3878.1SCOPE

Provide sod for turf establishment, erosion control, energy dissipation of low flow water outfalls, river banks, and channel bottoms.

3878.2REQUIREMENTS

Provide sod consisting of densely-rooted bluegrass or other permanent grasses and flowers, depending on sod type shown on the Plans. Provide Material from vendors on the APL.

Cut turf-type sod in uniform strips at least 12 inches wide and 3/4 inches thick. Cut the sod thicker to retain and expose the dense root system in the bottom side of the sod . Cut the sod when it contains sufficient moisture to withstand exposure and handling during the transplant operations . Rake the sod free of debris and trim the top growth to a height from 1 inch to 3 inches. Do not use sod strips with dry or dead edges upon delivery. Between June 1 and September 15, do not cut sod more than 24 hours before delivery. Provide native sod in the dimensions specified in the Plans or by the manufacturer’s recommendations for handling immediately before installation. Before delivery, provide certification from the grower to the Engineer stating the grass varieties contained in the sod. Do not place sod until the Engineer approves the certification. Provide salt tolerant and the netted sods from certified growers as defined by the Minnesota Crop Improvement Association and the Office of Environmental Services. The Engineer will require certification of conformance based on third -party inspection and documentation process for all Material from certified growers. A Lawn Sod Provide lawn sod meeting the following requirements and characteristics:

(1)Soil is moist
(2)Uniform texture
(3)Dark green
(4)Maximum grass blade widths 0.2 inch
(5)Weed-free
(6)Maximum thatch thickness 0.2 inch over the base soil
(7)Consists of a blend of 4 or 5 fine leafed turf grasses
(8)At least two-thirds of the grasses, as determined by initial seeding proportions, consist

of improved and elite type Kentucky bluegrass varieties as specified in the Seeding Manual B Salt Tolerant Sod Provide salt-tolerant sod for use along boulevards or in a potential salt environment meeting the following requirements and characteristics:

(1)Low maintenance type
(2)Fine leafed
(3)Uniform texture
(4)Free of noxious, broad-leafed, and grassy weeds
(5)Contains less than 3 percent coarse grasses
(6)Originated from the blend of grass seed of seed components listed by the Minnesota

Crop Improvement Association, Minnesota Turf Association, and the Office of Environmental Services C Mineral Sod Provide mineral sod meeting the following requirements and characteristics:

(1)Commercially produced on or harvested from mineral based soils consisting of no

greater than 10 percent organic matter by weight

(2)Fine leafed
(3)Uniform texture
(4)Free of noxious, broad-leafed, or grassy weeds
(5)Contains less than 3 percent coarse grasses
(6)Consists of a blend of 4 or 5 fine leafed turf grasses
(7)At least 35 percent of the grasses, as determined by initial seeding proportions, consist

of improved type Kentucky bluegrass varieties as specified in 3876, “Seed” D Native Sod Provide native sod meeting the following requirements:

(1)Commercially produced from native grass and flower seed mixtures per 3876, “Seed,”

and as shown on the Plans

(2)Seeded and grown in turf reinforcement mats or natural organic mats for at least

30 Calendar Days before delivery and installation

3878.3SAMPLING AND TESTING

The Engineer will obtain test samples for determination of soil organic matter content of mineral sod from the soil exposed in the bottom side of the sod rolls. The Engineer will test for organic matter content meeting the requirements of ASTM D2974, Standard Test Methods for Moisture, Ash, and Organic Matter of Peat and Other Organic Soils. The Department may conduct its own inspection during sod production in the fields or at the Project. Provide representative samples of the sod to the Engineer if requested . Do not deliver sod until the Engineer approves the samples.

Get an email when 3878 changes

Minnesota revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Minnesota Standard Specifications for Construction, 2025 Edition. Pages 1047–0 of 1,081. View official source ↗

Ask about this section

Scoped to Minnesota 2025 Standard Specifications for Construction, Section 3878 — Sod. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.