ROADSIDE DEVELOPMENT

861CLEANING SEDIMENTATION STRUCTURES

PA · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 793–0 Save this section

Ask about Section 861

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

861.1DESCRIPTION —This work is removal and disposal of sediment deposited in erosion and

sedimentation control structures and/or devices.

861.3CONSTRUCTION—Install cleanout stakes near the center of sediment trap and/or sediment basin

as indicated or directed. When sediment accumulation has reached the associated cleanout elevations indicated on plans and as directed, remove and dispose of the sediment. Do not damage the structure or device. Maintain or replace cleanout stake as required, as indicated, or as directed.

861.4MEASUREMENT AND PAYMENT—Cubic Yard

The sediment removed will normally be measured by the number of full loads hauled multiplied by the rated capacity of the hauling equipment, in cubic yards. Cross -sectional measurements will be used for large quantities and when not using hauling equipment.

Get an email when 861 changes

Pennsylvania revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Publication 408 Highway Construction Specifications, 2026 Edition. Pages 793–0 of 1,522. View official source ↗

Ask about this section

Scoped to Pennsylvania Publication 408 — Specifications, Section 861 — CLEANING SEDIMENTATION STRUCTURES. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.