CATEGORY 400 STRUCTURES SECTION 440 — PRESTRESSED CONCRETE BEAMS AND SLAB PANELS
440.01 Description
Furnish and place prestressed concrete beams and slab panels, elastomeric bearing pads, bearing plates and other embedded items, all steel strands, jacks, and other required devices. The concrete overlay riding surface for slab panel bridges is included in this work.
440.02 Materials
Fine Aggregate 901.01 Coarse Aggregate 901.01 Fine Aggregate for Overlay Bonding Grout 901.01, Fine Aggregate/Sand Mortar and Epoxies Cement 902.03 and 902.04 Admixtures: Air Entraining 902.06.01 Retarding 902.06.02 Water Reducing 902.06.02 , 902.06.03 Pozzolans 902.06.04 , 902.06.05 Concrete Overlay 902.10, Mix No. 8 Nonshrink Grout 902.11(c) Self-Consolidating Concrete 902.17 Reinforcing Steel 908.01 Welded Steel Wire Fabric 908.05 Prestressing Strand 908.11 Elastometric Bearing Pads 910.02 Closed Cell Neoprene Sponge Elastomer 911.10 Production Plants Section 915 Fusion Bonded Epoxy Powder Coating for Steel 917.02 Water 921.01 Epoxy Adhesive 921.04 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Threaded Tie Rods A722 Tie Rod Heavy Hex Nuts Supplied by tie rod manufacturer; shall provide full tensile strength of tie rod Concrete Protective Coatings Contract Documents Concrete Chloride Content Contract Documents Chloride Ion Content Contract Documents Epoxy Protective Coatings 917.01 Epoxy Grout 902.11(d)
440.02.01 Self Consolidating Concrete, (SCC). The Contract Documents shall specify cylinder
strength of the concrete at 28 days, required cylinder strength of the concrete at transfer of the tensioning load and the time when forms may be removed. Ensure that the composition, proportioning, and mixing of concrete produces a homogeneous concrete mixture of a quality that meets the specified material and design requirements. Prior to start of fabrication submit all SCC mix design sources for approval. The manufacturer shall furnish certifications as specified in TC-1.03.
440.02.02 Reinforcing Steel and Tie Rod Tubes. Except for prestressing strands, epoxy coat all
reinforcing steel in and extending from beams and slab panels, and in the concrete overlay. Tie rod tubes shall consist of corrugated, rigid or semi-rigid type, galvanized steel sheathing, or rigid plastic sheathing.
440.02.03 Debonding Material. Use solid or split plastic sheathing having a thickness of at least
0.025 in. for debonding of pretensioning steel strands. 440.02.04 Joint Sealers. According to the manufacturer’s specifications.
440.03 Construction
440.03.01 Working Drawings. Refer to Section 499. Address reinforcing, anchorages, steel
strand profiles, lifting inserts, and all other pertinent information. If methods other than specified are proposed, submit changes as specified in Section 499. When proposed changes are accepted or rejected, construct members accordingly at no additional cost to the Administration.
440.03.02 Prestressed Concrete Plants. The prestressed concrete manufacturing plant shall be
registered and certified under the Precast/ Prestressed Concrete Institute Program. Submit a valid certificate to the Engineer prior to the start of production.
440.03.03 Beds and Forms. Support casting beds on unyielding foundations. Clean the beds and
forms after each use. Prevent accumulation of bond breakers. Prior to stringing steel strands, inspect the bottom of forms for cleanliness and alignment. Coat the contact surfaces of forms with bond breaker that dries to a surface hardness. Ensure that the coating is dry to prevent contamination of the steel strand. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
440.03.04 Meetings. Conduct a pre-pour meeting prior to beginning any prestress concrete work.
Ensure a representative of the prestress concrete plant is present.
440.03.05 Protection of Prestressing Steel Strand. Store under shelter and keep it free of
deleterious material such as grease, oil, wax, dirt, paint, loose rust, or other similar contaminants. Do not use steel showing corrosion, etching, pitting, or scaling. A light coating of surface rust is acceptable if it can be removed completely from the steel by wiping with a cloth. Do not store on a surface that contributes to galvanic or battery action. Do not use steel strand as a ground for electric welding. Protect it from electric welding sparks. 440.03.06 Reinforcing Steel, Inserts, and Chairs. Place reinforcing steel within the specified tolerances, and secure it to beds and forms using chairs, blocking, or ties. Fabricate cages of bars by tying only. Do not support cages by tensioned strands. Bend tie wire ends into the slab panel. Show the type and placement of inserts on the working drawings. Except for stainless steel accessories, recess form ties, chairs, and inserts in the concrete by at least 1 in.
440.03.07 Methods of Force Measurement. Use one of the following methods as the primary
measuring system. Check it by using one of the other methods as a secondary measuring system:
440.03.08 Stringing Steel Strands. Do not reuse strands containing former vise grip points unless
the points are outside the new vise locations. Do not reuse strands that have been draped. All steel strands shall have the same lay or direction of twist. Use shears or abrasive cutting wheels to cut the ends. Position over chairs to eliminate sagging of strands in the bottom rows.
440.03.09 Steel Strand Splices. Only one splice is permitted per strand. For single strand
tensioning, the number of strands that may be spliced in each bed is not restricted. For multiple strand tensioning, either splice all strands and adjust the elongation for average slippage, or no splices are permitted.
440.03.10 Steel Strand Vises. Use vises capable of anchoring stressing loads positively with
minimum slippage and which are cleaned, lubricated, and inspected between each use. Do not use grips that show wear or distortion, or that allow slippage in excess of 1/4 in. Clean and inspect the full set of vises before starting each prestressing operation. The maximum permissible time for holding tensioned strands in the bed before placing concrete is 72 hours. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
440.03.11 Wire Failure in Steel Strands. Remove and replace any seven wire steel strand that
contains a broken wire. Check all strands for wire breakage before placing concrete.
440.03.12 Pretensioning. Apply the specified total load to each strand. Apply the load as a total
of two loading stages. The initial load shall straighten the strand, eliminate slack, and provide a starting or reference point for measuring elongation. Limit the initial load to 10 percent of the specified tensioning force. Receive approval from the Engineer for any initial loading exceeding 10 percent (i.e. multiple bed casting). Measure the initial load within a tolerance of ± 100 lb. Do not use the initial elongation measurement to determine the initial force. In all stressing operations, keep the stressing force symmetrical about the vertical axis; however, in tensioning single strands, the initial and final loads may be applied in immediate succession to each strand. Use jack mounted pressure gauges as the primary system of force measurement for the final tensioning of straight single strands. Check elongation against pressure gauge readings on all strands. Check vise slippage. The computed elongation, including operational losses and equivalent elongation for the initial tensioning force, shall agree with the pressure gauge reading within 3 percent. Use jack mounted pressure gauges as the primary system of force measurement for the final tensioning of multiple strands. For uniform application of load to the strands, place the position of the face of the anchorage at final load parallel to its position under initial load. Verify parallel movement by measurement of equal movement on opposite anchorage sides and by checking the plumb position of the anchorage before and after final load application. Check vise slippage. After stressing the steel strands as specified and placing all other reinforcement, cast the concrete member to the specified length. Maintain strand stress between anchorages until the concrete has reached the specified compressive strength.
440.03.13 Steel Strand Tensioning. In all methods of tensioning, measure the stress induced in
the strands both by jacking gauges and by elongation. Recalibrate any jack or gauge that appears to be giving erratic results or gauge pressures and elongations indicate materially different stresses during manufacturing. Provide means for measuring elongation to the nearest 1/8 in. For differences in indicated stress between jack pressure and elongation of up to 5 percent, place the difference so that the discrepancy will be on the side of a slight overstress rather than understress. For discrepancies in excess of 5 percent, carefully check the entire operation and determine the source of the discrepancy before proceeding. Thoroughly seal split plastic sheathing for debonded steel strands with tape prior to placing concrete. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
440.03.14 Surface Finish and Curing.
440.03.14 01 Surface Finish.
440.03.14 02 Curing.
440.03.15 Detensioning.
440.03.16 Camber. Clearly and permanently identify all beams so that the camber readings taken
as indicated below can be associated with the proper beam. Take camber readings as follows, in the presence of the Engineer.
440.03.17 Tolerances. The tolerances for each beam or slab panel shall be as shown in Tables
440.03.17 A or B, respectively unless otherwise specified:
TABLE 440.03.17A PRESTRESSED CONCRETE BEAM TOLERANCE Depth (overall) ± 1/4 in. Width (flanges & fillets) ± 1/4 in. Width (web) ± 1/4 in. Length of Beam ± 1/8 in. per 10 ft or 1/2 in. whichever is greater Exposed Beam Ends (deviation from square or designated skew) Horizontal ± 1/4 in. Vertical ± 1/8 in. per ft of beam height Side Inserts (spacing between center of inserts and from the centers of inserts to the ends of the beams) ± 1/2 in. Bearing Plate (spacing from the centers of bearing plates to the ends of the beams) ± 1/2 in. Stirrup Bars: Average of all bars Individual bar longitudinal spacing ± 1/2 in. ±1 in. Horizontal Alignment (deviation from a straight line parallel to the center line of beam) 1/8 in. per 10 ft max Camber Differential between adjacent beams of same type and steel strand pattern 1/8 in. per 10 ft at time of erection or 1/2 in. max Center of Gravity of steel strand group ± 1/4 in. Center of Gravity of depressed group steel strand at end of beam ± 1/2 in. Position of hold down points for depressed strand ± 6 in. Camber deviation from plan camber, as measured at release or at beginning of beam storage at the fabricating plant ±50% of plan camber or ±1/2 in. whichever is greater TABLE 440.03.17B PRESTRESSED CONCRETE SLAB PANEL TOLERANCE Depth (overall) ±1/2 in., -1/4 in. Width (overall) ±0 in., -1/2 in. Slab Panel Length @ center line (based on design length specified) ±1/2 in. Horizontal Alignment (deviation from a straight line parallel to the slab panel center line) ¼ in. max Horizontal Misalignment of adjacent panel sections ½ in. max Camber Deviation from specified camber, as measured at prestress transfer or at the beginning of slab panel storage at the fabrication plant ±1/2 in. Location of each strand ±1/8 in. Center of Gravity of strand group ±1/4 in. Stirrup Bars (longitudinal spacing) ±1 in. Longitudinal Position of handling devices ±3 in. Concrete Bearing Area (variation from plane surface when tested with a straightedge through middle half of slab panel ±1/8 in. Tie Rod Tubes (spacing between the tube centers and from tube centers to slab panel ends) ±1/2 in. Tie Rod Tubes (spacing from tube center to slab panel bottom) ±3/8 in. Threaded Inserts (spacing between the center of inserts and from center of inserts to ends of slab panels) ±1/2 in. Skew Ends (deviation from designated skew) ±1/2 in. Vertical ends (deviation from specified dimension) ±3/8 in. Camber deviation from plan camber, as measured at release or at beginning of beam storage at the fabricating plant ±50% of plan camber or ±1/2 in. whichever is greater
440.03.18 Slab Panel Plant Assembly. Before shipping the slab panel units to the job site,
assemble all slab panels in the presence of the Engineer for the entire bridge width. This requirement is essential to ensure that the overall bridge width is within the specified tolerances and that there is no misalignment. Any misalignment of the holes will be cause for rejection of the affected slab panels. Do not drill or core holes into the slab panels.
440.03.19 Marking, Handling, Shipping, and Storage. Mark each member with an erection
mark for identification, weight marks for beams 6000 lb or more, and inspection stamps. For beams, paint the erection marks on the top surface of the top flange. Do not place markings of any kind on any surface of a beam that will be visible in the completed structure. Mark slab panels with an individual, consecutive identification mark at a permanently exposed location. The identification mark shall match that shown on the approved working drawings. Furnish an erection diagram clearly indicating erection marks that show the position of the member in the structure. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Utilize the cast-in-place lifting devices and a sufficient number of cranes and spreader beams whenever the prestress concrete members are lifted. Furnish copies of material orders and shipping statements. Show the weight of each individual prestress concrete member. During shipment, ensure that blocking is placed at intervals that will prevent sag and distortion. Ship all members in the upright position, adequately braced and supported to dampen vibrations during transport as shown on the working drawings. Members too long to fit inside of a truck or trailer shall not cantilever beyond the bed more than one quarter of their length. Support members too long to comply with this requirement on dollies, additional vehicles, or other vehicles that will support the long pieces as approved. Load restrictions are as specified in GP 5.10. Do not ship prestress members until approved, at least five days have elapsed since the prestress transfer, and the minimum 28 day compressive strength has been attained. Store beams off the ground in an upright position. Protect them as far as practical from surface deterioration, and keep them free of accumulations of dirt, oil, and other deleterious material.
440.03.20 Erection. Refer to 430.03.27, 430.03.28, 430.03.29, 430.03.31, 430.03.32, and
430.03.33 Slab Panels. Follow the following sequence of operations for the erection of slab panel units.
420.03 09(b) or 420.03.09(d), respectively.
440.03.21 Bearing Pads. Store them at the site on suitable blocking or platforms at least 4 in.
above all surfaces and vegetation. Keep free from vegetation growth and accumulations of dirt, oil, and other foreign material. Coat the surfaces of the concrete bearing areas that will be in contact with the bottom of the bearing pads and the full contact area of the bottom of the bearing pads with epoxy adhesive. Adhere to the manufacturer’s recommendations for mixing and applying the epoxy adhesive material. Applying epoxy adhesive when surface temperatures are at least 50 F with a predicted ambient 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS temperature for the next four hours of 50 F or above. Ensure that the surfaces are clean, dry, and sound. Be prepared to use water jets, abrasive blasting, and air blasting, for satisfactorily cleaning the surfaces. Accurately set the bearing pads in the epoxy adhesive and secure them in place by blocking or other mechanical means until the adhesive sets.
440.03.22 Placing and Finishing Concrete Overlay. Place and finish the overlay as specified in
420.03 including superstructure placement restrictions. Unless otherwise noted on the contract plans, place the entire bridge slab overlay in one continuous
pour. No transverse or longitudinal joints will be permitted. Place the finishing machine’s supporting rails outside the overlay limits. Do not use hold down devices that are shot or drilled into the concrete. Submit plans for anchoring support rails and the concrete placing procedure for approval. Take precautions to secure a smooth riding surface as specified in 420.03.07(d). Prior to placement operations, review the equipment, procedures, and personnel with the Engineer. Place the concrete overlay using the following sequence of operations.
440.04 Measurement and Payment
Prestressed concrete members will not be measured but will be paid for at the Contract lump sum price for the pertinent Prestressed Concrete Beams or Prestressed Concrete Slab Panels item. The payment will be full compensation for all concrete, forms, reinforcing, bearing pads, steel strands, sheathing, steel components, steel rods, inserts, tensioning, grout, bearing assemblies, epoxy adhesive, testing, furnishing, and applying concrete protective coatings when specified, transporting, storage, erection, and for all material, labor, equipment, tools and incidentals necessary to complete the work.
440.04.01 Concrete overlay for the precast concrete slab bridge deck will not be measured but will
be paid for at the Contract lump sum price for the pertinent Superstructure Concrete item. The payment will be full compensation for surface preparation, overlay bonding grout, furnishing, placing, finishing, curing and grooving the concrete overlay; fabricating, coating and placing the epoxy coated welded steel wire fabric or reinforcing steel within the concrete overlay, roadway angle, and for all material, labor, equipment, tools, and incidentals necessary to complete the work. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS 450 — RETAINING WALLS 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 400 STRUCTURES SECTION 450 — RETAINING WALLS
450.01 Description
Construct cast-in-place reinforced concrete footings and stems conforming to the AASHTO definitions of rigid retaining walls. When retaining wall mounted noise barriers are specified, the anchorage assemblies are included in the retaining wall. All components shall be as specified unless prior approval for alternatives is obtained from the Administration. When piles or drilled shafts (caissons) are specified, refer to Sections 410 and 412, respectively. 450.01.01 Preapproved Alternate Retaining Walls. Alternate retaining walls may only be used when specified. Only those retaining walls specified will be permitted. All other retaining walls, even though they are preapproved or have been previously used on Administration projects, are prohibited for use. The Administration will not consider any other alternate retaining walls as a value engineering change proposal. Enforcement. These requirements will be enforced on all projects. Preapproved Alternate Retaining Wall List. Alternate retaining walls are selected from the list of Preapproved Alternate Retaining Walls , which is maintained by the Office of Structures. Procedures for adding products to the prequalified list may be obtained from the Office of Structures. Alternate retaining walls that have been previously used on Administration projects without complying with the preapproval requirements shall be formally submitted through these procedures before they will be added to the Preapproved Lists for consideration to be used on future projects. These and other retaining wall systems may be submitted for addition to the Preapproved Lists, but the Administration will not permit these submittals to be used on an advertised or awarded project. Deviations. Submit any proposed deviation in materials, post size or shape; panel size or shape; reinforcing type, size, or placement from what is shown in the Contract Documents or from the preapproved alternate retaining wall details on file in the Administration’s Office of Structures. All costs for reviews, whether the details are accepted or rejected, shall be borne by the Contractor. Any fabrication or creation of any retaining wall element that is a deviation and is made prior to written approval of the Administration shall be at the risk of the Contractor.