1716Contractor’s Responsibility for Work

MN · 2025 Standard Specifications✓ Full text on BuildSpecBook pages 88–0 Save this section

Ask about Section 1716

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

The Contractor is responsible for the Work until the Engineer issues P roject acceptance in writing under 1516.2, “Project Acceptance.” The Contractor shall protect the Work against injury or damage from weather or other causes arising from the execution or non-execution of the Work. The Contractor shall rebuild, repair, and correct injuries or damage to the Work at no additional cost to the Department before the Engineer will accept the Project under 1516.2, “Project Acceptance,” unless either of the following is true:

(1)The Contract specifies otherwise
(2)The damage to the Work was caused by unforeseeable causes beyond the control of

and without the fault or negligence of the Contractor, including acts of God such as earthquake, tidal wave, flood, tornado, hurricane, other cataclysmic phenomenon of nature, or acts of a public enemy or of governmental authorities If the Engineer suspends the Work, the Contractor shall perform the following functions at no additional cost to the Department:

(1)Take precautions to prevent damage to the Project
(2)Provide for normal drainage in accordance with 2573, “Storm Water Management,” and

2574.5C, “Establishing Vegetation and Controlling Erosion”

(3)Erect necessary temporary Structures, signs, or other facilities in accordance with 1404,

“Maintenance of Traffic,” and 1710, “Traffic Control Devices”

(4)Take precautions to protect new tree growth and other vegetative growth against injury

as specified in 2571, “Plant Installation and Establishment,” 2572, “Protection and Restoration of Vegetation,” and 2574.5C, “Establishing Vegetation and Controlling Erosion” If the Contractor fails to comply with these provisions, the Engineer will notify the Contractor in writing of the unacceptable Work. If the Contractor fails to take action as directed by the Engineer, the Department may have the Work performed by others and will deduct the costs for this Work from moneys due the Contractor under this Contract or any other Contract with the Department.

Get an email when 1716 changes

Minnesota revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Minnesota Standard Specifications for Construction, 2025 Edition. Pages 88–0 of 1,081. View official source ↗

Ask about this section

Scoped to Minnesota 2025 Standard Specifications for Construction, Section 1716 — Contractor’s Responsibility for Work. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.