CATEGORY 500 PAVING SECTION 528 — RESURFACING ASPHALT PAVEMENT USING PORTLAND CEMENT CONCRETE
528.01 Description
Resurface existing asphalt pavements with a Portland Cement Concrete (PCC) surface. The location and extent of the resurfacing will be as specified and as directed.
528.01.01 Whitetop Patching (WT Patching). Removal of deteriorated remaining pavement, stone base, or soil after milling and replacing with
concrete.
528.02 Materials
Aggregates 901.01 Concrete Admixtures 902.06 Portland Cement Concrete Whitetopping Mix 902.10 Mix No. WT Rapid Hardening Cementitious Materials for Concrete Pavement Repairs 902.14 Synthetic Fibers 902.15 Joints Section 911 Portland Cement Concrete Plants 915.03
528.03 Construction
Submit the proposed paving plan at least 30 days prior to beginning the work. The plan shall include equipment, milling plan, proposed material sources, and placement methods. Ensure pavement surfaces are protected from all damage. Mix, place, and finish the concrete when natural light is sufficient, or provide adequate artificial lighting as approved.
528.03.01 Pre-pave meeting. Conduct a pre-paving meeting at least three weeks prior to
beginning the work. The meeting shall consist of the following personnel: Contractor, concrete supplier, paving sub-contractor (project manager and onsite foreman/supervisor), traffic control personnel, Project Engineer, lab personnel, and OMT Design Engineer. Provide the meeting minutes to all attendees. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Discuss the following issues during the meeting: work schedule, who is responsible for changes and the approval process for those changes, traffic control, traffic control limits, weather conditions/temperatures, type of equipment for the work, material supply, saw-cutting, curing, protection/transportation of cylinders if being used for opening strength determination, allowable admixtures, material removal, break down procedures, and opening to traffic. Discussions should also cover the following: a plan if the pavement is left too thin after milling, a plan if stone base/soil is encountered during or after milling, mix approval, and how to maintain the designed pavement thickness while paving.
528.03.02 Surface Preparation. Mill the existing pavement before Whitetopping Mix placement
as shown or as directed. After milling clear all debris or other loose material so that the existing pavement can be inspected by the Engineer to determine if WT Patching or RUMR is required. Prior to WT Patching, surface should be free of any dust, contaminants, or loose material that might prevent an adequate bond.
528.03.03 WT Patching. After milling, remove areas showing signs of deterioration as
determined. The condition of the underlying stone base or soil and depth of the removed material will be determined by the Engineer after removal of the deteriorated material.
528.03.04 Removal of Unsuitable Material and Refill (RUMR). Refer to 528.03.03. Remove
the material in these areas to a depth as determined by the Engineer. Compact the underlying stone base or soil then place WT Patching as directed.
528.03.05 Equipment. Refer to 520.03.01. Slip form equipment is not needed. Match curing
may be used. If match curing is to be utilized, the following equipment will be required:
528.03.06 Weather Restrictions. Refer to 520.03.02 for weather restrictions except the
requirement for the temperature as modified herein. Place concrete when the ambient air and surface temperatures are at least 50 F and rising and discontinue when the temperature falls below 45 F.
528.03.07 Forms. Refer to 520.03.04.
2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
528.03.08 Concrete Placement. Refer to 520.03.07, except as follows:
528.03.09 Consolidation of Concrete. Refer to 520.03.08, Fixed Form Paving.
528.03.10 Thickness Check. Refer to 520.03.10, except as follows:
528.03.11 Curing. Refer to 520.03.12. If match curing is used, refer to 528.03.05(a), or as
directed. Cure the concrete for a minimum of 24 hours or until opening to traffic strength (2000 psi) is achieved. The requirement for an approved spraying machine having drive wheels is waived when using the liquid membrane forming compound method.
528.03.12 Joints. Joints shall conform to the details shown and as specified, and perpendicular to
the finished grade of the pavement. Transverse construction and contraction joints shall be straight and continuous from edge to edge of the pavement.
528.03.13 Pavement Surface Diamond Grinding. Refer to Section 509.
528.03.14 Pavement Profile. Refer to Section 535. 528.03.15 Opening to Traffic. The pavement may be opened to vehicular traffic after having
attained a compressive strength of 2000 psi. Prepare the field samples according to PP 54. Test the cylinders on site under observation with a portable testing machine according to T 22. These tests are for determining concrete strength for opening to traffic, not for acceptance.
528.04 Measurement and Payment
Resurfacing Asphalt Pavements Using Portland Cement Concrete will be measured and paid for at the Contract unit price per square yard for the pertinent Portland Cement Concrete Pavement items. The square yard measurement will be computed on the basis of the as-built width and as-built length measured along the pavement center line. The payment will be full compensation for placement of all Portland Cement Concrete, forms, surface preparation, evaporation reducer, curing, joints, joint construction, saw cutting, corrective action due to the Contractor’s negligence, match-cure cylinder testing, measuring pavement thickness, and for all material, labor, equipment, tools, and incidentals necessary to complete the work.
528.04.01 Milling of the existing pavement and removal and disposal of all asphalt millings will
be measured and paid for under separate pay items as specified in Section 508.04.
528.04.02 Portland cement concrete for Whitetop (WT) patching will be measured and paid for at
the Contract unit price per cubic yard.
528.04.03 Removal of deteriorated material, stone base or soil will be measured and paid as
Class 1-A Excavation as specified in Section 201.
528.04.04 Diamond Grinding Portland Cement Concrete Pavement will be measured and paid for
at the unit cost per square yard. The payment will be full compensation for grinding, cleaning the pavement surface, technicians, removal and disposal of all grindings, surface profile testing, corrective action, and for all material, labor, equipment, and incidentals necessary to complete the work.
528.04.05 Pavement Thickness Price Adjustment. Refer to 520.04.01.
535 — PAVEMENT SURFACE PROFILE CATEGORY 500 PAVING SECTION 535 — PAVEMENT SURFACE PROFILE
535.01 Description
Measure the roughness of the final surface of Asphalt Mix (SAM) or Portland Cement Concrete (PCC) pavements using an International Roughness Index (IRI) Inertial Profiler to collect Quality Control (QC) data. The IRI Inertial Profiler shall conform to E950 and MSMT 563. The Administration will use an IRI Inertial Profiler to perform all Quality Assurance (QA) testing and acceptance. Measure all traveled roadway surfaces unless otherwise indicated.
535.02 Materials
Not applicable.
535.03 Construction
535.03.01 Equipment Standardization. MSMT 563. Perform standardization on
Administration specified sites at regular intervals.