Electrical (16000-16999)

631.11Air Tool (including operator) Hour

ME · 2020 Standard SpecificationsBook pages 570571View official source ↗

6-100

631.07 Method of Measurement Equipment rental will be measure d by the hour to

the nearest ¼-hour. Time spent moving to and from the site wit hin the project limits and from beyond the project limits, servicing, maintaining, and cha nging attachments will not be measured for payment. Supervision required in the performance of hourly equipment re ntal work will be measured for payment only when called for on the Plans. This i tem does not relieve the Contractor of the responsibility to supervise other contract it ems. Foreman will be measured by the hour to the nearest ¼ hour of time actually spe nt supervising operators of hourly equipment rental pay items. The name of the supervisor will be supplied to the Resident.

631.08 Basis of Payment The accepted quantities of equipment rental will be paid

for at the contract unit price per hour for each type of equipm ent used. Payment shall include operators, fuel, grease, oil, and other incidentals nec essary to operate the equipment. No separate payment will be made to direct work done under the se items, except when called for on the Plans. Payment will then be made under Pay Item 631.36. Payment made will be limited to the grade of foreman and limited to hou rs spent in actually supervising equipment operators. Such related costs as use of pickup truck, meal and room expenses, benefits, insurance, retirement, travel time, and ove rtime will not be paid for separately but will be considered incidental to the unit price bid for this pay item. Payment for equipment rental will be based on experienced opera tors, familiar with the work being performed. Operators, determined to be below normal acceptable standards of production or workmanship, will be paid for at reduced hours as determined by the Resident. Payment will be made under: P a y I t e m P a y U n i t

631.10 Air Compressor (including operator) Hour

631.11 Air Tool (including operator) Hour

631.111 Tractor Mounted Hydraulic Hammer Hour

631.12 All Purpose Excavator (including operator) Hour

631.121 Heavy Duty All Purpose Excavator (including operator) Hour 631.122 Mini All Purpose Excavator (including operator) Ho ur

631.13 Bulldozer (including operator) Hour

631.131 Small Bulldozer - Grader (including operator) Hour 631.132 Small Bulldozer (including operator) Hour 631.133 Skid Steer (including operator) Hour

631.14 Grader (including operator) Hour

631.15 Roller, earth and base operator) Hour

631.16 Roller, Pavement (including operator) Hour

631.171 Truck-small (including operator) Hour 6-101 631.172 Truck-large (including operator) Hour

631.18 Chain Saw Rental (including operator Hour

631.20 Stump Chipper Rental (including operator) Hour

631.21 Road Broom (including operators and hauler) Hour

631.22 Front End Loader (including operator) Hour

631.221 Small Front End Loader (including operator) Hour

631.28 Brush Chipper (including operator) Hour

631.29 Rototiller (including operator) Hour

631.32 Culvert Cleaner (including operators) Hour

631.36 Foreman Hour

SECTION 632 and 633 - VACANT SECTION 634 - HIGHWAY LIGHTING

634.01 Description This work shall consist of furnishing and installing a highway

lighting system or modifying or removing an existing highway li ghting system, including the design of Light Standards, in accordance with these specifi cations and in reasonably close conformity with the plans.

634.02 General All material furnished by the Contractor shall be new unless otherwise

specified. Substitutes for specified material may be accepted, upon approval of the Fabrication Engineer. Substitutes shall provide equal or better service. Where an existing system is to be modified, the existing material shall be remove d, upgraded, or disposed of as shown on the plans or as directed. All electrical equipment shall c onform to NEMA, UL, or EIA stan dards, wherever applicable. In addition, all materials and workmanship shall c onform to the requirements of the NEC, the local electrical Utility Company, and all local or dinances, which may apply. 634.021 Materials Materials shall meet the requirements specif ied in the following Section of Division 700 - Materials: Steel Conduit 715.02 Non-metallic Conduit 715.03 Prewired Conduit 715.04 Metallic Junction and Fuse Box 715.05 Secondary Wiring 715.07 Luminaires, Lamps and Ballast 715.08 Luminaires, Lamp and Ballast for High Mast Lighting 715.09 Photo Electric Control 715.10 S e r v i c e E q u i p m e n t 715.11 Lowering System for High Mast Lighting 715.12 Aluminum Supports 720.01 Aluminum Mast Arm and Bracket Arm 720.02

Source: Maine Standard Specifications for Road and Bridge Construction, 2020 Edition. Pages 570571 of 817.