5-88
505.06 Method of Measurement Shear connectors shall be measure d as one lump sum,
consisting of all shear connectors required and acceptably inst alled. Stud welded anchors and fasteners will be considered incidental to the pay item for which they are required.
505.07 Basis of Payment The accepted quantity of shear connect ors will be paid for at
the lump sum price. Payment will be made under: P a y I t e m Pay Unit
505.08 Shear Connectors Lump Sum
SECTION 506- SHOP APPLIED PROTECTIVE COATING - STEEL
506.01 Description This work shall consist of applying protect ive coating to steel
substrate in accordance with the Plans and this Specification. The protective coating system shall be as specified on the Plans. ALL REQUIREMENTS IN THIS SPECIFICATION ARE THE RESPONSIBILITY O F THE CONTRACTOR UNLESS NOTED OTHERWISE.
506.02 Materials Materials shall comply with the requirements of the respective
Subsections of this Specification.
506.03 Submittals Submit the following, as applicable:
506.04 General Specifications Specifications for the protectiv e coating and/or protective
coating systems are: Zinc Rich Coating System Subsections 506.10 through 506.19 H o t - D i p G a l v a n i z i n g S u b s e c t i o n s 506.20 through 506.29 T h e r m a l S p r a y C o a t i n g S u b s e c t i o n s 506.30 through 506.39 Fusion Bonded Epoxy Coating Subsections 506.40 through 506.49 506.05 Inspection Quality Control (QC) is the responsibility o f the Contractor. Inspect all aspects of the work and supervise all sampling, measurement s and testing. Record measurements and test results in a clear and legible manner in a format acceptable to the Fabrication Engineer. Reject mat erials and workmanship that do not meet Contract