B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Legal Relations and Responsibility to the Public

1712Protection and Restoration of Property

MN · 2025 Standard Specifications✓ Full text on BuildSpecBook pages 83–0 Save this section

Ask about Section 1712

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

1712.1PROPERTY

The Contractor is responsible for the preservation of all public and private property of any character in performing the Work. A Monuments The Contractor shall preserve all land and property corner monuments, R ight-of-way monuments, and vertical and horizontal control point monuments indicated in the Contract or provided in writing by the Engineer before the start of Work in the vicinity of the monument . If the Engineer determines that a monument designated for preservation was disturbed during construction A ctivities, the Department will deduct a charge of $1,000.00 per monument from the moneys due or becoming due the Contractor. The Engineer will determine the number of monuments disturbed or destroyed by the Contractor. If the Engineer determines that a monument requires removal to allow construction, the Department will not deduct the charge of $1,000.00 per monument from moneys due or becoming due the Contractor.

1712.2ADVANCE NOTICE

The Contractor shall give advance notice to the owners of all private property where the Contractor’s operations will interfere with the property. The notice shall advise the private property owners of the nature of the interference and indicate the Contractor’s intention to arrange for the protection of their property.

1712.3GENERAL LIABILITY

The Contractor is responsible for all damages to property of any character, resulting from any act, omission, neglect, or misconduct in the execution or non-execution of the Work. The Contractor will not be responsible for property within the Project Site if both of the following conditions are met:

(1)The Contract did not specify the existence and approximate location of the underground

property

(2)The Contractor fulfilled its obligations under Minnesota Statutes, Chapter 216D

The Contractor shall restore property damaged by the Contractor’s act, omission, neglect, or misconduct to a condition equal to or better than that existing before the damage occurred by repairing, rebuilding, replacing the property, or otherwise correcting the damage to the s atisfaction of the Engineer, at no additional cost to the Department. Denial of a claim by the Contractor’s insurance carrier does not relieve the Contractor of its obligations in this regard.

Get an email when 1712 changes

Minnesota revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Minnesota Standard Specifications for Construction, 2025 Edition. Pages 83–0 of 1,081. View official source ↗

Ask about this section

Scoped to Minnesota 2025 Standard Specifications for Construction, Section 1712 — Protection and Restoration of Property. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.