663.1DESCRIPTION—This work is construction of brick masonry.

663.2MATERIAL—

• Brick. Section 713.1

• Mortar. Section 705.7(b)

663.3CONSTRUCTION—

(a)Excavation. Excavate for masonry structure footer, as required, to form a compacted, firm, even

foundation surface as specified in Section 204 for Class 3 excavation. Remove unsuitable material as specified in Section 203.1(b).

(b)Footing. Construct masonry structure footer as detailed and as specified in Section 1001 using

Class A cement concrete as specified in Section 704.

(c)Sample Panel. Construct an on-site, sample, masonry panel approximately 4 feet square, indicating

the color range, texture, bonding pattern, mortar color, tooling, and workmanship of the proposed brick masonry structure. Obtain approval of the sample panel before erecting the brick masonry.

(d)Placing Brick. Lay brick with exposed surfaces true to line, in courses, in a full bed and head of

mortar, and with joints not exceeding 3/8 inch in width. Do not furrow beds. Stagger head joints on adjoining courses one -half brick, as nearly as practicable. Make courses level, except as otherwise indicated or directed. Construct at least one course in every six entirely of headers, common bond, unless otherwise directed. Saturate bricks with water and ensure that bricks are surface dry before pla cement. Do not use broken or chipped brick in exposed faces. When making closures, do not use less than the width of a brick and lay whole brick, with the long side at right angle to the face.

(e)Pointing. Finish mortar joints with a concave pointing tool to a depth not exceeding 1/8 inch and to

an approved appearance.

(f)Curing and Protection. Do not place mortar and bricks or point, in freezing weather, unless

otherwise authorized in writing. Protect brickwork and other masonry from freezing until cured. Provide adequate protection from frost and remove and replace work damaged by frost. Protec t completed brickwork from the elements. Cure brickwork with water moisture for at least 3 days. Wet and clean the exposed brick faces with a 10% (by volume) solution of muriatic acid, applied with stiff fiber brushes.

(g)Select Borrow Excavation (Structural Backfill). Backfill as specified in Section 205.

663.4MEASUREMENT AND PAYMENT—

(a)Brick Masonry. Cubic Yard
(b)Class A Cement Concrete. Cubic Yard
(c)Excavation. Cubic Yard

For the class indicated.

664 – 1

Get an email when 663 changes

Pennsylvania revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Publication 408 Highway Construction Specifications, 2026 Edition. Pages 587–0 of 1,522. View official source ↗

Ask about this section

Scoped to Pennsylvania Publication 408 — Specifications, Section 663 — BRICK MASONRY. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.