5-114 the Special Detour is no longer n eeded and is closed to traffic ; the final 20 percent of the lump sum price will be paid when the Special Detour is removed and the area encompassing the Special Detour is acceptably restored. Traffic control devices, tempor ary erosion control, pavement, a nd dust control will be paid for in accordance with the applicable Contract items. Payment will be made under: P a y I t e m P a y U n i t
510.10 Special Detour, ___ foot Roadway L u m p S u m
Width Vehicular and Pedestrian Traffic N o t S e p a r a t e d 510.11 Special Detour, Pedestrian Traffic Only L u m p S u m
510.12 Special Detour, ___ foot Roadway L u m p S u m
Width Vehicular and Pedestrian Traffic S e p a r a t e d SECTION 511- COFFERDAMS
511.01 Description This work shall consist of the complete des ign, construction,
maintenance and removal of cofferdams and other related work, i ncluding dewatering and inspection, required to allow for the excavation of foundation units, to permit and protect the construction of bridge or other structural units and to protect adjacent Roadways, embankments or other structural units, in accordance with the C ontract.
511.02 Materials As specified in the cofferdam Working Drawing s.
511.03 Cofferdam Construction
511.04 Pumping Pumping from the interior of any cofferdam shal l be done in such a
manner as to prevent any current of water that would carry away or segregate the concrete. Pumping to dewater a sealed cofferdam shall not commence until the seal concrete has set sufficiently to withstand the hydrostatic pressure and meet s the following minimum curing time, after the completion of the installation of the se al concrete:
511.05 Method of Measurement Cofferdams will be measured as on e lump sum unit, as
indicated on the Plans or called for in the Contract.
511.06 Basis of Payment The accepted quantity of cofferdam wil l be paid for at the
Contract lump sum price for the respective cofferdam items, whi ch price shall be full compensation for design, construction, maintenance, inspection and removal. When required, the elevation of the bottom of the footing of an y substructure unit may be lowered, without change in the price to be paid for cofferda ms. However, if the average elevation of more than 25 percent of the area of the excavation is more than three feet below the elevation shown on the Plans, and if requested by the Contr actor, then the additional costs incurred that are included in the cofferdam Pay Item will be paid for in accordance with Section 109.7, Equitable Adjustments to Compensation and T ime. The Contractor shall immediately notify the Department when these additional c osts commence. Failure of the Contractor to provide this notification will result in undo cumented additional work that will be non-reimbursable. The Department will evaluate this ad ditional work to determine an appropriate time extension, if warranted. All costs for sedimentation control practices, including, but n ot limited to, constructing, maintaining, and removing sedimentation control structures, and pumping or transporting water and other materials for sedimentation control will not be paid for directly, but will be considered incidental to the cofferdam Pay Item(s). All costs for related temporary soil erosion and water pollutio n controls, including inspection and maintenance, will not be paid for directly, but will be considered incidental to the cofferdam Pay Item(s). All costs associated with preparation of Working Drawings, desi gn calculations, written procedure for sediment/overburden removal and excavation inspec tion, and the inspection of the seal cofferdam excavation shall be considered incidental to the cofferdam Pay Item(s). 5-117 There shall be no additional payment for repeated inspection by the Department of the same cofferdam excavation. All costs for cofferdams and related temporary soil erosion and water pollution controls, including inspection and maintenance, will be considered incide ntal to related Pay Items, when a specific Pay Item for cofferdams is not included in the Contract. Seal concrete will be evaluated under Section 502. Payment will be made under: P a y I t e m P a y U n i t
511.07 Cofferdam L u m p S u m
SECTION 512 - FRENCH DRAINS
512.01 Description This work shall consist of furnishing, plac ing and compacting stone
and gravel and furnishing and placing erosion control geotextil e for French drains in accordance with these specifications and in reasonably close co nformity with the lines and grades shown in the Contract.
512.02 Materials. Materials shall meet the requirements of the following Sections of
Division 700 — , Materials.
Aggregate for Subbase 703.06(b) G r a v e l B o r r o w 703.20 Stone for French Drains 703.24 Erosion Control Geotextile 722.03 (Class 1) Gravel for French drains shall meet the requirements of either Aggregate for Subbase, Type D, or Gravel Borrow, at the Contractor's option.
512.03 Drains Stone shall be placed behind and against the str uctures with the bottom
of the stone at the elevation of the flow line of the weeper dr ains. The stone shall form a box section, 2 feet wide and 2 feet high, for the entire length of the structure. Erosion control geotextile shall be installed to separate the stone box section from the surrounding gravel. Installation of the erosion control geotextile shall b e in accordance with Section 620, Geotextiles. Gravel shall be placed to form a box section around the stone, to the limits of 2 feet above the stone, 2 feet behind the stone and 2 feet b elow the stone, but not to be placed below the top of the footing.