872.3 872.4(n) • Temporary Sediment Basin: Fill in excavated areas, removing embankments, riser pipe assemblies, corrugated metal pipe, and anti -seep collars , or as directed . Restore the areas as specified in Section
105.14. Satisfactorily dispose of removed materials
• Sediment Basin located in a Permanent Stormwater Management Basin area: Remove accumulated sediment and restore basin to final contouring as indicated, stabilize disturbed areas as indicated, remove temporary orifice covers, temporary standpipes , affix permanent stormwater management features as specified in Section 875.3, as indicated, or as directed. Sat isfactorily dispose of removed materials.
872.4MEASUREMENT AND PAYMENT —
For the type indicated .
For the type indicated.
For the type indicated.
For the type indicated.
For the type indicated.
Section 850.4
Section 212.4
873.1 873.4
873.1DESCRIPTION —This work is construction , maintenance, and removal of a temporary baffle wall .
873.2MATERIAL —
specified in Section 106.03(b)3.
Pressure Treated wood. Certify as specified in Section 106.03(b)3.
873.3CONSTRUCTION —As shown on the Standard Drawings , and as follows:
Place the pressure treated posts and fasten plywood sheets as indicated and directed. Drive posts and plywood to minimum dimensions indicated to e nsure flow is diverted along the length of the baffle. Clean the baffle as necessary to e nsure adequate flow is maintained during all construction phases. When no longer required, satisfactorily remove.
873.4MEASUREMENT AND PAYMENT —Linear Foot
All necessary hardware is incidental.