689.3(a) 689.3(b) The Representative will review and respond to the detailed Narrative Schedule and supporting documentation within 1 4 calendar days of receipt . Include, as a minimum, the following in the initial Narrative Schedule and in all Schedule revisions:
• Activity description;
• Activity d uration, in working days; and
• Start and finish calen dar dates of activities.
In addition, submit a workday calendar showing work days and non -work days, number of shifts per day, and number of hours per shift. Provide enough activities to demonstrate t he necessary interdependencies. Use the above information to complete a narrative description of the construction schedule. If the Narrative Schedule is not received within 15 calendar days after the actual Notice to Proceed Date, the Contractor will be required to attend a scheduling workshop to prepare an acceptable Narrative Schedule. The District Executive may elect not to release current estimate payments until the Narrative Schedule is submitted and accepted.
Day Work Plan from Asta Powerproject that includes a breakdown of activities. Provide a generalized project schedule for the balance of the work, to meet the Required Completion Date and specified Milestone Date(s). Instead of the 60 Calendar Day Work Plan, the Contractor may submit the CPM Schedule specified in basis, a 60 Calendar Day Work Plan until the CPM Schedule is accepted.
days after contract execution . At a minimum, this schedule should include the scheduling concepts and logic that w ere used in sequencing work activities to prepare the contract bid, a workday calendar that identifies work days and non -work days, the number of shifts per day, and the number of hours per shift. Instead of the Bid Preparation Schedule, the Contractor may submit the CPM Schedule specified in Section 689.3 (b)3 within 30 calendar days after the Notice to Proceed . The District Executive, after consultation with the Contractor, may withhold current estimate payments until the Bid Preparation Schedule or CPM Schedule is submitted and accepted .
proposal. Submit the CPM Schedule through PPCC in an Asta Powerproject (.pp) file format using the PennDOT Construction template as defined in