681.07 Method of Measurement Precast Aggregate-filled Concret e Block Gravity
Wall will be measured by the Square Foot of front surface not t o exceed the dimensions shown on the Contract Plans unless authorized by the Resident. Vertical and horizontal dimensions will be from the edges of the blocks. No field meas urements for computations will be made unless the Resident specifies, in writing, a chang e in the limits indicated on the Plans.
681.08 Basis of Payment The accepted quantity of Precast Aggr egate-Filled
Concrete Block Gravity Wall will be paid for at the contract un it price per Square Foot complete in place. Payment shall be full compensation for furn ishing geotechnical design as required, all labor, equipment and materials including all prec ast concrete units, hardware, joint fillers, geosynthetic, drainage pipe, and technical field representative. Excavation, foundation material and backfill material will all be incidenta l to the Precast Aggregate- Filled Concrete Block Gravity Wall. Cost of cast-in-place concrete for leveling pad will not be pa id for separately, but will be considered incidental to the Precast Aggregate-Filled C oncrete Block Gravity Wall. There will be no allowance for excavating and backfilling for the Precast Aggregate- Filled Concrete Block Gravity Wall beyond the limits shown on t he approved submitted Plans, except for excavation required to remove unsuitable subs oil in preparation for the foundation. Payment for excavating unsuitable subsoil shall be full compensation for all costs of pumping, drainage, sheeting, bracing and incidentals f or proper execution of the work, and will be paid as common excavation in accordance with Section 203. Payment will be made under: 6-235 P a y I t e m P a y U n i t Precast Aggregate-Filled Concrete Block Gravity Wall Square F oot 7‐1 Chapter 7 DIVISION 700 - MATERIALS GENERAL STATEMENT MATERIALS CERTIFICATION LETTER For all materials used in the work for which there is no speci fied acceptance testing by the project Inspectors or the Labor atory, the Contractor shall subm it a Materials Certification Letter similar to the following, prior to acceptance as specified in S ection 107.9.4. Company Letterhead M r . / M r s . , R e s i d e n t D a t e A d d r e s s P r o j e c t N o. T o w n This is to certify that all materials incorporated into the pr oject for which there is no specified acceptance testing by project inspectors or the labor atory, comply with the pertinent specified material requirements of the contract. Processing, p roject testing, and inspection control of raw materials shall be in conformity with the applic able drawings and/or standards for all articles furnished. All records and documents pertinent to this letter and not sub mitted herewith will be maintained and will be available by the undersigned for a perio d of not less than three years from the date of completion of the project. The Materials Certification letter must be signed by a person having legal authority to bind the Contractor. Materials listed in the above Certificate may be subject to ra ndom sampling and testing by the Department at any time. When random verification samples a re obtained from the project, they shall be provided by the Contractor at no cost to the Depa rtment. Certified materials, which fail to meet specification requirements, may not be accep ted and may require replacement with materials that do meet the specifications. The Contractor may be required t o submit to the Resident, for i nclusion in the project records, certification and other data from the Manufacturer per taining to materials used on the project. The Certificate shall include the actual test results of the ma terial in storage from which the shipments are being made. Certificates shall be supplied for e ach lot, batch, or blend of each type and grade of material. A new certificate shall be issued at least every 30 days or upon receiving or manufacture of a new material. 7-2 The Contractor shall give the supplier sufficient advance noti ce of orders to permit testing. Material not represented by tests will not be accepted for use on the work. Deliveries of asphalt materials shall be accompanied by a load ing invoice, delivery ticket, or slip, as required under Section l08.1.3 f. The Loading Invoice shall include the applicable certificate number and shall include a printed or stamped state ment such as the following: “THIS IS TO CERTIFY THAT THE ASPHALT MATERIAL REPRESENTED BY THIS LOADING INVOICE CONFORMS TO THE SPECIFICATIONS OF THE PURCHASER FOR THE MATERIAL TYPE AND GRADE STATED THEREON.” In the event an intermediate hauler of the asphalt material is involved, a copy of their own delivery slip shall be furnished, as well as a copy of the supp lier's loading invoice. The hauler's delivery slip and the supplier's loading invoice shall be cross -referenced by use of their respective serial numbers. All test procedures shall conform to the requirements of AASHT O unless otherwise noted. Gradation tests shall be completed in accordance with AASHTO T 27 except that the sample may be separated on the ½ inch screen. Testing as specified in AASHTO T 11 shall be performed on any materials for which there is a specification l imit on the amount of material passing a No. 200 sieve. The Department may require the Contractor to submit, for inclu sion into the project records, certification that new Work Zone Category 1 and Category 2 Devi ces meet National Cooperative Highway Research Program (NCHRP) Report 350 guideli nes. Work Zone Category 1 Devices include plastic drums, cones, and tubular ma rkers. Work Zone Category 2 Devices include portable sign stands (with signs), Type I, Type II, and Type III barricades, vertical panels, intrusion alarms, and other work zone devices under 100 pounds. All Work Zone Category 1 and Category 2 Devices shall meet NCHRP Report 350 and MUTCD guidelines. Vendors/Contractors will be allowed to self-certify Work Zone Category 1 Devices with a letter of self-certification. A letter of self-certification s hall contain at a minimum
701.01 Portland Cement and Portland Pozzolan Cement Portland cement shall
conform to the requirements of AASHTO M 85, Type II. A Type I, Type II or Type III cement meeting AASHTO M 85 may b e used when making precast units. A Type IP (MS) Portland-pozzolan cement (blended hydraulic cem ent with moderate sulfate resistance) meeting the requirements of AASHTO M 240 , may be used instead of Type II or where Type I Portland cement, meeting the requiremen ts of AASHTO M 85, is allowed. The definitions of the two hydraulic cements mentione d above are as follows: (See ASTM C 219) Portland cement - a hydraulic cement produced by pulverizing Po rtland cement clinker, and usually containing calcium sulfate. Portland-pozzolan cement - a hydraulic cement consisting of an intimate and uniform blend of Portland cement or portland blast furnace slag cement and fine pozzolan produced by intergrinding Portland cement clinker and pozzolan, by blend ing Portland cement or portland blast furnace slag cement and finely divided pozzolan, or a combination of intergrinding and blending, in which the amount of the pozzolan constituent is within specified limits. Only one brand of cement shall be used on any one contract unle ss otherwise permitted, in writing, by the Resident. The cement shall be protected from dampness during storage. Partially set cement or cement that contains caked lumps shall not be used. The Contractor shall arrange for the cement supplier to provide a Manufacturer’s Certification (Mill Test Report) for all cement materials furni shed for use on the project. Reports shall include all mandatory and optional requirements s pecified in AASHTO M 85 or AASHTO M 240 including any processing additions. Reports sha ll represent the cement incorporated into the project and reports shall be supplied, at a minimum, on a monthly basis. Reports shall be submitted to the Department’s Materials Testing Engineer.
701.02 Water Water used in mixing or curing concrete shall be reasonably clean and
free of oil, salt, acid, alkali, sugar, vegetation, or substanc es injurious to the finished product. If required by the Resident, it shall be tested in ac cordance with the requirements of AASHTO T 26. Water known to be of potable quality may be us ed without testing. Where the source of water is relatively shallow, the intake sha ll be so enclosed as to exclude silt, mud, grass, or other foreign materials.