PATCHING PORTLAND CEMENT CONCRETE PAVEMENT SECTION 503 157 b. providing and placing dowel bars;
503.5.1 Price Adjustment for Low Strength Concrete. The Department will calculate the prorated payment for concrete, as referenced in Section 503.3.7, as shown in the following equation:
ITEM DESCRIPTION UNIT 503001 PATCHING PCC PAVEMENT, 6’ TO 15’, TYPE A SY 503002 PATCHING PCC PAVEMENT, 15’ TO 100’, TYPE B SY 503004 PATCHING PCC PAVEMENT (UNDERCUTTING) SY-IN 503006 DOWEL BARS EA
PCC CRACK AND JOINT SEALING SECTION 504 158 SECTION 504 — PCC CRACK AND JOINT SEALING
504.1Description.
This work consists of sealing existing transverse joints, longitudinal joints, and pavement cracks in existing pavement, existing patches, or around new patch perimeters.
504.2Materials.
504.3Construction.
504.3.1 Sealant Equipment. Use sealing equipment specifically recommended by the sealant manufacturer. 504.3.2 Existing Sealant Removal.
pressure water blaster. The Department will not allow use of V -shaped plow tools to remove existing sealant.
accordance with the Standard Construction Details. 504.3.3 Refacing of Joints. Saw or reface existing joints using a power -driven concrete saw with diamond or abrasive blades to remove all old sealant from the joint faces, to expose new clean PCC, or to cut the joint to the width and depth necessary to provide the joint reservoirs shown in the contract. 504.3.4 Cleaning Before Resealing.
the joint faces and openings by sandblasting, followed by compressed air that is dry and oil free. Use compressed air equipment that delivers a continuous pressure of at least 100 pounds per square inch, measured at the source, to remove cuttings or debris remaining on the joint faces or in the joint openings.
exposed concrete surface.
installed expansion joint material, such as at existing concrete patch locations, insert a nonreactive adhesive -backed tape instead of the backer rod. Place tape 1 /8-inch wider than the nominal joint width. PCC CRACK AND JOINT SEALING SECTION 504 159 D. Equip air compressors with traps capable of removing moisture and oil from the compressed air. Stop work when there is oil or moisture in the compressed air. Make necessary adjustments to the equipment until the air stream is free of contaminants before resuming wor k.
are present on the concrete surface.
shielding the work with rigidly supported plywood sheeting or other suitable material and methods subject to the engineer’s approval.
damage occurs, submit repair procedure for approval and perform repairs to the satisfaction of the engineer. 504.3.5 Limits of Joint Preparation. Limit the final stages of joint preparation, including air pressure cleaning of joints, and placement of separating or backup material, to the length of joint that will be resealed during a day's production. 504.3.6 Installation of Hot -Poured Sealant.
of the manufacturer's recommendations to the engineer.
beginning of the day.
completion of the work, the surface of the sealant material is 1/16 to 3/16 -inch below the adjacent pavement surface. Remove excess material on the surface of the pavement. Do not allow traffic on the pavement in the area of the joints during the curing period.
504.4Method of Measurement.
the saw cutting item.
504.5Basis of Payment.
price per linear foot. Payment constitutes full compensation for:
PCC CRACK AND JOINT SEALING SECTION 504 160 ITEM DESCRIPTION UNIT 504001 PCC CRACK AND JOINT SEALING LESS THAN 3/4 -INCH WIDE LF 504002 PCC CRACK AND JOINT SEALING, 3/4 -INCH TO 1 3/4-INCH WIDE LF
PCC PATCHING, PARTIAL DEPTH SECTION 505 161 SECTION 505 — PCC PATCHING , PARTIAL DEPTH
505.1Description.
This work consists of partial depth patching of PCC.
505.2Materials.
505.3Construction.
Provide a flatwork technician with an ACI or NRMCA certification, or a certification from another program pre -approved by the Department, to supervise all concrete finishing work. Provide the flatwork certification to the engineer before placing concrete. 505.3.1 Preparation and Placement.
the patch area to provide a vertical face at the edge. Break and remove concrete within the patch area to a depth required until sound and clean concrete is ex posed. Avoid fracturing the sound concrete below the patch and undercutting or spalling the patch boundaries during the concrete removal operation.
slab, place an insert, styrofoam, wax-based bond breaker or other approved bond -breaking medium to maintain existing joint dimensions.
material. 505.3.2 Joints.
unobstructed.
achieved, if no overlay is planned in accordance with Section 504. 505.3.3 Concrete Strength Requirements.
material in accordance with the manufacturer’s recommendations. The contractor may open the patch area to traffic once the patch material reaches a compressive strength equal to or greater than 2,000 -psi. Use only rapid cured concrete that will reach a compressive strength of 2,000 -psi in 6-hours or less.
strength in the desired timeframe, then reschedule the work, subject to the approval of the engineer.