801STOCKPILING TOPSOIL OR TOPSOIL MIXTURE

PA · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 726–0 Save this section

Ask about Section 801

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

801.1DESCRIPTION—This work is separation and salvaging of topsoil or topsoil mixture encountered in

grading the project and depositing it in stockpiles at locations within the right of way.

801.2MATERIAL—

(a)Topsoil. Acceptable friable loam that is reasonably free of subsoil, clay lumps, brush, roots, weeds,

other objectionable vegetation, stones, other foreign material larger than 2 inches in any dimension, litter, and/or other material unsuitable or harmful to plant growth.

(b)Topsoil Mixture. Designated top 8 inches of existing soil collected and combined with organic plant

matter such as vegetative slashings consisting of crushed or shredded branches, stems, bark, leaves, seeds, and roots.

801.3CONSTRUCTION—

(a)Topsoil. After clearing and grubbing the area and before starting other construction operations,

remove topsoil from areas, as indicated or directed. Adjust equipment and methods of operation to avoid mixing subsoil with topsoil. Separate the topsoil from other excavated material and stockpile at acceptable locations within the right of way. Do not compact and do not stockpile topsoil in a wet or frozen condition. Satisfactorily and uniformly grade stockpiled topsoil not required for the project. Apply seeding and soil supplements to these stockpiles, using the formula, as directed, and apply, as specified in Section 804.3. Apply mulch of the type directed, on the stockpiles, as specified in Section 805.3.

(b)Topsoil Mixture. During clearing and grubbing operations and before other construction operations,

shred all designated vegetation under 4 inches caliper in size using a crawler or loader mounted, self - powered, land clearing shredder capable of shredding vegetation to a desired maximum rough size of 12 inches long and 2 inches in diameter. Collect and mix the organic slashings with the top 8 inches of soil to be salvaged, as indicated, or directed. Stockpile topsoil mixture at acceptable locations within the right of way. Do not compact material. Periodically water stockpile as directed.

801.4MEASUREMENT AND PAYMENT—

Stockpiled topsoil and topsoil mixture is incidental to Clearing and Grubbing, Excavation, and Borrow Excavation.

Get an email when 801 changes

Pennsylvania revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Publication 408 Highway Construction Specifications, 2026 Edition. Pages 726–0 of 1,522. View official source ↗