BEARING DEVICES SECTION 623 317 SECTION 623 — BEARING DEVICES
623.1Description.
This work consists of fabricating, providing, and installing bearing devices.
623.2Materials.
specified edition of the AASHTO LRFD Bridge Construction Specifications, including materials, fabrication, and testing.
623.3Construction.
Construction Specifications, Chapter 18.
the materials proposed for use. Provide the seal of a professional Delaware engineer. Do not begin fabrication until receiving the engineer's approval of the d rawings. Include the following in the working drawings:
representative responsible for coordinating production, inspection, sampling, and testing.
required grouped first according to load range type and then grouped by actual design capacity.
conform to the approved processes of the specified AASHTO/AWS D1.5 Bridge Welding Code.
of bearing.
horizontal load, rotation, and movement capacity; and maximum design coefficient of friction as noted in the contract.
BEARING DEVICES SECTION 623 318 2. If the contractor proposes an alternate design, submit supporting calculations certified by a registered Delaware professional engineer. Design bearings in accordance with the specified edition of the AASHTO LRFD Bridge Design Specifications, Chapter 14 . For steel -reinforced elastomeric bearings, design using Method B.
during shipment and storage.
strap, or otherwise fasten the components to prevent movement.
environmental and physical damage. Do not store elastomeric pads in direct sunlight.
by the engineer for installation. If the contract requires dismantling at the site, open or dismantle the bearings only under the direct supervision of the manufacturer's representative.
concrete or steel surface provided that it is flat to within a tolerance of 0.5 percent of the nominal dimension for steel reinforced bearings and 1 percent of the nom inal dimension for others. Place these bearings within 0.01 radians. Use grout or approved equal means to correct any lack of parallelism between the top of the bearing and the underside of the girder that exceeds 0.01 radians.
elastomer. Do not subject the elastomer or bond to temperatures in excess of 390 degrees F.
new concrete beams or replacing bearings in the field, use an approved epoxy adhesive to attach the bearings to the beam or sole plate.
before applying the adhesive.
representative of the bearing manufacturer is on -site for the first bearing installation and available to provide guidance for the duration of the installatio n process.
upon final installation to verify that the components are level and parallel to within 0.03 inch per foot.
embed the bolts in the holes. BEARING DEVICES SECTION 623 319 2. Either cast -in-place or epoxy grout anchor bolts in preformed sleeved holes. Burr the threads at the face of the nut.
hardening caulking compound or elastic joint sealer.
portion of the existing bearing intended for reuse or any of the existing bar reinforcement.
the time of setting. Anticipate lengthening of the bottom chord or bottom flange, resulting from dead load after setting, so that the anchor bolts at expansion bearings will center in the slots at mean temperature and under dead load. Ensure that anchor bolts or nuts allow full and free movement of the superstructure at movable bearings.
623.4Method of Measurement.
accepted.
623.5Basis of Payment.
cleaning, lubricating, and installing bearing devices.
anchor bolts, removing and disposing of existing anchor bolts, and installing anchor bolts.
disposing of debris, and greasing bearings. ITEM DESCRIPTION UNIT 623000 ELASTOMERIC BEARINGS EACH 623001 POT BEARINGS EACH 623002 DISC BEARINGS EACH 623003 REPLACE ANCHOR BOLTS EACH BEARING DEVICES SECTION 623 320 ITEM DESCRIPTION UNIT 623004 CLEAN AND GREASE BRIDGE BEARINGS EACH 623005 STEEL REINFORCED ELASTOMERIC BEARINGS EACH
JOINTS SECTION 624 321 SECTION 624 — JOINTS
624.1Description.
This work consists of fabricating, providing, and installing joints and joint seals.
624.2Materials.
624.3Construction.
fabrication. Include details and drawings of the steel elements, seals, and all other permanent elements fabricated as part of the joint system. Include techn ical data relating to the joint material, patching mortar, primer, adhesive, and other related materials, as well as mill test reports for all steel.
joint system. A manufacturer's letter of certification as an approved installer may suffice instead of having a manufacturer's representative onsite. Qualif ying personnel must oversee all operations.
similar projects with the same type of joint system within the last 5 -years. Include a brief description of each project and the owner's contact person's name and current phone number for each project listed.
contract. Repair concrete in accordance with Section 628, as required.
shipment. Set the opening of the joint at the width required for the seal in accordance with the contract. Galvanize steel elements. Perform welding and steel cutting work in accordance with
site to maintain true shape and alignment.