125 The removal and disposal of slide and slipout material in accordance with Subsection
207.14 will be paid for at the contract price for "Unclassified Excavation", unless the Engineer,
prior to the removal of such material, orders the slide or slipout material to be removed and disposed of as "Extra Work", or the Contractor, prior to perform ing any such work, requests in writing that the removal and disposal of any such slide or slipout material be paid for as "Extra Work", and the Engineer approves. The cost of any work outside the limits of the slide necessary to make slide or slipout area s accessible to normal excavation equipment will be paid for as "Extra Work". The above provisions shall not be so construed as to relieve the Contractor from the duty of maintaining all slopes true and smooth. The quantity of subgrade work done under thi s item will be the number of cubic yards of "Subgrade" established in the Proposal, subject to adjustment as provided for in Subsection s 104.2 and 109.2. Any additional work beyond the scope of the original Plans but authorized by the Engineer will be mea sured in cubic yards, compacted in place, and paid for at the unit bid price for subgrade, subject to the provisions of 104.2. The quantity of subgrade work done under Item 207002 -* will be the number of cubic yards measured and compacted in place, subje ct to adjustment as provided for in 104.2 and 109.2. Any additional work beyond the scope of the original Plans but authorized by the Engineer will be measured in cubic yards, compacted in place, and paid for at the unit bid price for subgrade. Measureme nt and payment for subgrade drains will be in accordance with the provisions of Section 606.
207.16 Basis of Payment :
The quantities, determined as provided above, will be paid for at the contract unit prices bid for these items, which prices and payments shall be full compensation for doing all the work prescribed in a workmanlike and acceptable manner, including all labor, tools, equipment, supplies, and incidentals necessary to complete the work . The cost of unclassified excavation including the hauling of all material, any reserving and rehandling of unclassified excavation material, embankment construction including compaction, furnishing and applying water as an aid to embankment compaction, and the cost of furnishing additional waste sites, grading, fertilizing, and seeding and mulching of all waste sites, shall be included in the unit price bid for "Unclassified Excavation". The cost of furnishing all materials, including furnishing and app lying water necessary as an aid to subgrade compaction, shall be included in the unit price bid for "Subgrade".