2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 200 GRADING SECTION 205 — TEST PIT EXCAVATION
205.01 Description
Excavate and backfill test pits to determine the location of underground structures and utilities.
205.02 Materials
Not applicable.
205.03 Construction
Determine the location of underground structures and utilities by test pit excavation prior to excavation operations. Excavate test pits at the location and to the size and depth authorized. Backfill test pits as specified in Section 210.
205.04 Measurement and Payment
Test Pit Excavation will be measured and paid for at the Contract unit price per cubic yard for the material actually removed from within the limits specified. The payment will be full compensation for all excavation, tamped backfill, and all material, labor, equipment, tools, and incidentals necessary to complete the work. Any pavement to be replaced will be measured and paid for as specified in Section 106. 206 — REMOVAL OF EXISTING PAVEMENT, SIDEWALK, PAVED DITCHES, CURB, OR COMBINATION CURB AND GUTTER, AND MONOLITHIC MEDIAN CATEGORY 200 GRADING SECTION 206 — REMOVAL OF EXISTING PAVEMENT, SIDEWALK, PAVED DITCHES, CURB, OR COMBINATION CURB AND GUTTER, AND MONOLITHIC MEDIAN
206.01 Description
Remove to full depth and dispose of existing pavement, sidewalk, paved ditches, curb, or combination curb and gutter and monolithic median.
206.02 Materials
Not applicable.
206.03 Construction
206.03.01 Full Depth Saw Cut. Saw cut to full depth the existing pavement, sidewalk, paved
ditches, curb, or combination curb and gutter along the lines specified or as directed.
206.03.02 Use of Removed Pavement, Sidewalk, Paved Ditches, Curb, or Combination Curb
and Gutter and Monolithic Median. When approved, removed materials may be broken and used in the work. Refer to 204.02.01. 206.03.03 Protection of Retained Pavement, Sidewalk, Paved Ditches, Curb, or Combination Curb and Gutter and Monolithic Median. Protect all sections designated to remain from being damaged. Repair or replace damaged areas.
206.04 Measurement and Payment
The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work.
206.04.01 Full depth saw cuts, removal and disposal of existing pavement, sidewalk, paved
ditches, curb or combination curb and gutter, and monolithic median within the limits of any class of excavation will be incidental to the Contract unit price for the Class of Excavation in which it occurs. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS