3879.1SCOPE

Provide agricultural liming material (ALM) containing calcium compounds, magnesium compounds, or both, capable of neutralizing soil acidity and providing an increase in soil pH within six months of placement into the soil.

3879.2REQUIREMENTS

ALM includes the following forms:

(1)Limestone (calcite or dolomite)
(2)Burned lime
(3)Slaked lime
(4)Marl

Gypsum is not a liming product. Provide lime product containing at least 80 percent total neutralizing power (TNP) ground fine to provide the following characteristics:

(1)At least 90 percent, including fine particles obtained in the grinding process, passes

through a No. 8 Sieve

(2)At least 60 percent passes through a No. 20 Sieve
(3)At least 50 percent passes through a No. 60 Sieve
(4)A maximum water content of 10 percent
(5)ALM with a rating of at least 1,000 pounds effective neutralizing power (ENP) per ton of

ALM Obtain the ALM from a Minnesota Department of Agriculture (MDA) licensed distributor or producer. For ALM supplied in bulk, deliver the ALM to the Project with the following information on a billing, delivery invoice, or Scale ticket label:

(1)Distributor or producer’s name, address, telephone number, and source of production

or stockpile location

(2)Customer’s name
(3)Date of sale or transfer
(4)T ype of ALM
(5)Minimum weight in pounds of ENP per ton, accurate within 3 percent
(6)Weight or cubic yards of ALM distributed and weight per cubic yard

For ALM supplied in bags or other container types, affix the following information to the bag or container:

(1)Distributor or producer’s name and address
(2)Minimum weight in pounds ENP per ton, accurate to within 3 percent
(3)The net weight

3879.3SAMPLING AND TESTING

Collect samples in accordance with the MDA Agricultural Lime Official Sampling Methods . Submit samples to MDA or the University of Minnesota testing lab for analysis of the following:

(1)Percent of TNP
(2)Percent passing the No. 8 Sieve, No. 20 Sieve, and No. 60 Sieve
(3)Percent dry matter
(4)The weight in pounds ENP per ton of ALM rating

Perform sampling and testing within 90 Calendar Days before applying the lime Material to the land. The weight in pounds ENP per ton of ALM is defined as follows: ( ) T WPDMENPton lb =

000 , 2

When: ENP =

×

%

TNPFI

Fineness Index (FI) = 0.2(%𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝. 8 − %𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝. 20) + 0.6(%𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝. 20 − %𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝. 60) + 1(%𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝. 60) PDM = percent dry matter = 100 − percent moisture W = weight, pounds (lb) ENP T = Ton of ALM The Engineer may accept Material provided in accordance with this section, on the basis of the distributor’s or producer’s guaranteed analysis. The Department reserves the right to sample, test, inspect, and accept or reject the Material based on its own tests.

Get an email when 3879 changes

Minnesota revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Minnesota Standard Specifications for Construction, 2025 Edition. Pages 1049–0 of 1,081. View official source ↗

Ask about this section

Scoped to Minnesota 2025 Standard Specifications for Construction, Section 3879 — Agricultural Lime. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.