CATEGORY 500 PAVING SECTION 513 — FOAMED ASPHALT STABILIZED BASE COURSE
513.01 Description
Construct a Foamed Asphalt Stabilized Base Course (FASBC) using a mix consisting of a water- foamed performance-graded asphalt binder and an aggregate blend, as specified.
513.02 Materials
Foamed Asphalt Stabilized Base Course Section 926 Recycled Asphalt Pavement (RAP) 900.03 Reclaimed/Recycled Concrete (RC) 900.03 Aggregate Section 901 Portland Cement 902.03 Fly Ash 902.06.04 Performance Graded Asphalt Binders Section 904 Production Plants Section 915 Water 921.01 Lime 921.03
513.03 Construction
513.03.01 Mix Design. Refer to 904.04.03. Submit a mix design approval from SHA’s Office of
Materials Technology’s (OMT) Soils and Aggregate Technology Division to the Engineer at least 30 days prior to placement of the FASBC material. Work will not be allowed to commence without OMT approval.
513.03.02 Quality Control Plan. Refer to 504.03, Section 915, and the following. Submit a Plant
Quality Control Plan to the Office of Material Technology and a Field Quality Control Plan to the District Engineer’s representative for approval at least 30 days prior to the placement of any FASBC.
513.03.03 Mixing Plant. Refer to 915.04 and the following:
513.03.04 Equipment. Refer to 504.03.01.
513.03.05 Weather Restrictions.
513.03.06 Storage and Transportation. FASBC must be stockpiled at the plant in a manner that
prevents moisture changes. FASBC can be stockpiled for a maximum of seven days prior to placement, unless otherwise approved. Stockpiling is not permitted for mixes containing cement or Class C fly ash. Handle and transport FASBC in a manner that minimizes segregation and loss of moisture. Do not dump FASBC into piles, haul over the completed aggregate base course, or stockpile on the job site without approval.
513.03.07 Placement. All FASBC material is to be placed using pavers. If multiple lifts are to
be placed, moisten the underlying surface prior to paving. 513.03.08 Compaction. Refer to 504.03.07 and as follows:
513.03.09 Curing and Maintenance. The FASBC shall be allowed to cure under ambient
environmental conditions and must be successfully proof rolled as specified in Section 204 or a 20 ton loaded truck before overlaying, unless otherwise approved. Repair any damaged areas of the FASBC prior to overlaying as directed. Areas that cannot be repaired must be replaced for the full depth of the base. Only allow necessary construction traffic on the FASBC unless otherwise directed. Measure the FASBC mat moisture according to T 110, T 265 or D4643 content every 2500 lane-ft through the full lift depth with a minimum sample weight of 3 lb daily until final cure is complete. Moisture may also be measured with a density gauge using the same method and locations used during compaction and applying asphalt and cement moisture corrections. Final cure will be considered complete when the moisture content drops at least 50 percent from the final compaction moisture and the FASBC is satisfactorily proof rolled as directed. Repair any damage to the completed FASBC material prior to overlaying as directed.
513.03.10 Sampling and Testing for Foamed Asphalt Cement Content. Sample for Asphalt
Cement Content behind the paver using MSMT 457 sampling method A or B before compaction of the FASBC. Obtain a total of three random samples per placement day using the Random Sample Location program used in asphalt pavement core testing. A Contractor’s Certified Technician must sample the mixture at the project site as witnessed by the Administration. The Administration will test at least one of the random behind-the-paver mix samples according to T 308. The Administration will determine the added foamed asphalt content of the random sample(s) using the ignition oven correction factor and results previously developed from the approved bag samples. The average of the foamed asphalt content of the behind-the-paver samples must be within ± 0.4 of the Job Mix Formula’s foamed asphalt cement target but no less than two percent. If the average is not within ± 0.4 of the Job Mix Formula target, the FASBC must be removed and replaced at no additional cost.
513.03.11 Control Strip. Construct a control strip at an approved location to determine the roller
patterns needed to achieve optimum density after compaction and after curing. Use the control strip to calibrate the nuclear density gauges used for QC and QA testing during placement. Place a minimum of 100 tons of FASBC in the control strip. The control strip shall be one-lane wide at the specified thickness and optimum foamed asphalt content. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Measure in-place density and moisture content in the control strip at six random locations according to MSMT 350. The average compacted dry density must be at least 97 percent of the Proctor (AASHTO T 180D) maximum dry density and the average compacted water content must be within two percentage points of optimum. Moisture content must be measured at each location using either a slow oven burn, microwave drying, or other approved suitable means with the temperature not to exceed 110 F. The measured moisture content shall be used to determine the moisture offset for the density gauge to correct for the presence of asphalt in the FASBC. A successful proof roll of the control strip as specified in Section 204 or a 20 ton loaded truck and meeting the compaction requirements are needed before proceeding with remaining FASBC construction. Accepted control strips may remain in-place and will be accepted and measured as a part of the completed foamed stabilized base. Tests used for the test strip will not be included in the evaluation for payment. Should the removal of any control strip be necessary, the Contractor must remove it at no additional cost. The Administration reserves the right to collect additional samples and perform additional tests on the material from all FASBC areas for information purposes as directed. The results of these additional tests will not be used for acceptance or payment.
513.04 Measurement and Payment
Foamed Asphalt Stabilized Base Course will be measured and paid for at the Contract unit price per square yard of the specified thickness. Surface area measurements will be based on the specified width of the base and the actual length measured along the centerline of the foamed asphalt stabilized base course. Payment will be full compensation for all aggregate, asphalt binder, other additives, furnishing, hauling, placing, curing, control strip, and for all material, labor, equipment, tools, and incidentals necessary to complete the work. Temporary graded aggregate base wedge constructed in conformance with Standard No. MD 104.01-28 will not be measured but the cost will be incidental to the foamed asphalt stabilized base course item. The cost of the Control Strip will not be measured but the cost will be incidental to the foamed asphalt stabilized base course item. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS 520 — PLAIN AND REINFORCED PORTLAND CEMENT CONCRETE PAVEMENTS CATEGORY 500 PAVING SECTION 520 — PLAIN AND REINFORCED PORTLAND CEMENT CONCRETE PAVEMENTS
520.01 Description
Construct plain and reinforced Portland cement concrete pavements.
520.02 Materials
Portland Cement Concrete and Related Products Section 902 Reinforcing Steel Section 908 Joints Section 911 Portland Cement Concrete Plant 915.03 Fusion Bonded Epoxy Powder Coatings for Steel 917.02 Reinforcement, including load transfer assemblies, tie bars, deformed steel bars, and longitudinal tie devices shall meet Section 908 and be epoxy coated.
520.03 Construction
Within 30 days prior to the start of paving operations, submit a proposed paving plan for approval. Include the production plants, location of the plants with respect to project site, equipment, proposed material sources, and indicate whether the fixed form method or slip form method is proposed. Protect the pavement against damage from all causes. Repair or replace damaged pavement. Mix, place, and finish concrete when natural light is sufficient, or with an approved artificial lighting system.
520.03.01 Equipment. All equipment, including the production plant and paving equipment, is
subject to approval. The plant, including central mixers, batching plant, truck mixers, and hauling equipment shall meet Section 915. Have the plant ready for inspection at least 48 hours prior to the start of construction operations. Have the paving equipment on the job site and ready for inspection at least 24 hours prior to the start of construction operations. Slip form pavers shall be self-propelled on crawler tracks. No other tractive force shall be applied. The paver shall be capable of being automatically controlled for both alignment and grade. 2025 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS