2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 600 SHOULDERS SECTION 604 — CONCRETE TRAFFIC BARRIERS
604.01 Description
Construct concrete traffic barriers.
604.02 Materials
Crusher Run Aggregate CR-6 901.01 Aggregate 901.01, Size No. 57 Curing Materials 902.07 Form Release Compound 902.08 Portland Cement Concrete 902.10, Mix No. 3 Portland Cement Concrete 902.10, Mix No. 6 or 420.02.04 and 902.10 PVC Pipe Section 905 Reinforcing Steel Section 908, Grade 60, Epoxy Coated Preformed Joint Fillers 911.02 Borrow Excavation 916.01 Geotextile Section 919 Reflective Delineators QPL Fusion Bonded Epoxy 917.02 Use concrete mix No. 6 to construct all concrete traffic barriers, end transitions, and footers unless otherwise specified.
604.03 Construction
Use cast-in-place construction. Excavate to the required depth and to a width that will permit the installation and bracing of forms where necessary. Remove all soft and unsuitable material, and replace it with suitable material. Properly shape the subgrade and compact it as specified in Section 208.
604.03.01 Concrete Barriers. Forming of the footer or concrete barrier may be by either the fixed
form or the slip-form method. Do not construct the footer and the barrier section monolithically.
604.03.02 Curing. Cure and protect concrete as specified in Section 420.
604.03.03 Finished Surface. Finish concrete as specified in Section 420. The completed barriers
shall be within 1/4 in. in 10 ft from the specified horizontal and vertical lines. The barrier shall present a smooth, uniform appearance.
604.03.04 Reflective Delineators. Install reflective delineators on the concrete traffic barrier as
specified.
604.04 Measurement and Payment
The payment will be full compensation for all test panels, excavation, removal of existing asphalt mix, disposal of excess or unsuitable material, reinforcement, drilled holes, drainage appurtenances, geotextile, No. 57 aggregate, conduit, boxes and fittings, backfilling, and for all material, labor, equipment, tools, and incidentals necessary to complete the work. The removal and disposal of unsuitable material will be measured and paid for at the Contract unit price for Class 2 Excavation, which price includes the cost of using suitable excavation as replacement material. When Borrow or Selected Backfill is authorized as replacement material, payment will be made at the Contract unit price for the respective items. The removal of existing concrete traffic barriers will not be measured unless specified elsewhere in the Contract Documents.
604.04.01 Concrete Traffic Barriers will be measured and paid for at the Contract unit price per
linear foot. Measurement will be along the center line of the top of the barrier.
604.04.02 Concrete Traffic Barrier End Transitions will be measured and paid for at the Contract
unit price per each.
604.04.03 Reflective Delineators will be measured and paid for at the Contract unit price per each.
2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS 605 — METAL TRAFFIC BARRIERS CATEGORY 600 SHOULDERS SECTION 605 — METAL TRAFFIC BARRIERS
605.01 Description
Furnish and Install metal traffic barriers.
605.01.01 Training and Certifications. The Traffic Barrier W-Beam Manager (TBWBM) shall
have valid certification from successful completion of the Installer option of the “SHA Traffic Barrier Certification.” At all times during the contract, maintain current valid certifications for at least one TBWBM.
605.01.02 Traffic Barrier W-Beam Manager (TBWBM). The Traffic Barrier W-Beam
Manager (TBWBM) is responsible for the appropriate installation of traffic barrier w-beam systems and end treatments, including methods of operation and implementation of corrective actions. Duties include the following