PIPE CULVERTS SECTION 601 163 DIVISION 600 — STRUCTURES
601.1Description.
This work consists of providing and placing pipe culverts, flared end sections, and connections to existing drainage inlets and manholes.
601.2Materials.
601.3Construction.
601.3.1 Preconstruction Inspection. The Department will review all existing pipes for use in the final drainage system and will discuss the system condition with the contractor before starting construction. 601.3.2 Excavation and Pipe Bedding.
Section 207 and the Standard Construction Details. Class C bedding is to be used in accordance with the Standard Construction Details unless specified otherwise. When Class A bedding is specified, cure PCC with materials in accordance with Section 1022.6 . Remove unsuitable material encountered below the proposed pipe bedding and replace as directed by the engineer in accordance with Section 207.
constructed, create a fill area for the pipe a minimum width of 2 pipe diameters on each side of the pipe and 18 -inches over the top of the pipe. If the embankment finished elevation is less than 18-inches above the pipe, build the fill to the finished elevation. Once the fill area is created, trench for pipe placement. 601.3.3 Reinforced Concrete Pipe.
of each pipe as follows: