3-8
307.06 Pulverizing The entire depth of existing pavement shall be pulverized together
with 1 inch or more of the unde rlying gravel into a homogenous mass. All pulverizing shall be done with equipment that will provide a homogenous mass of p ulverized material, processed in-place, which will pass a 2 inch square mesh sieve.
307.07 Weather Limitations Full depth recycled work shall be p erformed when;
a Recycling operations will be allowed between May 15th and September 15th inclusive in Zone 1 - Areas north of US Rout e 2 from Gilead to Bangor and no rth of Route 9 from Bangor to Calais. Recycling will be allowed between May 1st and September 30th inclusive in Zone 2 - Areas south of Zone 1 i ncluding the US Route 2 and Route 9 boundaries. b The atmospheric temperature, as determined by an approved the rmometer placed in the shade at the recycling location, is 50°F and rising. c When there is no standing water on the surface. d During generally dry conditions, or when weather conditions a re such that proper pulverizing, mixing, grading, finishing and curing can be obtai ned using proper procedures, and when compaction can be accomplished as determined by the Re sident. e When the surface is not frozen and when overnight temperature s are expected to be above 32°F. f Wind conditions are such that the spreading of lime or cement on the roadway ahead of the recycling machine will not adversely affect the operation.
307.08 Surface Tolerance The complete surface of the Full Dept h Recycled course shall
be shaped and maintained to a tolerance, above or below the req uired cross sectional shape, of ⅜ inch.
307.09 Full Depth Recycling Procedure New aggregate or recycle d material meeting the
requirements of Section 307.021 - New Aggregate and Additional Recycled Material, shall be added as necessary to restore cross-slope and/or grade befor e pulverizing. Locations will be shown on the plans or described in the construction notes. T he Resident may add other locations while construction of the project is in progress. The Contractor will use recycled material to the extent it is available, in lieu of new aggregat e. The material shall then be pulverized, processed, and blended into a homogeneous mass pass ing a 2 inch square mesh sieve. Material found not pulverized down to a 2 inch size will be required to be reprocessed by the recycler with successive passes until approved by the Re sident. Should the Contractor be require d to add new aggregate or recyc led material to restore cross-slope and/or grade after the initial pulverizing process, those areas will require re- processing to blend into a homogenous mass passing a 2 in squa re mesh sieve. 3-9 Sufficient water shall be added during the recycling process to maintain optimum moisture for compaction. The resultant material from the initial pulverizing processes s hall be graded and compacted to the cross-slope and profile shown on the plans or as directed by the Resident. The Contractor will also be responsible for re-establishing the existing profile grade. The completed surface of the full depth recycled course shall be sh aped and maintained to a tolerance, above or below the required cross sectional shape, o f ⅜ inch. Areas not meeting this tolerance will be repaired as described in Section 307.091 . The initial pulverizing process density requirements will be the same as Section 307.10 1 unless otherwise directed by the Resident. Additives, if required, shall be introduced following completio n of the initial pulverizing and blending process. Emulsified asphalt stabilizer shall be in corporated into the top of the processed material as specified in section 307.04 to the depth specified in the contract by use of the liquid mixer unit or a distributor, at the rate spec ified in the mix design. The emulsified asphalt shall then be uniformly blended into a homog eneous mass until an apparent uniform distribution has occurred. The rate of applic ation may be adjusted as necessary by the Resident. Cement or lime shall be introduced a s described in section 307.041. The resultant material shall be graded and compacted t o the cross-slope and profile shown on the plans or as directe d by the Resident. The Contrac tor will also be responsible for re-establishing the existing profile grade. After final compaction, the roadway surface shall be treated wi th a light application of water, and rolled with pneumatic-tired rollers to create a clos e-knit texture. The finished layer shall be free from:
307.10 Quality Control The Contractor shall operate in accordan ce with the approved
Quality Control Plan (QCP) to assure a product meeting the cont ract requirements. The QCP shall meet the requirements of Section 106.4 - Quality Cont rol and this Section. The Contractor shall not begin recycling operations until the Depar tment approves the QCP in writing. Prior to performing any recycling process, the Department and t he Contractor shall hold a Pre-recycle conference to discuss the recycling schedule, typ e and amount of equipment to be used, sequence of operations, and traffic control. A copy o f the QC random numbers to be used on the project shall be provided to the Resident. All field supervisors including the responsible onsite recycling process supervisor shall attend th is meeting. The QCP shall address any items that affect the quality of the Recycling Process including, but not limited to, the following: