P l a n s Supplemental Specifications Supplemental Standard Details Standard Specifications Standard Details 101.3.7 Multiple Pay Items When there is more than one Pay It em for similar Work governed by one Specification, the item number in the Specification may be appended with additional digits to differentiate such multiple Pay Items. Fo r example, Specification item
900.061, 900.062, 900.0601, and 90 0.0602, etc. unless the
context clearly indicates otherwise.
Scope of Section This Section includes requirements related t o eligibility to Bid and the Bidding process from advertisement for Bids, through Bid Op ening, to the analysis of Bids.
102.1Eligibility to Bid
102.1.1 Basic Requirements To be eligible to Bid, prospective Bidders must (A) not have been debarred or suspended from Bidding, and (B) not be in Default with respect to any outstanding Contract with the Department, unless the Department grants written permission to Bid despite such Default. For related provisions , see Sections 102.9 - Bid Opening and 103.3 - Post-Bid Qualification. 102.1.2 Suspension From Bidding The Department may suspend th e right of a Contractor to submit Bids as the general Contractor on construction Projects being developed by the Department’s Bureau of Project Development for up to two years pursuant to Department’s “Rules Regarding Suspension From Bidding.” 102.1.3 Debarment The Department may debar a Contractor from Bidding, subcontracting, or being employed in any capacity regarding any Project administered by the Department pursuant to “Rules Regarding Debarment of Contra ctors,” Department Register 17-229, Chapter 102 (October 2, 1985).
102.2Advertisement - Notice to Contractors A Notice to Contr actors will provide a
solicitation or an invitation to bid and be advertised in printed or electronic media pursuant to Maine law. Such Notice will contain a brief and general des cription of the nature and location of the Work and infor mation about how to Bid and how t o provide any prequalification requirements.
102.3Examinations of Documents, Site and Other Information B efore submitting a
Bid, the Bidder is responsible for: (A) obtaining and examining the Plans, Specifications, all Bid Amendments, and all other Bid Documents; (B) examining the Geotechnical Information and all other information provided or referenced in the Bid Documents; (C)