5-88
505.06 Method of Measurement Shear connectors shall be measure d as one lump sum,
consisting of all shear connectors required and acceptably inst alled. Stud welded anchors and fasteners will be considered incidental to the pay item for which they are required.
505.07 Basis of Payment The accepted quantity of shear connect ors will be paid for at
the lump sum price. Payment will be made under: P a y I t e m Pay Unit
505.08 Shear Connectors Lump Sum
SECTION 506- SHOP APPLIED PROTECTIVE COATING - STEEL
506.01 Description This work shall consist of applying protect ive coating to steel
substrate in accordance with the Plans and this Specification. The protective coating system shall be as specified on the Plans. ALL REQUIREMENTS IN THIS SPECIFICATION ARE THE RESPONSIBILITY O F THE CONTRACTOR UNLESS NOTED OTHERWISE.
506.02 Materials Materials shall comply with the requirements of the respective
Subsections of this Specification.
506.03 Submittals Submit the following, as applicable:
506.04 General Specifications Specifications for the protectiv e coating and/or protective
coating systems are: Zinc Rich Coating System Subsections 506.10 through 506.19 H o t - D i p G a l v a n i z i n g S u b s e c t i o n s 506.20 through 506.29 T h e r m a l S p r a y C o a t i n g S u b s e c t i o n s 506.30 through 506.39 Fusion Bonded Epoxy Coating Subsections 506.40 through 506.49 506.05 Inspection Quality Control (QC) is the responsibility o f the Contractor. Inspect all aspects of the work and supervise all sampling, measurement s and testing. Record measurements and test results in a clear and legible manner in a format acceptable to the Fabrication Engineer. Reject mat erials and workmanship that do not meet Contract 5-89 requirements. The QCI may perform sampling, measurements and t esting in addition to the minimum required. Make the results of all sampling, measuremen ts and testing available to the Quality Assurance Inspector (QAI). Training in surface preparation, coatings application, and insp ection is required for QCI’s. Acceptable training includes one or more of the followi ng:
506.06 Non-Conforming Work Submit a non-conformance report to the Fabrication
Engineer describing the defici encies and proposed solution. Co rrect or replace rejected coatings as directed by the Fabrication Engineer.
506.07 Facilities for Inspection Provide a private office at t he fabrication plant for the
Department’s inspection personnel, or QAI’s. The office shall be in close proximity to the work. The office shall be climate controlled to maintain the t emperature between 68° F and 75° F and have the exit(s) closed by a door(s) equipped with a lock and 2 keys which shall be furnished to the Inspector(s). The QAI’s office shall meet the following minimum requirem ents: Description Quantity Office area (minimum ft2) 100 Drafting Table Surface (ft2) 3 5 Drafting stools-each 1 O f f i c e D e s k 1 Ergonomic Swivel Chairs 1 Folding Chairs 2 High-speed internet connection (ports) or wireless 1 Fluorescent Lighting of 100 foot-candles minimum for all work a reas 2 5-90 110 Volt 60 Cycle Electric Wall Outlets 3 W a l l C l o s e t 1 Waste Basket with trash bags 1 B r o o m 1 D u s t p a n 1 Water Cooler 1 Cleaning materials-floor, surf aces, windows- for duration of th e project The Contractor will be responsib le for disposing of trash and s upplying commercially bottled water for the water cooler. The QAI has the option to reject any furniture or supplies prov ided to the QAI’s office, based on general poor condition. Provide parking space for the QAI(s) in close proximity to the entrance to the QAI’s office. Maintain the pathway betw een the parking area and the QAI’s office so that it is free of obstacles, debris, snow and ice. The facilities and all furnishings shall remain the property of the Contractor upon completion of the Work. Payment for the facilities, heating, l ighting, telephone installation, internet connection, basic monthly telephone and internet charg es and all furnishings shall be incidental to the Contract. Failure to comply with the above requirements will be considere d denial of access to the Work for the purpose of inspection. The Department will reject all Work done when access for inspection is denied.
506.08 Applicator Qualification Shop-applied paint systems sha ll be applied by
applicators that hold a current A ISC Sophisticated Paint Endors ement (SPE) or are qualified in accordance with NACE NIICAP. Thermal Spray Coating (TSC), i ncluding sealers and top coating shall be applied at facilities with a minimum of fi ve years’ experience with additions of the certifications in the previous section or qual ified in accordance with SSPC- QP6, Contractor Metallizing. Fusion bonded coatings and hot-di p galvanizing shall be applied in facilities with a minimum of five years’ experience of satisfactory performance. The Fabrication Engineer may accept other shop qualifications b ased on experience and/or an audit by the Department.
506.09 Inspection Measure and record the following, as applica ble to the coating
application, in a Job Control Record (JCR):
506.10 Description This work shall consist of surface preparat ion and application of
coating systems in accordance with the Plans and this Specifica tion. The color of structural steel painted in its entirety shall comply with Federal Standar d 595, Color No. 14272 (Green), unless otherwise specifi ed in the Contract. The color of partially painted weathering steel shall comply with Federal Standard 595, Color No. 30045 (Brown), unless otherwise specified in the Contr act. All other coating colors s hall be as specified in the Contract.
506.11 Materials Coatings systems shall be from the Northeast Protective Coating
Committee (NEPCOAT) Qualified Pr oducts List (QPL), list A or B. The list may be found through NEPCOAT’s Web page: http://www.nepcoat.org. Provide the paint batch descrip tion, lot number, date of manufa cture, shelf life and the manufacturer’s storage requirements to the QAI. Provide the ma nufacturer's published data sheet for each coat of the coating system including equipment, surface cleanliness, anchor