNCTION BOXES FOR HIGHWAY SIGNING, LI GHTING, AND SIGNALS

626.01 Description This work shall consist of furnishing, ins talling, modifying, or

removing concrete foundations, conduits, and junction boxes for highway lighting, traffic signals, and highway signing in accordance with these Specifica tions and in reasonably close conformity with the Contract Documents.

626.02 Materials The materials furnished by the Contractor sh all be new. Where an

existing system is to be modified, the existing material shall be removed and abandoned or salvaged as shown in the Contract Documents or as directed by t he Resident. All electrical equipment shall conform to NEMA or UL standards, wherever applicable. In addition to these requirements, all materials and workmanshi p shall conform to the requirements of: NEC, ASTM Standa rds, the ANSI, the local elect rical Utility Company, and any local ordinances that may apply. Materials shall meet the requirements specified in the followin g Sections of Division 700, Material Details. G r a v e l B o r r o w 703.20 Reinforcing Steel 709.01 Precast Concrete Units 712.06

Source: Maine Standard Specifications for Road and Bridge Construction, 2020 Edition. Pages 551552 of 817.