Legal Relations and Responsibility to the Public

1715Opening Sections of the Roadway to Traffic Before Completion of the Project

MN · 2025 Standard Specifications✓ Full text on BuildSpecBook pages 87–0 Save this section

Ask about Section 1715

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

The requirements of this section shall not relieve the Contractor of obligations for maintenance of traffic over Roads undergoing improvements, as specified in 1404, “Maintenance of Traffic.” Opening of a section of the Roadway to traffic shall not constitute acceptance of the incomplete portions of the Project, nor shall opening a section of the Roadway to traffic before the completion of the entire Contract waive any provisions of the Contract. The Special Provisions may require, or the Engineer may direct, the Contractor to open sections of the Roadway to traffic before the completion of that section or the entire Project. When the Contractor is required to do so, the following applies:

(1)On sections of the Roadway that the Department requires the Contractor to open to

traffic before completion of the entire Project, the Department will relieve the Contractor of any expense for actions required under 1404, “Maintenance of Traffic.” The Contractor is responsible for repair of damage to the Work not attributable to traffic. The Contractor must perform Highway maintenance work in accordance with 1514, “Maintenance During Construction.”

(2)If a section of the Roadway is opened to traffic as directed by the Engineer, for

unforeseen reasons not the fault of the Contractor, the Department will pay the Contractor for additional expenses incurred in completing the remaining Work under traffic. The Department may extend the Contract Time, if justified, with a Change Order executed in advance of the traffic opening, describing the agreed conditions.

(3)If a section of the Roadway is opened to traffic before its completion, as a requirement

of the Contract or as directed by the Engineer as a result of failure or negligence by the Contractor, the Contractor shall perform remaining construction operations with the least possible obstruction to traffic. The Department will not provide the Contractor any additional compensation or extension of time due to increased costs or changed working conditions resulting from opening the Road to traffic before its co mpletion.

Get an email when 1715 changes

Minnesota revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Minnesota Standard Specifications for Construction, 2025 Edition. Pages 87–0 of 1,081. View official source ↗

Ask about this section

Scoped to Minnesota 2025 Standard Specifications for Construction, Section 1715 — Opening Sections of the Roadway to Traffic Before Completion of the Project. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.