EXCAVATION AND EMBA NKMENT SECTION 202 103 SECTION 202 — EXCAVATION AND EMBANKMENT
202.1Description.
This work consists of excavation and embankment work.
202.2Materials.
202.3Construction.
202.3.1 General.
slopes associated with erosion control methods in accordance with Division 900;
completed in a neat and workmanlike manner.
removed and disposed under other pay items. 202.3.2 Preparing for Earthwork Operations and Maintaining the Site during Earthwork Operations.
grading, and embankment work.
embankment work.
before earth moving operations begin.
EXCAVATION AND EMBA NKMENT SECTION 202 104 1. Construct haul roads as necessary to perform the excavation and embankment work.
contractor obtains the approval of the U.S. Army Corps of Engineers or both, as applicable.
Control dust by using water during earth -moving operations.
to provide subgrade drainage.
subgrade in accordance with the contract.
following:
stability of the lift in accordance with Section 202.3.8.F. 202.3.3 Excavation.
unsuitable material.
by the engineer.
materials from the project as specified in Section 106.8. EXCAVATION AND EMBA NKMENT SECTION 202 105 2. Do not import borrow material without the approval of the engineer until all suitable excavated material has been used.
than 5 feet measured vertically from the bottom of fill to subgrade.
immediately place. Stockpile in accordance with Section 908.3 .A.
ownership of the excess topsoil to the contractor.
removal.
with Section 106.8.
in fill areas for later use. Stockpile in accordance with Section 908.3.
project.
embankments, shoulders, and slopes.
purposes. This includes material generated from bituminous pavement removal, incidental removal, and any other construction materials suitable for use as fill mate rial.
utility companies and utility contractors performing work within the limits of construction.
an approved Erosion & Sediment Control plan.
EXCAVATION AND EMBA NKMENT SECTION 202 106 202.3.4 Obstructions Encountered during Excavation.
limits of the excavation unless otherwise noted in the contract.
211 that are located below existing ground and within the excavation limits in accordance with
material meeting the requirements of Section 1001, in accordance with Section 201.3.4.
requests to the engineer to abandon pipes in place. If the engineer approves abandoning the pipes in place, fill pipes with flowable fill and plug both ends wit h Class C concrete.
property. Store salvaged pipe on or adjacent to the project for transport by the Department. 202.3.5 Preparation of Subgrade.
from the subgrade to side ditches at intervals necessary to provide subgrade drainage. Provide and maintain all facilities necessary for the complete drainage of the construction area. Provide sediment and erosion control measures for all water drained or pumped from the subgrade in accordance with the contract.
and stability. Scarify, dry, reshape, and re -compact material if construction equipment on embankments causes movement, rutting, or displacement of the mat erial, and test for density and moisture requirements. Do not allow vehicles to travel in a single track and form ruts in the subgrade.
directed by the engineer in accordance with Section 202.3.6.
accordance with AASHTO T99 Method C Modified and in -place field density in accordance with AASHTO T310. Compact the subgrade to 95 percent or more of the maximum den sity.
elevations before constructing the base or surface course. Limit the maximum variation from the subgrade elevation to the prescribed elevation to plus or minus 1/2 -inch.
material. Remove boulders, large rocks, muck, vegetation, or other foreign materials from the subgrade unless directed by the engineer. Fill depressions that deve lop during rolling with suitable material and continue to roll the subgrade until no depressions develop.
or slope rounding earthwork to finished grade elevation to form a box to retain the base material. Do not place base material in a section where a box is not complete unless specifically approved by the engineer. EXCAVATION AND EMBA NKMENT SECTION 202 107 202.3.6 Proof Rolling.
other equipment approved by the engineer.
soft, yielding, or spongy areas will be deemed stable.
achieve stability when proof rolling shows the subgrade is unstable. 202.3.7 Undercut Excavation.
construction preparation procedures to correct the unstable situation before undercutting. Normal construction preparation procedures include:
Compact the subgrade to 95 percent or more of the maximum density.
AASHTO T99 and AASHTO T310 . Compact the subgrade to 95 percent or more of the maximum density.
the subgrade or foundations.
subgrade or foundation materials
accurately judge the success of these procedures.
correcting instability.
perform undercut excavation.
purpose of correcting unstable subgrades and embankment foundations.
nor by improved environmental conditions, both given reasonable time to establish their effect, shall qualify for measurement as undercut excavation.
contractor to remove the material from within defined areas and depths. The engineer may EXCAVATION AND EMBA NKMENT SECTION 202 108 direct additional undercutting below the original defined depth. Dispose of excavated material in accordance with Section 106.8 unless otherwise directed by the engineer.
established by the engineer. Do not use equipment that will displace the underlying or adjacent material.
accordance with Section 1001 to backfill and compact the area in accordance with this section. Conduct undercut operations in a manner that allows the engineer time to take necessary measurements before placing backfill. The Department will not allow p lacement of backfill material in water unless approved by the engineer.
rework becomes necessary, salvage and reuse as much of the previously placed backfill as possible. Correct unstable subgrade or embankment foundation that exists.
Ensure that the correction of an unstable condition results in a firm, unyielding foundation. 202.3.8 Embankment Construction.
and compacting material that meets the requirements of Section 1001.
site.
material. Cease placement of embankment material when the pace of grading and compacting the material cannot keep pace with the excavation or placement of the material .
equipment is configured and operated to meet the requirements specified.
than 6:1, build benches. Backfill the benched area continuously in loose lifts no deeper than 8 inches. Begin all horizontal cuts at the intersection of the ground l ine and the vertical side of the previous bench. Step existing slopes to keep the embankment from wedging against structures. Compact excavation from benching only with the new embankment material.
matter from the existing ground surface. Scarify the cleared surface to a minimum depth of 6 - inches. Compact the subgrade material to the specified embankment density in accordance with AASHTO T99 and AASHTO T310 . Compact the subgrade to 95 percent or more of the maximum density. Where the height of the embankment is greater than 5 -feet, disc all organic matter thoroughly before constructing embankment. EXCAVATION AND EMBA NKMENT SECTION 202 109 3. Scarify existing roadways containing granular material within 3 -feet of the subgrade 6 -inches deep. Compact to the specified embankment density in accordance with AASHTO T99 and AASHTO T310 . Compact the subgrade to 95 percent or more of the maximum density.
the pavement structure if the subgrade is more than 3 -feet from the final grade, scarify 6 - inches deep and recompact unless otherwise required by the contract.
grade or within the pavement structure, if the subgrade is less than or equal to 5 -feet from the final grade, remove the underlying surfaces and base materials, scarify to a depth of 6 - inches, and compact.
except for bituminous material 12 -inches and less above the zone of frequent soil saturation.
compact.
pavement breaker or other approved equipment. The Department may restrict use of certain heavy equipment in heavy residential areas.
lifts parallel to the centerline and extending the full width of the embankment. If required, disc each lift to ensure uniform distribution of moisture and embankment materials. Compact each lift in accordance with the following before placing the next lift:
soil moisture content is not within 2 percent of optimum.
not place rocks, broken concrete, and other solid materials in embankment areas designated for placing or driving piles.
equal to the average dimension of the material being placed. The maximum allowable dimension is 36 -inches. Cut and dispose of exposed rebar. Distribute spalls and finer fragments to level and smooth each lift. Place rock, bituminous material, or PCC on the lift being constructed and push into place. Construct rock, bituminous material, or PCC lifts no c loser than 24-inches below finished subgrade.
instability discovered during the proof roll. After corrective measures, proof roll again to verify lift stability. EXCAVATION AND EMBA NKMENT SECTION 202 110 4. At the end of each working day of embankment placement, construct edge berms, interceptor berms, and embankment slopes as needed in the event of rain before work commences the following day. Extend temporary slope drains to connect to edge and intercept or berms.
aggregate, broken concrete, or other material that would be retained on a 2 1/2 -inch sieve and
bituminous material, or PCC obtained from the excavation. 202.3.9 Compaction Procedures.
Continue compaction until each lift is thoroughly and uniformly compacted to the full width of the embankment and to 95 percent or more of the maximum density of the same soils as determined by AASHTO T99 Method C Modified and AASHTO T310.
construction equipment for compaction as long as the traffic of hauling equipment is evenly distributed over the fill.
inaccessible to the specified methods of compaction, in continuous uniform horizontal lifts of no greater than 8 -inches loose measurement. Compact to the specified density before placing the next lift.
approved roller. 202.3.10 Rock Excavation.
rippers, and all boulders and detached stones with a volume of 1/2 cubic yard or greater, as rock excavation. The classification "Rock Excavation" shall n ot apply to soft disintegrated rock, bituminous pavements, gravel, broken stone, or concrete pavements and structures. These and other materials are classified as normal excavation and are included under Section 202.3.3. Drain pockets left in the surface o f the rocks before backfilling. Embank excavated rock in accordance with Section 202.3.8 or dispose in accordance with Section 106.8.
EXCAVATION AND EMBA NKMENT SECTION 202 111 C. Blasting.
conference, submit blasting methods, a schedule, and the proposed protection for ensuring safety during blasting operations.
operations. The Department will not allow excessive blasting or "over shooting." Remove and replace with approved backfill material all material outside the limits shown on the contract that is shattered or loosened by blasting.
natural undamaged condition with surfaces remaining reasonably straight and clean. If the blasting operation does not result in the slope conditions called for in the contract, modify operations until blasting does produce the required slope conditions.
produce a neat break ensuring that subsequent blasting and excavation do not affect the backslope face. Drill presplitting holes to the full depth of the ledge.
will produce an acceptable backslope. If the engineer finds the backslope acceptable, continue presplitting. Establish test sections until the engineer finds th e results satisfactory.
accommodate the head of the drill. Extend pre -splitting at least 20 -feet ahead of the limits of fragmentation blasting, unless otherwise directed. If the pre -splitting is unsatisfactory, make adjustments in the spacing, diameter, and loading of the pre -split holes using another 100 -foot test section.
completion before beginning structure work.
slices, even if located beyond the payment lines indicated in the contract.
202.4Method of Measurement.
202.4.1 Excavation and Embankment.
excavated material.
regular intervals and at breaks in grade.
EXCAVATION AND EMBA NKMENT SECTION 202 112 D. The Department will measure topsoil in its original position or in a stockpile after excavation, at the discretion of the engineer.
measure by cross -sectioning or the Department may measure topsoil quantity by cross -sectioning the area of removal before and after the contractor strips th e topsoil.
that are stockpiled for use at a later date. The Department will measure excess excavation generated by others by the cubic yard in the stockpile.
pay for this work in accordance with Section 109.7.
has approved to be abandoned in place.
outside the limits of excavation, regardless of depth. 202.4.2 Undercut Excavation.
material computed by the average end area method.
by the contractor instead of following the construction preparation procedures described in Section 202.3.7, as undercut excavation.
engineer that were not re -excavated due to the contractor’s methods of operation. 202.4.3 Rock Excavation.
by the contract or as adjusted by the engineer based on exposing the rock to perform cross - sections or topographical surveys before and after excavation.
subgrade. The Department will measure material used for backfilling the excavated areas under its appropriate section, within the limits established by the section.
202.5Basis of Payment.
202.5.1 Excavation and Embankment.
compensation for: