Incidental Construction (600-699)

697RESET TEMPORARY IMPACT ATTENUATING DEVICES

PA · 2026 Standard SpecificationsBook pages 783785View official source ↗

855.3 855.4 bag when contained silt reduces flow to approximately 50 % of rate of initial bag discharge, or when directed. Dispose of bag and sediment in a manner satisfactory to the Representative. Do not cut open bags and seed. Restore area as specified in Section 105.14.

855.4MEASUREMENT AND PAYMENT —Each

856.1 856.4(c) 856 – 1

856.1DESCRIPTION —This work is construction , maintenance , and removal of a rock barrier for channel

and slope protection .

856.2MATERIAL —

(a)Rock, Class R -4. Section 850.2(a), except petrographic examination by the LTS is not required.
(b)Coarse Aggregate, No. 57 . Section 703.2

856.3CONSTRUCTION —As shown on the Standard Drawings and as follows:

(a)Installation. Determine the required dimensions of the rock barrier . Produce an even distribution of

rock with minimum voids. Provide a 12 -inch layer of coarse aggregate on the uphill side of the barrier .

(b)Maintenance. Inspect the rock barrier weekly and after each runoff event throughout the duration

of the project. If needed, immediately repair any damaged areas of the rock barrier found during inspection. Remove sediment when accumulations reach half the height of the barrier . Remove and dispose of sediment in an approved manner.

(c)Remove sediment and rock barrier upon stabilization of each channel as indicated .

856.4MEASUREMENT AND PAYMENT —

(a)Rock. Square Yard or Cubic Yard
(b)Coarse Aggregate. Cubic Yard
(c)Removal Sediment and Rock Barrier . Each

Includes removal of accumulated sediment and proper disposal of all removed materials.

Source: Pennsylvania Department of Transportation Specifications, 2026 Edition. Pages 783785 of 1,522.