861.1DESCRIPTION —This work is removal and disposal of sediment deposited in erosion and
sedimentation control structures and/or devices.
861.3CONSTRUCTION—Install cleanout stakes near the center of sediment trap and/or sediment basin
as indicated or directed. When sediment accumulation has reached the associated cleanout elevations indicated on plans and as directed, remove and dispose of the sediment. Do not damage the structure or device. Maintain or replace cleanout stake as required, as indicated, or as directed.
861.4MEASUREMENT AND PAYMENT—Cubic Yard
The sediment removed will normally be measured by the number of full loads hauled multiplied by the rated capacity of the hauling equipment, in cubic yards. Cross -sectional measurements will be used for large quantities and when not using hauling equipment.