CATEGORY 300 DRAINAGE SECTION 303 — PIPE CULVERTS
303.01 Description
Furnish and install pipe culverts, make connections to miscellaneous structures and other pipe culverts, reinstall existing pipes, remove existing pipe culverts, abandon existing pipes, and clean existing pipes.
303.02 Materials
No. 57 Aggregate 901.01 Crusher Run Aggregate CR-6 901.01 Curing Compound 902.07.03 Portland Cement Concrete 902.10, Mix No. 2 Grout 902.11 Controlled Low Strength Material 902.16 Brick 903.03 Mortar 903.06 Pipe Section 905 Select Borrow 916.01 Common Borrow 916.01 Stormwater Management (SWM) Facility Embankment Clay Core Borrow 916.01 Water 921.01 Detectable Utility Marking Tape 921.11 Bedding. Use earth meeting the requirements of M 145, A-1, A-2-4, A-2-5 or A-3. The maximum particle size is 1.25 in. Do not use organic material, stones larger than 1.5 in., or frozen lumps. Selected Backfill may be used. Backfill. Use material meeting the requirements for Select Borrow, Selected Backfill or Controlled Low Strength Material (Flowable Backfill). Large lumps, clods, frozen material, or rocks are not acceptable. For plastic pipe installations, use backfill materials meeting the requirements of M 145, A-1, A-2-4, A-2-5, or A-3. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
303.03 Construction
303.03.01 Pipe Culvert Installation
When endwalls are visible from the roadway, construct them parallel to the roadway with the askew pipe protruding through the end wall. If not visible, construct them normal to the center line of the pipe. Clean existing pipes and dispose of the material. Trench Excavation. When a pipe is to be laid on existing ground, on or under fill, construct embankment to a height of at least 9 in., but not more than 3 ft above the proposed top of the pipe. Excavate to a depth at least 4 in. below the bottom of pipe. When rippable rock is encountered, remove rocks, boulders, and other hard, lumpy, or unyielding material to a depth of at least 12 in. below the bottom of the outer diameter of the pipe. When non-rippable rock is encountered, remove it to a depth of at least 8 in. below the outer diameter of the pipe. Handle excavated material as specified in 402.03.01. Ensure trench width is at least twice the outside diameter of the pipe or the outside diameter plus 18 in. on each side, whichever is less. Ensure trench sides are vertical up to at least the midpoint of the pipe to be installed.
303.03.02 Mid-Pipe Pipe Culvert Connections. Pipe connections may be either prefabricated
or constructed in the field. Use a prefabricated connection unless specified or directed. For reinforced concrete pipes connecting to other reinforced concrete pipes, a field pipe connection includes cutting a hole in one pipe, inserting and trimming the connecting pipe, and placing a concrete collar using Concrete Mix No. 2 at the connection. Finish the connection to provide a smooth surface. For corrugated metal pipes, a welded connection may be substituted for the concrete collar when the connection is to other corrugated metal pipes. Coat the weld with a zinc rich paint coating according to M 36. For connections to drainage structures, refer to 305.03.05. For plastic pipes, use a prefabricated plastic connection matching the pipe material. When dissimilar pipe materials are encountered, use a junction box as specified in Section 305. 303.03.03 Pipe Culvert Encasement. When specified, encase pipes using Concrete Mix No. 2.
303.03.04 Removal of Existing Pipe Culverts. When specified, remove and dispose of existing
pipe culverts. Use backfill material that is similar to the adjacent material and compact as specified in Section 208, Section 210, or Section 701, whichever is applicable.
303.03.05 Reinstallation of Existing Pipe Culverts. When specified, remove, salvage, and
reinstall pipe culverts as specified in 303.03.01. 303.03.06 Abandoned Pipe Culverts. Plug abandoned pipe culverts using Concrete Mix No. 2 or brick masonry as specified in 463.03. Fill pipes with Flowable Backfill as specified in Section 314. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
303.03.07 Clean Existing Pipe Culverts. When specified, clean existing pipe culverts, removing
all sediment and debris without damaging the pipe, pipe joints, or connecting structures. Remove and dispose of sediment and debris as specified in Section 308.
303.04 Measurement and Payment
The payment will be full compensation for all applicable excavation, sheeting, shoring, dewatering, hauling, storing, rehandling of material, removal and disposal of excess and unsuitable material, tamped fill, forming bed, foundation, grouting, masonry, bedding, pipe, backfill, compaction, inspection, and for all material, labor, equipment, tools, and incidentals necessary to complete the work.
303.04.01 New pipe culverts will be measured complete in place and paid for at the Contract unit
price per linear foot for the pertinent size and type of pipe. When a new pipe is installed in the same location as an existing pipe, the cost of removal and disposal of the existing pipe, including end walls and end sections, will not be measured but the cost will be incidental to the Contract price of new pipe. Detectable utility marking tape will not be measured but will be incidental to the Contract price of pertinent pipe item.
303.04.02 Pipe connections will be measured and paid for at the Contract unit price per each for
the pertinent size and type of pipe connection. No deduction from the new pipe measurement will be made for pipe connections. Connections to drainage structures with prefabricated holes in which the pipe will be connected with grout or mortar will not be measured, but the cost will be incidental to the pertinent pipe culvert item.
303.04.03 Pipe elbows will be measured and paid for at the Contract unit price per each for the
pertinent size and type of pipe elbow.
303.04.04 Excavation required below the planned elevation will be measured and paid for as
specified in 301.04.
303.04.05 Selected Backfill will be measured and paid for as specified in Section 302.04. 303.04.06 Flowable Backfill will be measured and paid for as specified in Section 314.04. 303.04.07 Select Borrow will be measured and paid for as specified in Section 203.04. 303.04.08 Common Borrow will be measured and paid for as specified in Section 203.04. 303.04.09 Pipe Bedding Backfill will be measured and paid for at the Contract unit price per cubic
yard.
303.04.10 Stormwater Management (SWM) Facility Embankment Clay Core Borrow will be
measured and paid for at the Contract unit price per cubic yard. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
303.04.11 Pipe culvert encasement will be measured and paid for at the Contract unit price per
cubic yard of Mix 2 Concrete for Miscellaneous Structures.
303.04.12 Removal of Existing Pipe will be measured and paid for at the Contract unit price per
linear foot. The size and type of pipe will not be measured but will be incidental to the Contract unit price. Removal of existing end walls and existing end sections associated with the pipe will not be measured but the cost will be incidental to the Contract price.
303.04.13 Reinstallation of existing pipe culverts will be measured and paid for at the Contract
unit price per linear foot for Relaid Existing Pipe Culverts Any Size. The size and type of pipe will not be measured but will be incidental to the Contract price.
303.04.14 Abandoned pipe culverts will be measured and paid for at the Contract unit price per
cubic yard for Flowable Backfill for Pipe Abandonment.
303.04.15 Plugs for abandoned pipe culverts and plugs to create a permanent blockage of the flow
of water will be measured and paid for at the Contract unit price per cubic yard of Mix 2 Concrete for Miscellaneous Structures or Brick Masonry for Miscellaneous Structures.
303.04.16 Cleaning existing pipe culverts will be measured and paid for at the Contract unit price
per linear foot for Clean Existing Pipe Any Size. The size and type of pipe will not be measured but will be incidental to the Contract price. Removal of construction debris and sediment will not be measured for payment. 304 — STRUCTURAL PLATE PIPE AND STRUCTURAL PLATE PIPE ARCH CULVERTS CATEGORY 300 DRAINAGE SECTION 304 — STRUCTURAL PLATE PIPE AND STRUCTURAL PLATE PIPE ARCH CULVERTS
304.01 Description
Furnish and install structural plate pipe and structural plate pipe arch culverts.
304.02 Materials
No. 57 Aggregate 901.01 Crusher Run Aggregate CR-6 901.01 Curing Compound 902.07.03 Portland Cement Concrete 902.10, Mix No. 2 Structural Plate for Pipe and Pipe Arches Section 905 Detectable Utility Marking Tape 921.11
304.03 Construction
304.03.01 Fabrication. Submit working drawings, including erection diagrams and strutting
tables, for approval. Include proposed lengths and lifting locations of preassembled sections in the erection diagrams. Upon approval, shop fabricate the plates, including all required holes, to the required dimensions. Ship the plates complete, with proper markings and all necessary connection devices. Ensure the plate configurations have radii and curvature according to AASHTO Load and Resistance Factor Design (LRFD) Bridge Design Specifications. When bottom plates of circular pipes are specified to the thicker than top and side plates, cover at least 25 percent of the periphery of the circle with the thicker plate. For pipe arches, the thicker plates include corner plates as well as bottom plates. Lay these culverts on a firm bed, true to the specified line and grade. Along those edges of the plates that will form longitudinal seams in the finished structure, stagger bolt holes in rows 2 in. apart, with one row in the valley and one in the crest of the corrugations unless otherwise specified. Along those edges of the plates that will form circumferential seams in the finished structure, provide a bolt spacing of not more than 12 in. Ensure the diameter of the bolt holes in the longitudinal seams do not exceed the diameter of the bolt by more than 1/8 in. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS