GUARDRAIL END SECTIONS AND TRANSITIONS SECTION 721 396 ITEM DESCRIPTION UNIT 721000 GUARDRAIL END TREATMENT, TYPE 1 -31, TEST LEVEL 2 EACH 721001 GUARDRAIL END TREATMENT, TYPE 1 -31, TEST LEVEL 3 EACH 721002 GUARDRAIL END TREATMENT, TYPE 2 -31, TEST LEVEL 2 EACH 721003 GUARDRAIL END TREATMENT, TYPE 2 -31, TEST LEVEL 3 EACH 721004 GUARDRAIL END TREATMENT, TYPE 3 -31 EACH 721005 GUARDRAIL END TREATMENT, TYPE 4 -27 EACH 721006 END ANCHORAGE 31 EACH 721007 ENTRANCE SPECIAL END ANCHORAGE EACH 721008 BURIED IN BACK SLOPE EACH 721009 GUARDRAIL TO BARRIER CONNECTION (EXIT TYPE 31) EACH 721010 GUARDRAIL TO BARRIER CONNECTION, APPROACH TYPE 1 -31 EACH 721012 GUARDRAIL TO BARRIER CONNECTION, APPROACH TYPE 3 -31 EACH 721013 GUARDRAIL TO CONCRETE MEDIAN BARRIER TRANSITION EACH 721017 BULLNOSE END TREATMENT EACH HIGH -TENSION CABLE BARRIER SECTION 722 397 SECTION 722 — HIGH -TENSION CABLE BARRIER
722.1Description.
This work consists of constructing high -tension cable barrier (HTCB).
722.2Materials.
Level 4 (TL -4) installation.
for a Test Level 3 (TL -3) installation.
requirements for a Test Level 3 (TL -3) installation.
or equal. Two coats of inhibitor from the below -ground end to 6 -inch above the final ground elevation.
requirements for a Test level 3 (TL -3) installation.
or equal. Two coats of inhibitor from the below -ground end to 6 -inch above the final ground elevation.
722.3Construction.
722.3.1 Submittals.
concrete end -terminal anchors. Base the design of line post concrete footings and concrete end - terminal anchors on the specific project location, requiremen ts as shown on the contract, what is specified here, and on Department supplied soil boring information.
722.3.2 Training.
engineer . Provide a minimum of 2 training sessions consisting of installation training before beginning cable barrier construction and maintenance training before primary inspection. The