INCIDENTAL CONSTRUCTION

660RUMBLE STRIPS

PA · 2026 Standard Specifications✓ Full text on BuildSpecBook pages 586–0 Save this section

Ask about Section 660

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

660.1DESCRIPTION—This work is the construction of rumble strips of the type indicated.

660.3CONSTRUCTION—As shown on the Standard Drawings and as follows:

(a)Equipment. Use a machine capable of providing a smooth cut without tearing or snagging, and

producing rumble strips as shown on the Standard Drawings. Equip machine with guides to provide uniformity and consistency in alignment of each cut with respect to the roadway.

(b)Milling Operation. Before the construction of the rumble strips, meet on-site with the Representative

to discuss rumble strip installation. Construct rumble strips to have finished dimensions and tolerances as shown on the Standard Drawings. After milling the first 100 feet of rumble strips, examine spacing, widths, length, and depths with straight edge. If adjustments are required, mill an additional 100 feet, and confirm correct installation. After installation has been corrected, p roceed as directed. Construct rumble strips before the placement of the permanent pavement markings. If constructing rumble strips into new concrete, only construct after curing as specified in Section 501.3(l). If constructing centerli ne rumble strips into asphalt pavement, construct before placement of the longitudinal joint sealing operation.

(c)Disposal of Milled Material. Satisfactorily remove milled material and clear areas disturbed by the

milling operation of all loose material before opening roadway to traffic. Remove and dispose of milled material according to DEP Residual Waste Regulations.

660.4MEASUREMENT AND PAYMENT—Linear Foot

For the type indicated. Measured longitudinally along center of rumble strip pattern. The unit prices include removal and disposal of milled material.

Get an email when 660 changes

Pennsylvania revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Publication 408 Highway Construction Specifications, 2026 Edition. Pages 586–0 of 1,522. View official source ↗