SAW CUTTING AND BUTT JOINTS SECTION 762 418 SECTION 762 — SAW CUTTING AND BUTT JOINTS
762.1Description.
This work consists of mechanically saw cutting and butt joints to join new and existing pavements.
762.2Materials.
None.
762.3Construction.
mounted on a sturdy frame designed to cut PCC and bituminous concrete pavements. Supply water continuously to the cutting blade either by water tank on the eq uipment or by other means. Cut a groove in a straight line deep enough to allow for removal of material without damaging the adjacent pavement.
beyond the limits defined in the contract with an approved sealant.
762.4Method of Measurement.
number of linear feet of pavement, saw cut and accepted, along the cut end to end.
will measure the quantity of a second saw cut as the number of linear feet of pavement, saw cut and accepted, measured along the second saw cut end to end.
patch perimeter.
surface of the pavement in accordance with the contract.
762.5Basis of Payment.
unit price per linear foot. Price and payment will constitute full compensation for:
SAW CUTTING AND BUTT JOINTS SECTION 762 419 3. sealing overcuts in accordance with Section 504.3.
Price and payment will constitute full compensation for:
ITEM DESCRIPTION UNIT 762000 SAWCUTTING, BITUMINOUS CONCRETE LF 762001 SAWCUTTING, CONCRETE, FULL DEPTH LF 762002 SAWCUTTING, CONCRETE, VARIABLE DEPTH LF 762003 SAWCUTTING, GREATER THAN 18” IN DEPTH LF 762004 BUTT JOINTS SY INITIAL EXPENSE, DE -MOBILIZATION SECTION 763 420 SECTION 763 — INITIAL EXPENSE, DE -MOBILIZATION
763.1Description.
This work consists of mobilization and de -mobilization.
763.2Materials.
Assume responsibility for the adequacy of all materials not required by the contract needed to assemble and set up the project.
763.3Construction.
763.4Method of Measurement.
The Department will not measure the work in this section.
763.5Basis of Payment.
full compensation for work associated with mobilizing and demobilizing the project.
the entire contract at the time of award (“Total bid price”), the Department will pay 45 percent of the item on each of the first 2 monthly estimates and the last 10 percent of the item on the final estimate. When the lump sum price for this item exceeds 5 percent of the total bid price, the Department will pay 2.25 percent of the total bid price on each of the first 2 monthly estimates; and that portion ex ceeding 5 percent of the total bid price, plus the remaining 1/2 percent of the total bid price, will be paid on the final estimate.
than once, regardless of the number of times that the contractor must mobilize or demobilize from the site.
108.4. ITEM DESCRIPTION UNIT