401.15 Compaction Immediately after the Hot Mix Asphalt Paveme nt has been spread,
struck off, and any surface irregularities adjusted, the Contra ctor shall thoroughly and uniformly compact the HMA by rolling. The Contractor shall roll the surface when the mixture is in th e proper condition and when the rolling does not cause undue displacement, cracking, o r shoving. The Contractor shall prevent adhesion of the HMA to the rollers or vibrating c ompactors without the use of fuel oil or other petroleum based release agents. Solvents desi gned to strip asphalt binders from aggregates will not be permitted as release agents on equi pment, tools, or pavement surfaces. The Contractor shall immediately correct any displacement occur ring as a result of the reversing of the direction of a roller or from other causes to the satisfaction of the Department. Any operation other than placement of variable dep th shim course that results in breakdown of the aggregate shall be discontinued. Any new p avement that shows obvious cracking, checking, or displacement shall be removed an d replaced for the full lane width as directed by the Resident at no cost to the Department. Along forms, curbs, headers, walls, and other places not access ible to the rollers, the Contractor shall thoroughly comp act the HMA with mechanical vib rating compactors. The Contractor shall only use hand tamping in areas inaccessible to all other compaction equipment. On depressed areas, the Contractor may use a trench roller or cleated compression strips under a roller to transmit compression to th e depressed area. 4-13 Any HMA that becomes unacceptable due to cooling, cracking, che cking, segregation or deformation as a result of an interruption in mix delivery shal l be removed and replaced with material that meets contract specifications at no cost to the Department.
401.16 Joints The Contractor shall construct wearing course tr ansverse and longitudinal
joints in such a manner that minimum tolerances shown in Sectio n 401.11 - Surface Tolerances are met when measured with a straightedge. The paver screed shall maintain a uniform head of HMA during transverse and longitudinal joint co nstruction. The HMA shall be free of segregation and meet temperature requirements outlin ed in Section 401.04. Transverse joints of the wear ing course shall be straight and n eatly trimmed. The Contractor may form a vertical face exposing the full depth of the course by inserting a header, by breaking the bond with the underlying course, or by cutting back with hand tools. The Contractor shall apply a coating of emulsified asphalt imme diately before paving all joints to the vertical face and 3 in of the adjacent portion of any pavement being overlaid except those formed by pavers operating in echelon. The Contra ctor shall use an approved spray apparatus designed for covering a narrow surface. The De partment may approve application by a brush for small surfaces, or in the event of a malfunction of the spray apparatus, but for a period of not more than one working day. Where pavement under this contract joins an existing pavement, or when the Department directs, the Contractor shall cut the existing pavement along a smooth line, producing a neat, even, vertical joint. The Department will not permit broken or raveled edges. The cost of all work necessary for the preparation of joints is incidental to related contract pay items. Longitudinal joints shall be generally straight to the line of travel and constructed in a manner that best ensure joint integrity. Methods or activities that prove detrimental to the construction of straight, sound longitudinal joints will be dis continued. The Contractor may utilize an a pproved notched wedge joint devi ce on all HMA layers 1 ½ inches in depth or greater. A notch ed wedge joint shall be co nstructed as shown in Figure 1 using a device that is attached to the paver screed and is ca pable of independently adjusting the top and bottom vertical notches. FIGURE 1: Notched Wedge Joint Notes
401.17 Hot Mix Asphalt Documenta tion The Contractor and the De partment shall agree
on the amount of Hot Mix Asphalt Pa vement that has been placed each day. All delivery slips shall conform to the requirements of 401.078.
401.18 Prepave Meeting Prior to placing any mix, the Departme nt and the Contractor
shall hold a Pre-paving conference to discuss the paving schedu le, source of mix, type and amount of equipment to be used, sequence of paving pattern, rat e of mix supply, random sampling, project lots and sublot s and traffic control. A copy of the density QC random numbers to be used on the project s hall be provided to the Resi dent. The Departments’ random numbers for Acceptance testing shall be generated and on file with the Resident and the Project Manager. All personnel of the Department and the C ontractor who have significant information relevant to the paving items shall atte nd, including the responsible onsite paving supervisor for the Contractor. The Resident will prepare minutes of the conference and distribute them to all attendees. Any requests to revise the minutes must be made to the Resident within 7 Days of Receipt. These minutes w ill constitute the final record of the Pre-paving confer ence. On the first day of paving and whenever there is a change in the onsite paving forem an or paving inspector, the De partment and the Contractor shall hold an informal onsite meeting to review the minutes of the Pre-paving conference, Project Specific QCP, Plans, T ypicals, Special Provisions and c ommunication process. This meeting shall be held prior to placing any mix. The onsite pav ing supervisor, QCT, Superintendent, Resident and/or paving inspector shall attend. Prepave meetings shall not be required on projects designated as Acceptance Method D unless o therwise noted in Section 403 - Hot Mix Asphalt Pavement. 4-15
401.19 Contractor Quality Control The Contractor shall operate in accordance with the
approved Quality Control Plan (QCP) to assure a product meeting the contract requirements. The Contractor shall not begin paving operations until the Depa rtment approves the QCP in writing. 401.191 Quality Control - Method A, B & C The QCP shall meet t he requirements of Section 106.6 - Acceptance and this Section. The QCP shall addr ess any items that affect the quality of the Hot Mix Asphalt Pavement including, but not limi ted to, the following: