CATEGORY 500 PAVING SECTION 524 — DOWEL BAR RETROFIT
524.01 Description
Place load transfer devices or dowel bars between two slabs in an existing Portland Cement Concrete (PCC) Pavement. Place dowel bars into slots cut across cracks or joints and backfilling with grout.
524.02 Materials
524.02.01 Plain Reinforcement. Dowel bars used as ties in PCC pavement expansion and contraction joints shall be plain round steel bars conforming to A615, Grade 60 or A36 unless otherwise specified. Bars shall be epoxy coated using epoxy powder conforming to 917.02. Each dowel bar shall be coated with a water insoluble lubricant as approved.
524.02.02 Expansion Caps. Use tight-fitting, commercial quality end caps made of a non-
metallic, non-organic material that allows for 1/4 in. of movement at each end of the dowel bar. 524.02.03 Dowel Bar Support Chairs. Chairs for supporting the dowel bars shall be either completely epoxy-coated steel conforming to A 884 or fabricated of commercial quality nonmetallic, non-organic material. The dowel bar chairs shall firmly hold the dowels centered in the slots during the fast setting grout backfill operations. Dowel chairs shall be designed to hold the bar a minimum of 1/2 in. above the bottom of the slot while the fast setting grout backfill is placed and consolidated.
524.02.04 Foam Core Insert . Use 3/8 in. thick foam core inserts to re-establish the joint or crack
and allow each side of the slot to expand and contract. The inserts shall consist of rigid Styrofoam material or closed cell foam, faced with poster board or plastic material. The width of the foam board in its final position shall be 1/16 in. wider than the slot to minimize movement of the foam board and prevent incompressible material from entering the contraction joint during concrete placement. The width of the foam core board may need to be increased for pavements with skewed cracks or joints.
524.02.05 Grout Material. Refer to 902.14. Use Class II or Class III Rapid Hardening
Cementitious Material to backfill the dowel bars. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
524.03 Construction
524.03.01 Equipment.
524.03.02 Cleaning. Clear the area of all cuttings and other material after the saw cutting and jack
hammering are complete. Clean the slot of all foreign material and remove from the job site. Sand blasting equipment may be used to remove all foreign material from the exposed surfaces. Provide a cleaned concrete surface free of spalls, latence, and all contaminants detrimental to achieving an adequate bond.
524.03.03 Dowel Bar Installation. Install the dowel bars in the existing PCC pavement as
specified in the Contract Documents and as follows:
524.04 Measurement and Payment
Dowel Bar Retrofit will be measured and paid for at the Contract unit price per each dowel bar placed and accepted. The payment shall be full compensation for saw cutting, jack hammering, dowel bars, form core, chairs, grout, expansion caps, clearing and hauling waste material, and for all equipment, material, labor, and all incidentals necessary to complete the work. Repair or replace dowel bar retrofits that are non-functioning or damaged at no additional cost to the Administration. 525 — PORTLAND CEMENT CONCRETE SPALL REPAIR CATEGORY 500 PAVING SECTION 525 — PORTLAND CEMENT CONCRETE SPALL REPAIR
525.01 Description
Repair spalled areas at various locations as specified in the Contract Documents or as directed. Spalling consists of small areas of cracking, breaking, chipping, or fraying of Portland Cement Concrete (PCC) slabs that typically occur within 2 ft of the edge of joints. Some spalling may occur in the middle of the slab away from the joints.
525.02 Materials
Rapid Hardening Cementitious Materials for Concrete Pavement Repair Portland Cement Concrete Mix #9 using No 7 aggregate Epoxy Adhesive 902.14 902.10 921.04
525.03 Construction
Repair spalled areas according to the following.