ROADSIDE DEVELOPMENT

872SEDIMENT BASIN

PA · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 805–0 Save this section

Ask about Section 872

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

872.1DESCRIPTION—This work is the construction, maintenance, removal and/or conversion of a sediment

basin to a permanent stormwater management facility.

872.2MATERIAL—

(a)Embankment. Section 206.2(a)
(b)Pipe. Section 601.2 (for the type indicated)
(c)Outlet Protection, Rock. Section 851.2
(d)Temporary Baffle Wall. Section 873.2
(e)Cleanout Stake. 2 inch by 2 inch, Spruce/Pine/Fir, Construction Grade, of the length required, or

other approved material of adequate size and length.

(f)Temporary Riser Pipe Assembly. Section 874.2 (where indicated)
(g)Concrete Outlet Structure. Section 875.2 (where indicated)
(h)Emergency Spillway.

• Rock. Section 850.2(a)

• Geotextile. Class 4, Type A. Section 735

(i)Seeding and Soil Supplements. Section 804.2
(j)Mulch. Section 805.2

872.3CONSTRUCTION—As shown on the Standard Drawings, at the location indicated or directed , and

as follows: As specified in Section 201.3, clear and grub the storage area and embankment foundation area site. Excavate the key trench for the full length of the embankment. Excavate the emergency spillway as indicated. Install the outlet protection, outlet pipe with the anti-seep collar attached, and outlet structure at the location indicated. When indicated, construct the temporary riser pipe assembly, as specified in Section 874.3. When concrete anti-seep collar is specified, construct collar as specified in the applicable parts of Section 1001.3. When the sediment basin is located in a permanent stormwater management facility and a concrete outlet structure is indicated, construct concrete outlet structure as specified in Section 875.3. Construction of the embankment and trench before placing the pipe is not required. Do not use coarse aggregate as backfill material around the pipe. Backfill the pipe with suitable embankment material to prevent embankment leakage along the pipe. Construct outlet protection of the type indicated at outlet end of pipe, as specified in Section 85 1.3. Place the embankment material, as specified in Section 206.3. If required, obtain borrow excavation for the formation of the embankment, as specified in Section 205. Apply seeding and soil supplements, as specified in Section 804.3. Mulch, if required, as specified in Section 805.3. Install and maintain cleanout stake as required, as indicated, or as directed. Inspect sediment basin after each runoff event. Remove accumulated sediment as specified in Section 861.3 and repair as required or as directed. When the tributary area to the sediment basin is stabilized, or the basin is no longer required, or when directed, satisfactorily recondition the site as follows:

• Temporary Sediment Basin: Fill in excavated areas, removing embankments, riser pipe assemblies, corrugated metal pipe, and anti-seep collars, or as directed. Restore the areas as specified in Section

105.14. Satisfactorily dispose of removed materials

• Sediment Basin located in a Permanent Stormwater Management Basin area: Remove accumulated sediment and restore basin to final contouring as indicated, stabilize disturbed areas as indicated, remove temporary orifice covers, temporary standpipes, affix permanent stormwater management features as specified in Section 875.3, as indicated, or as directed. Satisfactorily dispose of removed materials.

872.4MEASUREMENT AND PAYMENT—

(a)Class 1 Excavation. Section 203.4
(b)Temporary Riser Pipe Assembly. Section 874.4
(c)Pipe. Section 601.4

For the type indicated.

(d)Anti-Seep Collar. Each

For the type indicated.

(e)Embankment. Section 206.4
(f)Borrow Excavation. Cubic Yard

Section 205.4.

(g)Seeding and Soil Supplements. Section 804.4

For the type indicated.

(h)Mulch. Section 805.4

For the type indicated.

(i)Concrete Outlet Structure. Section 875.4
(j)Outlet Protection, Rock. Section 851.4

For the type indicated.

(k)Rock. Cubic Yard

Section 850.4

(l)Geotextile. Square Yard

Section 212.4

(m)Cleaning of Sedimentation Structures. Section 861.4
(n)Temporary Baffle Wall. Section 873.4

Get an email when 872 changes

Pennsylvania revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Publication 408 Highway Construction Specifications, 2026 Edition. Pages 805–0 of 1,522. View official source ↗

Ask about this section

Scoped to Pennsylvania Publication 408 — Specifications, Section 872 — SEDIMENT BASIN. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.