ALKYD TYPE THERMOPLASTIC PAVEMENT MARKINGS SECTION 862
551 SECTION 862 – ALKYD TYPE THERMOPLASTIC PAVEMENT MARKINGS
862.1Description.
This work consists of providing and installing alkyd type thermoplastic pavement markings.
862.2Materials.
862.3Construction.
862.3.1 Submittals.
marking work. Submit the schedule 2 -weeks before the striping application. 862.3.2 Equipment.
until equipment is approved by the engineer.
a vehicle cabin. Provide the certificate of analysis to the engineer upon request.
requirements:
conforms with the manufacturer’s requirements and the requirements of the contract.
material, with an automatic thermostatic device to provide positive temperature. The kettles are to conform to the requirements of the National Board of Fire Un derwriters (NBFU), the National Fire Protection Association (NFPA), and State and local authorities. Kettles are to be easily accessible for performance of cleaning and maintenance.
mixing and conveying parts, including the application apparatus, maintains the material at the specified temperature and constructed to prevent clogging of th e applicator conveying parts between the reservoir and the application apparatus.
Provide proof of calibration to the engineer upon request.
surface, at the required application rate, by pressurization or other method not dependent upon gravity.
application. ALKYD TYPE THERMOPLASTIC PAVEMENT MARKINGS SECTION 862
552 2. Capable of applying centerline and edgeline markings at the width indicated in solid or broken patterns or various combinations thereof.
material batch. 862.3.3 Pavement marking layout.
862.3.4 Application.
laitance, and other contaminants to a width at least 4 -inches wider than the marking to be applied.
with the manufacturer's recommendations. If the manufacturer recommended temperature requirement for the pavement marking material application deviates from these specifications, the manufacturer's recommendations shall hol d priority. Confirm the atmospheric and pavement surface conditions with the engineer prior to starting work.
applying new material over existing thermoplastic material. Remove existing thermoplastic material that is not properly bonded to the existing pavement surface a t the direction of the engineer.
to demonstrate that the application equipment is working properly and applying markings as required. Repeat the demonstration whenever there is a change in equipment settings or as directed by the engineer when the quality of the line being applied is in question. Authorization to proceed will be given by the engineer when the quality control test indicates conformance. If the application of the control st rip is on the actual roadway, correct any application that is not in compliance with the contract.
recommendations. Apply in accordance with the following provisions unless approved otherwise by the engineer.
mils for transverse lines, symbols, and legends. Uniformly apply glass beads across the surface at a rate of 10 -pounds per 100 square feet of marking. ALKYD TYPE THERMOPLASTIC PAVEMENT MARKINGS SECTION 862
553 4. All necessary markings shall be installed before the end of the workday. Install the markings as soon as possible after weather interrupts the work.
track -free using a method approved by the engineer. Follow the manufacturer’s recommendations for track -free time.
any layout markings installed that detract from the overall appearance or function of pavement markings in accordance with Section 868.
complete. 862.3.5 Evaluation and Correction.
days from the date the pavement is opened to traffic. Time charges will not be assessed during the observation period provided all other work is complete. The engineer may waive a portion or all of the 180 -day observation period.
corrective action.
notification. Examples of pavement marking defects for alkyd type thermoplastic pavement marking material include:
longitudinal marking.
traveled way.
marking, or legends.
862.4Method of Measurement.
markings placed and accepted.
square feet placed and accepted. Symbols and transverse pavement markings will be measured in accordance with the following square foot values: ALKYD TYPE THERMOPLASTIC PAVEMENT MARKINGS SECTION 862
554 1. Straight arrow symbol 12.50 ft²
862.5Basis of Payment.
linear foot. Price and payment constitute full compensation for:
compound on PCC pavement;
contract unit price per square foot. Price and payment constitute full compensation for:
compound on PCC pavement;
ITEM DESCRIPTION UNIT 862001 PERMANENT PAVEMENT STRIPING, ALKYD -THERMOPLASTIC, 4" LF 862002 PERMANENT PAVEMENT STRIPING, ALKYD -THERMOPLASTIC, 6" LF ALKYD TYPE THERMOPLASTIC PAVEMENT MARKINGS SECTION 862
555 862003 PERMANENT PAVEMENT STRIPING, ALKYD -THERMOPLASTIC, 10" LF 862004 PERMANENT PAVEMENT STRIPING, ALKYD -THERMOPLASTIC, 12" LF 862005 PERMANENT PAVEMENT STRIPING, ALKYD -THERMOPLASTIC, 16" LF 862006 PERMANENT PAVEMENT STRIPING, ALKYD -THERMOPLASTIC, SYMBOL/LEGEND SF
PREFORMED THERMOPLASTIC PAVEMENT MARKINGS SECTION 863
556 SECTION 863 – PREFORMED THERMOPLASTIC PAVEMENT MARKINGS
863.1Description.
This work consists of providing and installing preformed thermoplastic pavement markings.
863.2Materials.
863.3Construction.
863.3.1 Submittals.
marking work. Submit the schedule 2 -weeks before the striping application. 863.3.2 Pavement marking layout.
863.3.3 Application.
laitance, and other contaminants to a width at least 4 -inches wider than the marking to be applied.
with the manufacturer's recommendations. If the manufacturer recommended temperature requirement for the pavement marking material application deviates from these specifications, the manufacturer's recommendations shall hol d priority. Confirm the atmospheric and pavement surface conditions with the engineer prior to starting work.
recommendations. Apply in accordance with the following provisions unless approved otherwise by the engineer.
engineer before preheating the surface.
application of the markings.
soon as possible after weather interrupts the work.
track -free using a method approved by the engineer. Follow the manufacturer’s recommendations for track -free time.
any layout markings installed that detract from the overall appearance or function of pavement markings in accordance with Section 868.