CONCRETE OVERLAYS SECTION 625 325 SECTION 625 — CONCRETE OVERLAYS
625.1Description.
This work consists of providing materials and constructing a concrete overlay on concrete deck surfaces.
625.2Materials.
625.3Construction.
625.3.1 Pre -Construction. Schedule a pre -construction meeting 14 calendar days in advance of starting construction for all overlay types. 625.3.2 Submittals. Provide required submittals for the applicable overlay system 14-days prior to the pre -construction meeting.
Submit a Construction plan that includes:
application.
travel lanes.
CONCRETE OVERLAYS SECTION 625 326 a. Performing surface preparation.
obstructions.
manufacturer will be present during overlay operations. The representative must have experience with installation of the specified system on projects of similar size and scope. Submit the manufacturer representative qualifications.
projects using the specified material within the last 5 -years. Documentation must include a description of each project, location, owner/agency name and contact information, construction date, and overlay quantity. ii. Documentation that assigned supervisory personnel have experience managing projects using the specified material. Experience must be on a minimum of 3 overlay projects using the specified material. Documentation must include a description of each project, location, owner/agency name and contact information, construction date, and overlay quantity. iii. A manufacturer’s letter of certification that the contractor is an approved installer. iv. Documentation that approved qualifying personnel will oversee all operations.
specification conformance.
approved equal. Certification must be within 1 -year of project operations. CONCRETE OVERLAYS SECTION 625 327 625.3.3 Latex -modified Concrete.
specified in the contract.
existing overlay.
specified, scarify the exposed concrete surface an additional 1/8 -inch to 1/4 -inch deep to create a bond for the proposed overlay.
subject to the engineer’s approval. Repair areas of unsound concrete in accordance with Section 628 and as specified in the Plans .
overlays before placing overlay against these surfaces.
placement. Hydro demolition may be used when approved by the engineer. Blast -clean the vertical edge of any previously placed lanes of overlay to promote bo nd. If it is necessary to remove materials detrimental to achieving bond, clean with detergent followed by shot or grit - blasting and air -blast -clean.
surface dry (SSD) condition. Saturated surface dry (SSD) is a state where the concrete has absorbed as much water it can possibly absorb without ponding or puddles forming on the surface. Achieve SSD condition by placing wet burlap on the surface for a minimum of 24 -hours or by other means submitted for approval by the engineer . Use compressed air, free of oil, to blow out any standing water in areas of concrete removal.
polyethylene film or other material approved by the engineer that completely covers the deck surface prepared for overlay.
continuous mixing -type. Provide mixers that are:
aggregate, latex modifier, and water to produce no less than 6 -cubic yards of latex modified PCC on the site;
equipped with a ticket print -out to indicate the quantity;
flow meter that is adjustable for minor variations in the moisture of the sand and aggregate;
on a continuous or intermittent basis, as required by the finishing operation, and discharges CONCRETE OVERLAYS SECTION 625 328 mixed material through a conventional chute directly in front of the finishing machine. Calibration must be performed by an approved testing laboratory or by the Department with evidence of accuracy being a yield that is within a tolerance of 1.0 percent according to the following test: With the cement meter set on zero and all controls set for the desired mix, activate the mixer and discharge mixed material into a 0.25 cubic yard container 3 feet square by 9 inches deep. When the container is full the cement meter should show a discharge of 1.875 bags of cement.
proceed at a steady pace.
ingredients to the mixer in accordance with the recommendations of the manufacturer of the latex modifier.
any other containers holding ingredients into the mix.
air content and slump.
discharged from the mixer.
overlay concrete at the worksite is 60-minutes.
rate of cement hydration, flash set, loss of water due to evaporation, high concrete ingredient temperatures, and the increased difficulty of concrete placement an d finishing. Ensure the temperature at the point of discharge does not exceed 85 degrees F.
45 degrees F for the entire curing period.
accordance with Section 625.3. 3.E. If ambient temperature falls below 45 degrees F during a cure day, the time below 45 degrees F will not be included in the 24 -hour period.
grout consisting of the overlay material brushed onto the deck. Scrub the grout onto saturated surface -dry deck areas. Do not allow excess grout to collect in low areas. Apply the bonding grout for only a short distance in advance of the placement of the overlay. The engineer will require reapplication of the grout if the grout dries before overlay placement.
with the contract and a maximum overlay thickness lift of 2 1/2-inches.
concrete is 10 -minutes. CONCRETE OVERLAYS SECTION 625 329 7. In case of a delay in the placement operation:
layers of wet burlap.
provide a gap, between the ceased operation and the continuation, long enough for the finishing machine to clear the previously placed overlay concrete.
edges, and adjacent to joint bulkheads. Provide a sufficient number of spud vibrators to simultaneously vibrate each edge of the pour behind the finishing ma chine. Hand -finish with a float along the edge of the pour or on small areas of repair. Perform edge -tooling at joints, except next to metal expansion dams, curbs, and previously placed lanes.
pan to properly consolidate the mix.
transversely along the edges of the overlay where hand -finishing takes place. Immediately correct irregularities exceeding 1/4 -inch in 10 -feet. Test the overlay concrete surface for smoothness, in accordance with Section 610.
with a minimum 4 -mil thick white, opaque polyethylene film. Lap sheeting a minimum of 6 - inches. For a period of 2 cure -days keep the burlap wet by the continuous application of water using soaker hoses. After the 2 -day wet cure period, remove the polyethylene and burlap and air cure for 3 cure -days. Record time, ambient temperature, and surface tempe rature throughout the curing period. Prohibit traffic on the overlay during this time.
curing period.
Methacrylate Sealer that conforms to Section 1045.4. Seal or repair cracking in a manner approved by the engineer before opening to traffic. The Department wil l sound the deck and the Contractor will remove and replace delaminated areas in accordance with Section 628. Correct areas of ponding to provide drainage away from the bridge deck. Crack repairs, removal and replacement of delaminated areas and correction of ponding will be performed by the contractor at no additional expense to the Department.
625.3.4 Polyester Polymer Concrete.
CONCRETE OVERLAYS SECTION 625 330 1. Shipping and Storing.
manufacture, batch number, brand name, quantity, and the date of expiration or the shelf life date. Ensure that the label of at least 1 of the system components has the mixing ratio printed on it. If using bulk resin, notify the engineer in writing 10 -days before delivery of the bulk resin. The Department defines bulk resin as resin stored in containers larger than 55 -gallons.
preservation until use. Ensure conformance with applicable fire codes that may require special storage facilities for some components of the overlay system.
weight of dry aggregate. Adjust the percentage during placement to enable proper finishing and texturing of the overlay surface.
and 90 -minutes. Use a Gillmore needle in accordance with the requirements of ASTM C266 to determine the initial set time. Use accelerators or inhibitors recommended by the resin supplier to achieve proper set times.
construction activities. Provide shielding as required or directed by the engineer.
with the bonding or curing of the overlay.
approved by the engineer. Unless otherwise specified, use automatic, self -propelled shot blasting units to clean concrete surfaces. Use a vacuum to recover spent abrasi ves. Use steel shot as abrasives for blast cleaning. In areas not accessible to machinery, clean with manual blast cleaning equipment. Use magnetic rollers to remove spent shot remaining on the deck after vacuuming.
of passes necessary to provide a surface capable of a tensile bond strength greater than or equal to 250 PSI in accordance with ASTM C1583.
Commercial Blast Cleaning. The Department will not allow wet blasting methods for cleaning.
particles, spent abrasives, or other foreign material on any of the surfaces planned for the overlay.
required for the overlay operation before overlay placement. If the pavement surface is contaminated before overlay placement, re -clean the area by abrasive bl asting to engineer’s satisfaction. CONCRETE OVERLAYS SECTION 625 331 8. Provide coverings to protect adjacent exposed areas not planned for an overlay. Clean and repair damage resulting from the overlay application to the engineer’s satisfaction.
dry aggregate;
while maintaining proper ratios to achieve specified set / cure times. Initiated resin must flow through a static mix tube for a duration sufficient to completely mix the liquids;
following, a minimum of every 5 -minutes: aggregate and resin volumes, time, and date. Submit to the engineer the recorded volumes at the end of each day;
System provider.
is dry. Blow the area clean with oil -free compressed air. Apply the prime coat only when the surface temperature is between 50 degrees F and 100 degrees F.
the rate of spread recommended by the manufacturer. Allow the prime coat to cure a minimum of 15 -minutes before placing polyester concrete.
placement. The engineer will determine the exact time of the saw cut.
whichever occurs first. Discard polyester concrete not placed within this time frame.
overlay in a manner that meets contract requirements. Phased construction or limited quantity, as approved by the engineer, may submit an alternate operation f or approval prior to use. The paving machine must:
not less than 2 -feet in the dimension parallel to the direction of paver travel. This measurement does not include finishing attachments, bolt on sections, or trailing pan extensions. CONCRETE OVERLAYS SECTION 625 332 ii. Use hydraulically controlled grade automation to establish the finished profile. The automation must be fitted with substrate grade averaging devices on both sides of the automation sensor of the sensor shall be constructed to work with string -line control. It is acceptable to match grade when placing lanes adjacent to previously placed accepted overlays . iii. Has sufficient engine power and weight to provide adequate vibration of the finishing pan while maintaining consistent forward placement speed. iv. Is capable of both forward and reverse under its own power.
the minimum thickness was not attained, add an additional layer with a minimum thickness of 1/4-inch after the overlay hardens.
off, before gelling occurs, and at a minimum rate of 2.75 ounces per square foot.
resulting from insufficient quantities of surface aggregate. Repair surface defects in the manner recommended by the manufacturer and approved by the engineer.
reach final cure and a minimum of 4 -hours after final finishing, before subjecting the overlay to traffic and equipment.
than 1/4 -inch from the lower edge of a 10 -foot long straight edge placed in any direction. Adjust surfaces that fail to conform to the tolerance by grinding with an approved grinding tool.
depressions exist that will cause water ponding . Repair surface depressions in the manner recommended by the manufacturer and approved by the engineer . 625.3.5 Modified Class D Portland Cement Concrete.
bonding agent . The horizontal surface shall receive a latex bonding agent that conforms to ASTM C1059 Type II. All vertical edges at all overlay joints shall receive an epoxy bonding agent that conforms to AASHTO M235 Type V. Follow the bonding agent manufacturer’s application recommendations CONCRETE OVERLAYS SECTION 625 333 B. Mixing . Mix PCC in accordance with Section 1022.
design strength.
degrees F and no greater than 105 degrees F.
delay comply with Section 625.4.1.C.5.
machine that complies with Section 610.3.4.D.4
spray applied without damaging the surface.
the burlap wet throughout the curing period by using soaker hoses to apply water in compliance with Section 1021.
compliance with Section 1022.6.B . Use sheets of the widest practical width. Overlap sheets a minimum of 6 inches and seal with tape, mastic, glue or other approved method to form a waterproof cover over the entire overlay surface.
sheets torn or damaged during the curing period. All curing operations must be performed without damaging the surface.
expense to the department.
period.
Methacrylate Sealer that conforms to Section 1045.4.
CONCRETE OVERLAYS SECTION 625 334 b. Areas determined to be delaminated by the Department sounding the deck will have to be removed and replaced at the Contractor’s expense.
design strength.
625.4Method of Measurement.
625.5Basis of Payment.
Price and payment will constitute full compensation for the material and delivery to project site.
inch . Price and payment will constitute full compensation for:
ITEM DESCRIPTION UNIT 625000 PROVIDING POLYESTER POLYMER CONCRETE OVERLAY CY 625001 PROVIDING LATEX -MODIFIED CONCRETE OVERLAY CY 625004 PROVIDING MODIFIED CLASS D PCC OVERLAY CY 6250 10 LATEX -MODIFIED CONCRETE OVERLAY PLACEMENT SY-IN 6250 11 POLYESTER POLYMER CONCRETE OVERLAY PLACEMENT SY-IN 6250 12 MODIFIED CLASS D PCC OVERLAY PLACEMENT SY-IN