196704 — Temporary Mulch and Temporary Seed

MD · 2025 Standard SpecificationsBook pages 802805View official source ↗

Water 920.09.01 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 700 LANDSCAPING SECTION 704 — TEMPORARY MULCH AND TEMPORARY SEED

704.01 Description

Perform Temporary Mulch and Temporary Seed to provide temporary soil erosion protection as follows. Short-Term Temporary Stabilization. Refer to 704.03.02 and apply Temporary Mulch to stabilize topsoil, subsoil, common borrow, or other specified soil substrate for up to two months after installation. Long-Term Temporary Stabilization. Refer to 704.03.03 and apply Temporary Seed to stabilize topsoil, subsoil, common borrow, or other specified soil substrate for two months to six months after installation. Permanent Stabilization. Refer to Section 705 and perform Turfgrass Establishment when redisturbance is expected in more than six months, or perform other permanent vegetation establishment as specified or as directed. Do not apply Temporary Mulch or Temporary Seed when redisturbance of soil is expected in more than six months. Performance of Temporary Mulch and Temporary Seed as specified herein complies with all requirements of the Maryland Department of the Environment for temporary stabilization of soils.

704.02 Materials

Fertilizer 37-0-0 (SCU) 920.03.01 Straw Mulch 920.04.01 Wood Cellulose Fiber Mulch 920.04.02 Soil Stabilization Matting 920.05.01 Fasteners 920.05.02 SHA Temporary Seed Mix 920.06.07(c)

704.03 Construction

704.03.01 General.

a.Schedule. Apply Temporary Mulch and Temporary Seed any time of the year.
b.Nutrient Management Plan (NMP). The fertilizer application rate specified in Table 2 of 704.03.03 shall be the NMP rate for Temporary Seed unless the Administration develops a NMP to revise the application rate.
c.Nutrient Management Reporting. Record the location and details of fertilizer applications on the Nutrient Management Reporting Form. Submit the Form within 24 hours after applying fertilizer.

704.03.02 Temporary Mulch. Refer to Description. Temporary Mulch may be either temporary

straw mulch or temporary matting mulch.

a.Selection of Temporary Mulch. Apply temporary straw mulch or temporary matting mulch to provide temporary erosion protection in flat or mildly sloping areas. Apply temporary matting mulch to provide temporary erosion protection in slopes or channels where flowing water may dislodge temporary straw mulch.
b.Temporary Straw Mulch. Lightly smooth excessively rough areas, but do not till the soil. Immediately apply straw and cover with wood cellulose fiber. Apply materials as follows. TEMPORARY MULCH AND TEMPORARY SEED TABLE 1 - APPLICATION RATES - TEMPORARY STRAW MULCH MATERIAL LB PER yd2 LB PER ACRE Straw Mulch 0.826 4000 Wood Cellulose Fiber Mulch 0.155 750 Cover at least 90 percent of the soil surface with straw mulch. When applied with mulch blower, apply straw mulch to a loose depth of 3/4 in. to 2 in. When applied by hand, apply straw mulch to a loose depth of 1-1/2 in. to 3 in. Secure straw mulch immediately after the completion of mulching operations by applying wood cellulose fiber uniformly over the straw without displacing the mulch. Do not operate machinery during windy weather that may interfere with uniform application. Do not allow materials to blow onto sensitive areas or structures. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
c.Temporary Matting Mulch. Select Type A, Type B, Type D, or Type E soil stabilization matting for installation in areas that will be redisturbed within two months. Install any of these matting types using methods and fasteners as specified in Section 709 for Type E Soil Stabilization Matting. Smooth the soil surface to allow uniform installation of matting. Install matting over the soil surface without tenting. Overlap edges of the matting at least 2 in. Install fasteners no more than 24 in. apart along edges, overlaps, and throughout the matting to firmly secure the matting to the soil surface. Do not water the matting. Remove matting and fasteners before performing permanent vegetation establishment. When approved, matting and fasteners may be removed and reused as Temporary Mulch in the same or different locations when their integrity is not degraded by damage or decomposition.

704.03.03 Temporary Seed. Refer to Description. Prepare the soil and apply seed, fertilizer,

straw mulch, and wood cellulose fiber mulch to areas that will remain undisturbed for two months to six months. Complete grading and shaping operations as directed. Perform operations when soil moisture and weather conditions are suitable. Cease operations when soil is frozen, or conditions are unsuitable. Loosen soil surfaces before applying seed and fertilizer. Refer to 705.03.06(b) through 705.03.06(d) regarding application equipment, and apply fertilizer materials according to Table 2 at any time of the year. Immediately apply straw and wood cellulose fiber over seeded and fertilized areas as specified in

704.03 02(b).

Refer to 704.03.02(b) and install Type A, Type D, or Type E soil stabilization matting in lieu of straw and wood cellulose fiber when approved. TEMPORARY MULCH AND TEMPORARY SEED TABLE 2 - APPLICATION RATES - TEMPORARY SEED MATERIAL LB PER yd2 LB PER ACRE SHA Temporary Seed Mix 0.026 125 Fertilizer 37-0-0 (SCU) 0.021 100 Straw Mulch 0.826 4000 Wood Cellulose Fiber Mulch 0.155 750

704.03.04 Repair. Repair Temporary Mulch or Temporary Seed that is defective before

Acceptance.

704.03.05 Acceptance. Submit a request for Acceptance when operations are completed.

Inspection will be conducted to verify completion. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS

704.03.06 Disturbance, Removal and Replacement.

a.Do not disturb or remove Temporary Mulch or Temporary Seed except as necessary to prepare soil, or to install permanent vegetation, or to perform other work as directed.
b.Replace Temporary Mulch with approved materials when it has degraded, or when more than 2 months have elapsed since Acceptance. Replace Temporary Mulch as additional work when directed.
c.Replace Temporary Seed with approved materials when it has degraded, or when more than 6 months have elapsed since Acceptance. Replace Temporary Seed as additional work when directed.

704.04 Measurement and Payment

Temporary Mulch and Temporary Seed will be measured and paid for at the Contract unit price for one or more of the specified items. The payment will be full compensation for all material, labor, equipment, tools, disposal fees and incidentals necessary to complete the work.

704.04.01 Temporary Mulch, applied as either temporary straw mulch or temporary matting

mulch, will be measured and paid for at the Contract unit price per square yard. Any soil stabilization matting which may be installed as temporary matting mulch will be incidental to the Contract unit price for Temporary Mulch, and will not be measured and paid for.

704.04.02 Temporary Seed will be measured and paid for at the Contract unit price per square

yard. Any soil stabilization matting which may be installed with Temporary Seed will be incidental to the Contract unit price for Temporary Seed, and will not be measured and paid for.

704.04.03 Turfgrass Establishment will be measured and paid for at the Contract unit price per

square yard. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS 705 — TURFGRASS ESTABLISHMENT 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 700 LANDSCAPING SECTION 705 — TURFGRASS ESTABLISHMENT

705.01 Description

Perform Turfgrass Establishment as follows. At Final Grade. For areas that are at final grade, establish turfgrass in topsoil or other specified soil substrate to provide permanent vegetation groundcover. Not Final Grade. For areas that are not at final grade, or areas that will not be redisturbed for at least six months after seeding operations are completed, establish turfgrass in topsoil, subsoil, common borrow, or other specified soil substrate to provide temporary vegetation groundcover. Temporary Stabilization. When it is not possible to perform Turfgrass Establishment, refer to Section 704 and perform Temporary Mulch or Temporary Seed, or as directed. Performance of Turfgrass Establishment as specified herein complies with all requirements of the Maryland Department of the Environment for permanent seeding.

705.02 Materials

Fertilizer 920.03.01 Straw Mulch 920.04.01 Wood Cellulose Fiber 920.04.02 Seed 920.06 SHA Turfgrass Seed Mix 920.06.07(a) SHA Special Purpose Seed Mix 920.06.07(b) SHA Temporary Seed Mix 920.06.07(c) Water 920.09.01

705.03 Construction

705.03.01 General.

a.Regions. Maryland is divided into Regions by counties as follows: Region 1. Garrett, Allegany, and Washington, west of Clear Spring MD.
Source: Maryland Standard Specifications for Construction and Materials, 2025 Edition. Pages 802805 of 1,113.