B
HomeLibrariesCopilotSearchProjectsBookmarks
FeedbackHelp Desk
Libraries
Building Codes
Code LibraryIBC — BuildingIRC — ResidentialIFC — FireIPC — PlumbingIMC — MechanicalIFGC — Fuel GasIECC — EnergyNEC — ElectricalModel Codes
Specifications
CSI SpecificationsDOT SpecsTransit SpecsUSACE
Standards
TransportationRailroadFire SafetyAccessibilityStructural
Tools & References
DiagramsAssembliesProductsCalculatorsChecklistsPermits
PricingLog in
Electrical (16000-16999)

721013 GUARDRAIL TO CONCRETE MEDIAN BARRIER TRANSITION EACH

DE · 2025 Standard SpecificationsBook pages 407413View official source ↗

HIGH -TENSION CABLE BARRIER SECTION 722 397 SECTION 722 — HIGH -TENSION CABLE BARRIER

722.1Description.

This work consists of constructing high -tension cable barrier (HTCB).

722.2Materials.

A.Provide a HTCB with the following capabilities and features:
1.Crashworthy on level terrain in accordance with the latest MASH testing requirements for a Test

Level 4 (TL -4) installation.

2.Crashworthy on a 4:1 sloped terrain in accordance with the latest MASH testing requirements

for a Test Level 3 (TL -3) installation.

3.Compatible with a crashworthy cable end terminal in accordance with the latest MASH testing

requirements for a Test Level 3 (TL -3) installation.

4.Galvanized steel posts Section 1070
a.Rust inhibitor coating meeting the requirements of Rust -Oleum Truck Bed Coating, (ROC -149)

or equal. Two coats of inhibitor from the below -ground end to 6 -inch above the final ground elevation.

B.Provide HTCB end term inals that are crashworthy in accordance with the latest MASH testing

requirements for a Test level 3 (TL -3) installation.

1.Galvanized steel posts Section 1070
a.Rust inhibitor coating meeting the requirements of Rust -Oleum Truck Bed Coating, (ROC -149)

or equal. Two coats of inhibitor from the below -ground end to 6 -inch above the final ground elevation.

722.3Construction.

722.3.1 Submittals.

A.Submit the following to the engineer before starting construction:
1.FHWA eligibility letters for the proposed HTCB system and end terminals.
2.Buy America certification for steel used on the Project.
3.Installation manual and HTCB system shop drawings.
4.Design details, calculations, dimensions, and specifications for line post concrete footings and

concrete end -terminal anchors. Base the design of line post concrete footings and concrete end - terminal anchors on the specific project location, requiremen ts as shown on the contract, what is specified here, and on Department supplied soil boring information.

5.Rust inhibitor specifications.

722.3.2 Training.

A.Provide on -site field instruction by the system manufacturer , at a location determined by the

engineer . Provide a minimum of 2 training sessions consisting of installation training before beginning cable barrier construction and maintenance training before primary inspection. The HIGH -TENSION CABLE BARRIER SECTION 722 398 manufacturer shall establish the training duration and shall provide field training on all aspects of the system. Coordinate the training schedule and location with the engineer. The engineer will advise the appropriate department staff, including construction inspectors and maintenance personnel regarding the training location and schedule. Provide all training materials in both hard copy and electronic PDF format.

B.Installation Training.
1.Hold the installation training before beginning HTCB construction. Submit the proposed training

date to the engineer a minimum of 14 calendar days before the session date for review and approval. At a minimum, the training shall include the following participants:

a.The prime contractor’s field superintendent, or designated representative.
b.HTCB sub -contractor’s field supervisor, or designated representative.
c.The engineer’s designated representatives including the project’s construction inspectors.
2.The engineer will have final approval of participants. Provide every participant with a complete

set of training handouts, the manufacturer’s installation manual, and the manufacturer’s plans for the approved system. Cover all aspects of the system inst allation, including the following subjects:

a.Description and function of all system components.
b.Manufacturer’s instructions and specifications for:
i.End anchor and post foundation installation, including foundation sizes, steel reinforcement,

concrete design strength, curing time, concrete testing, and locations; ii. line post installation; iii. end terminal assembly installation; and iv. wire rope installation and tensioning.

c.Sequence of construction operations.
d.Discussion of critical tasks.
e.Installation inspection.
C.Maintenance Training.
1.Hold the maintenance training a minimum of 7 calendar days before primary inspection of the

system. Submit the proposed training date to the engineer a minimum of 14 calendar days prior to the training session date for review and approval. Include the f ollowing participants:

a.District Maintenance Engineer, or designated representative;
b.District Maintenance Superintendent, or designated representative;
c.Area Yard Supervisor, or designated representative; and
d.District maintenance personnel.
2.The engineer will have final approval of participants. Provide every participant with a complete

set of training handouts, the manufacturer’s maintenance manual, and the manufacturer’s plans for the approved system. The training course and accompanying course material shall cover, at a minimum, the following subjects: HIGH -TENSION CABLE BARRIER SECTION 722 399 a. A description of the system components.

b.A discussion of critical features.
c.Cable barrier and terminal assembly inspection.
d.Cable barrier component replacement.
e.Terminal assembly replacement.
f.Cable tension monitoring and re -tensioning.
g.End anchor reattachment.
h.Freeing captured vehicles.
i.Field cable splicing.

3 Construction

A.Provide construction stake -out for the line posts and end terminals. Notify the engineer of any

potential conflicts with underground utilities or drainage before construction. The engineer may require the contractor to excavate test pits to determine the exact location and depth of any existing utility that may c onflict with the proposed alignment of the high -tension cable barrier system.

B.Complete all clearing, grubbing, and final grading before installing each section of cable barrier

post foundations, terminals, transitions, or anchor systems. Excavate and grade as necessary for the HTCB maintenance strip in accordance with the contrac t. Pave the maintenance strip before excavating and drilling post foundations.

C.Excavate and install cast -in-place, reinforced concrete foundations for line posts and end terminal

foundations in accordance with the manufacturer’s requirements and approved foundation shop drawings. Place foundation reinforcing steel as required in t he approved shop drawings. Place the concrete and install sockets, keeping the top of the foundation flush with the final grade. Place line posts and fitting gaskets. Space the posts, in accordance with the manufacturer’s requirements. Set posts plumb and in a straight line.

1.Refresh any damaged rust inhibiter coatings so no metal is exposed, to the satisfaction of the

engineer.

D.Install the HTCB system cables in accordance with the manufacturer’s details and specifications.

Position rigging screws to avoid interference with posts or other rigging screws unless recommended by the manufacturer.

E.Tension cables in accordance with the manufacturer’s specifications. Use certified, calibrated

testing equipment specified by the manufacturer at the beginning of the installation and throughout the project. The Department will only accept results from 1 model of tension testing device. Provide a certificate to the engineer showing that the tensioning instrument was calibrated no more than 30 calendar days before its first use on the project.

F.Provide a certified tester to perform system tension tests. Provide a letter from the manufacturer

certifying that the tester is trained in the use of the testing equipment.

G.Retest the cable tension in accordance with the manufacturer’s specifications 14 calendar days to

21 calendar days after the first test. Re -tension the cable when the test reading is less than the HIGH -TENSION CABLE BARRIER SECTION 722 400 manufacturer’s recommendations for the given temperature. Re -tension the cables to the manufacturer’s specifications by successively reading tension measurements at every rigging screw or turnbuckle. Repeat the testing and re -tension the cable in accordanc e with the manufacturer’s specifications until the manufacturer certifies the full cable system.

H.Keep a tension log showing:
1.The project name;
2.date;
3.time;
4.location;
5.weather conditions;
6.ambient temperature;
7.cable temperature;
8.tension measurement location;
9.actual tension reading;
10.tension reading after adjustment; and
11.applicable notes and the signature of the person conducting the test.
I.Provide a copy of the tension log to the engineer. Provide a letter from the manufacturer

certifying that the contractor tensioned the cable in accordance with the manufacturer’s specifications and that the cable tension complies with the manufacturer’s re quirements.

J.Delineate the HTCB system with retroreflective sheeting. Beginning with the first vertical line post

in each direction of a cable barrier segment, delineate posts at intervals no greater than 50 -feet on tangents and curves with a radius of 3,500 -feet or greater and 30 -feet on curves having a radius less than 3,500 -feet. Delineate all end terminal posts in accordance with the manufacturer’s recommendations. Ensure that delineation is visible from both directions of traffic unless otherwise shown on the pl ans. Use delineation consisting of yellow retroreflective sheeting meeting the requirements of ASTM D4956 Type IX material. The minimum area of sheeting required is 8 square inches. Attach the sheeting near the top of the post as recommended by the manufac turer. On posts with flat surfaces facing approaching traffic, the contractor may apply retroreflective sheeting directly to the post. On posts without flat surfaces facing approaching traffic, the contractor may apply the sheeting to the post cap.

K.Notify the engineer immediately if the traveling public damages the cable barrier during

construction or prior to final acceptance of the Project. Mark the affected area as directed by the engineer within 8 -hours of the damage. If only line posts incurred damage, replace the posts and re-install the cable to the posts within 48 -hours of contractor notification. If an end terminal is struck and the cables disengaged, repair, re -tension, and test the system within 24 -hours of contractor notification. After each hit, re -tension the system in accordance with the manufacturer’s specifications, if required.

L.Within 10 calendar days of the Initial inspection, supply spare parts for the HTCB system. Deliver

the parts to the DelDOT maintenance facility as directed by the engineer. Provide an extra supply of the following: HIGH -TENSION CABLE BARRIER SECTION 722 401 1. Socketed -type line posts, including post hardware, caps, reflective sheeting, straps, spacers, and socket covers. Include 200 posts and accessories.

2.Rigging screws and threaded terminals. Provide enough materials to complete 8 turnbuckle

assemblies.

3.Anchor posts including post hardware and caps, reflective sheeting, straps, fittings, spacers, and

socket covers. Provide enough materials to complete 3 end anchor installations.

4.Fitting gaskets or socket covers. Provide 100 socket covers.
M.Provide a tension meter kit and repair tool rope spreader. Provide 1 new, calibrated tension meter

that bears a serial number and has a current Certificate of Calibration from a National Institute of Standards and Testing accredited laboratory.

722.4Method of Measurement.

The Department will measure the quantity of high -tension cable barrier as the number of linear feet constructed, tested, and accepted. The Department will measure the length from the first line post adjacent to each end terminal for the run of cable barrie r. The Department will not include posts associated with the end terminal, as identified in the manufacturer’s shop drawings, in the linear foot quantity. The Department will measure the quantity of end terminals as the actual number of each end terminal c onstructed, tested and accepted.

722.5Basis of Payment.

A.The Department will pay the quantity of high -tension cable barrier at the contract unit price per

linear foot. Price and payment will constitute full compensation for:

1.Training;
2.excavation;
3.concrete and steel reinforcement ;
4.backfill and backfilling;
5.providing and placing materials and components;
6.wire rope;
7.reflective sheeting;
8.testing and re -tensioning;
9.tension meter kit;
10.repair tool rope spreader; and
11.spare parts.
B.The Department will pay the quantity of end terminals at the contract unit price per each. Price

and payment will constitute full compensation for:

1.Training;
2.excavation;
3.concrete and steel reinforcement ;

HIGH -TENSION CABLE BARRIER SECTION 722 402 4. backfill and backfilling;

5.providing and placing materials and components;
6.end terminals; and
7.spare end terminal posts and accessories.

ITEM DESCRIPTION UNIT 722001 HIGH TENSION CABLE BARRIER LF 722002 HIGH TENSION CABLE BARRIER END TERMINAL EACH CONCRETE BARRIER SECTION 723 403 SECTION 723 — CONCRETE BARRIER

723.1Description.

This work consists of constructing concrete barriers.

723.2Materials.

A.Borrow, Type C Section 1001
B.Bar Reinforcement Section 1037
1.Epoxy Coated
2.Grade 60
C.Expansion Joint Material Section 1042 .3.D
D.Liquid Membrane -Forming Compounds for Curing Section 1022
E.PCC Section 1022
1.Minimum 28 -day Compressive Strength - 4,500 pounds per square inch
2.Blend of a minimum of 40 percent Ground Granulated Blast Furnace Slag (GGBFS)
3.Fine Aggregate
F.Geotextile Section 1060
G.Coarse Aggregate , No. 57 Stone Section 1004
H.Metal Screen Galvanized Steel
I.Pipe for Weep Hole , PVC Schedule 40 Section 1049
J.Silane Based Concrete Sealer Section 1045.3
k.The Department will not allow supplier changes or substitutions once the project starts without

the engineer’s approval.

723.3Construction.

A.Provide precast or cast -in place barriers meeting contract requirements. Use slip -form

construction methods in accordance with the contract. Conduct a pre -pour meeting at least 10 - days before the start of work with representatives from the Department, the contractor, and other involved parties.

B.Excavate and compact within the template of the barrier in accordance with Section 202 and the

contract. Remove unsuitable material below the proposed foundation and replace with Borrow Type C as directed by the engineer in accordance with Section 202.

C.Construct cast -in-place barrier with forms in accordance with Section 604 and contract. Place

reinforcement bars in accordance with Section 611 and contract. Construct and c ure cast -in-place barrier in accordance with Section 610.3.6.

D.Construct precast units in accordance with Section 612. Remove the precast units from the forms

and casting bed after 12 -hours if the units reach a compressive strength of at least 1,400 PSI. Saw cut joints to control cracking of concrete.

Source: Delaware Standard Specifications for Road and Bridge Construction, 2025 Edition. Pages 407413 of 779.