General

025102 — Removal and Disposal of Existing Buildings

MD · 2025 Standard SpecificationsBook pages 141142View official source ↗

by a Contractor's representative. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 102 — REMOVAL AND DISPOSAL OF EXISTING BUILDINGS

102.01 Description

Remove and dispose of existing buildings, including foundations, footings, or any part thereof, and backfill as specified. Locations of buildings included in the work will be designated in the Contract Documents by the circled numbers ① , ②, ③ etc.

102.02 Materials

Not applicable.

102.03 Construction

Schedule the removal, razing, or occupation of buildings and appurtenances as one of the first items of work. Post and protect the buildings from vandalism and theft. Remove and dispose of buildings scheduled for temporary use immediately when vacated. Buildings and appurtenances may be disposed of by burning if they are not located close to habitable dwellings and if not prohibited by local or State laws, regulations, ordinances, or by the fire marshal. Salvaged materials shall become the property of the Contractor. Selling of merchantable material and removal by the purchaser shall be done only during daylight working hours and accompanied

102.04 Measurement and Payment

Buildings to the Engineer prior to beginning work. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Removal and Disposal of Existing Buildings will not be measured but will be paid for at the Contract lump sum price. The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work. Buildings not designated for removal and disposal in the Contract Documents will not be measured but the cost will be incidental to Section 101. The Administration reserves the right to eliminate from this item any or all buildings or structures. For each building eliminated from this item, the item will be credited to the extent of the cost eliminated, which will be determined from a breakdown submitted by the Contractor showing the tabulation of individual unit costs used in arriving at the Contract price for this item. Submit a breakdown of the Contract lump sum price for Removal and Disposal of Existing 103 — ENGINEERS OFFICE CATEGORY 100 PRELIMINARY SECTION 103 — ENGINEERS OFFICE

103.01 Description

Furnish, clean, and maintain in good condition an Engineers Office at an approved location within the immediate vicinity of the project. The office shall be separate from any offices used by the Contractor, and it and all items therein shall be for the exclusive use of the Administration’s Engineers and Inspectors. Rented properties conforming to the type of office specified in the Contract Documents will be acceptable.

103.02 Materials

Not applicable.

103.03 Construction

Set up, equip, and make the office ready for use as approved by the Engineer at least five days prior to commencement of other work on the project. When an Engineers Office is not specified, have the computer system ready for use at least five days prior to the start of any work on the project. Leave the office and components in place until all field records are complete. Protect the Administration and Administration employees from any loss or damage to their property stored in the Engineers Office. Provide protection in the amount of twenty thousand ($20 000) dollars, nondeductible, per each occurrence, for loss or damage due to fire, theft, vandalism, storms, floods, or any combination thereof. Complete the reimbursement, replacement, or repair within 30 days from the date the Engineer reports the loss. If facilities, equipment, or services become defective, are stolen, or for other reasons do not function as intended, repair or replace with an equal or better unit within one business day after notification by the Engineer at no additional cost to the Administration. Unless otherwise specified, the office and all furnished equipment and accessories shall become the property of the Contractor at the completion of the project. Upon removal of the office, restore the location to a condition acceptable to the Engineer. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS

Source: Maryland Standard Specifications for Construction and Materials, 2025 Edition. Pages 141142 of 1,113.