Water 920.09.01 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 700 LANDSCAPING SECTION 704 — TEMPORARY MULCH AND TEMPORARY SEED
704.01 Description
Perform Temporary Mulch and Temporary Seed to provide temporary soil erosion protection as follows. Short-Term Temporary Stabilization. Refer to 704.03.02 and apply Temporary Mulch to stabilize topsoil, subsoil, common borrow, or other specified soil substrate for up to two months after installation. Long-Term Temporary Stabilization. Refer to 704.03.03 and apply Temporary Seed to stabilize topsoil, subsoil, common borrow, or other specified soil substrate for two months to six months after installation. Permanent Stabilization. Refer to Section 705 and perform Turfgrass Establishment when redisturbance is expected in more than six months, or perform other permanent vegetation establishment as specified or as directed. Do not apply Temporary Mulch or Temporary Seed when redisturbance of soil is expected in more than six months. Performance of Temporary Mulch and Temporary Seed as specified herein complies with all requirements of the Maryland Department of the Environment for temporary stabilization of soils.
704.02 Materials
Fertilizer 37-0-0 (SCU) 920.03.01 Straw Mulch 920.04.01 Wood Cellulose Fiber Mulch 920.04.02 Soil Stabilization Matting 920.05.01 Fasteners 920.05.02 SHA Temporary Seed Mix 920.06.07(c)
704.03 Construction
704.03.01 General.
704.03.02 Temporary Mulch. Refer to Description. Temporary Mulch may be either temporary
straw mulch or temporary matting mulch.
704.03.03 Temporary Seed. Refer to Description. Prepare the soil and apply seed, fertilizer,
straw mulch, and wood cellulose fiber mulch to areas that will remain undisturbed for two months to six months. Complete grading and shaping operations as directed. Perform operations when soil moisture and weather conditions are suitable. Cease operations when soil is frozen, or conditions are unsuitable. Loosen soil surfaces before applying seed and fertilizer. Refer to 705.03.06(b) through 705.03.06(d) regarding application equipment, and apply fertilizer materials according to Table 2 at any time of the year. Immediately apply straw and wood cellulose fiber over seeded and fertilized areas as specified in
704.03 02(b).
Refer to 704.03.02(b) and install Type A, Type D, or Type E soil stabilization matting in lieu of straw and wood cellulose fiber when approved. TEMPORARY MULCH AND TEMPORARY SEED TABLE 2 - APPLICATION RATES - TEMPORARY SEED MATERIAL LB PER yd2 LB PER ACRE SHA Temporary Seed Mix 0.026 125 Fertilizer 37-0-0 (SCU) 0.021 100 Straw Mulch 0.826 4000 Wood Cellulose Fiber Mulch 0.155 750
704.03.04 Repair. Repair Temporary Mulch or Temporary Seed that is defective before
Acceptance.
704.03.05 Acceptance. Submit a request for Acceptance when operations are completed.
Inspection will be conducted to verify completion. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
704.03.06 Disturbance, Removal and Replacement.
704.04 Measurement and Payment
Temporary Mulch and Temporary Seed will be measured and paid for at the Contract unit price for one or more of the specified items. The payment will be full compensation for all material, labor, equipment, tools, disposal fees and incidentals necessary to complete the work.
704.04.01 Temporary Mulch, applied as either temporary straw mulch or temporary matting
mulch, will be measured and paid for at the Contract unit price per square yard. Any soil stabilization matting which may be installed as temporary matting mulch will be incidental to the Contract unit price for Temporary Mulch, and will not be measured and paid for.
704.04.02 Temporary Seed will be measured and paid for at the Contract unit price per square
yard. Any soil stabilization matting which may be installed with Temporary Seed will be incidental to the Contract unit price for Temporary Seed, and will not be measured and paid for.
704.04.03 Turfgrass Establishment will be measured and paid for at the Contract unit price per
square yard. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS 705 — TURFGRASS ESTABLISHMENT 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 700 LANDSCAPING SECTION 705 — TURFGRASS ESTABLISHMENT
705.01 Description
Perform Turfgrass Establishment as follows. At Final Grade. For areas that are at final grade, establish turfgrass in topsoil or other specified soil substrate to provide permanent vegetation groundcover. Not Final Grade. For areas that are not at final grade, or areas that will not be redisturbed for at least six months after seeding operations are completed, establish turfgrass in topsoil, subsoil, common borrow, or other specified soil substrate to provide temporary vegetation groundcover. Temporary Stabilization. When it is not possible to perform Turfgrass Establishment, refer to Section 704 and perform Temporary Mulch or Temporary Seed, or as directed. Performance of Turfgrass Establishment as specified herein complies with all requirements of the Maryland Department of the Environment for permanent seeding.
705.02 Materials
Fertilizer 920.03.01 Straw Mulch 920.04.01 Wood Cellulose Fiber 920.04.02 Seed 920.06 SHA Turfgrass Seed Mix 920.06.07(a) SHA Special Purpose Seed Mix 920.06.07(b) SHA Temporary Seed Mix 920.06.07(c) Water 920.09.01