ELECTRIC AND ITMS CABLE AND SPLICING SECTION 832
487 SECTION 832 — ELECTRIC AND ITMS CABLE AND SPLICING
832.1Description.
This work consists of providing, placing, splicing, and removing electrical or communication cable in conduit.
832.2Materials.
832.3Construction.
Transport and unreel electric cable from a cable trailer. Do not lay reels on the ground to remove wire or cable.
and Cabinet.
mechanical puller if the engineer determines that manual pulling is not feasible.
amount specified below between the pulling grip and the pulling medium, unless otherwise directed by the engineer:
material.
off the reel and then pull into the conduit. ELECTRIC AND ITMS CABLE AND SPLICING SECTION 832
488 c. Arrange the cables in a straight lay to avoid damaging insulation and to avoid twists or kinks.
final splicing.
terminal point except for a home run cable to a loop detector wire. Do not splice emergency preemption cable in any application.
junction wells.
locations.
to avoid damaging or entanglement with existing cables or wires. The Department will not allow bending or taping the end of the fishing device instead of using the blunt end terminal.
using a pulling head.
For lighting cables, seal all conduit ends after cable placement in accordance with Section 831 - Conduit. Traffic signal conduits do not require duct sealant.
span wire to be taped.
the steel pole.
the span wire.
inches.
ELECTRIC AND ITMS CABLE AND SPLICING SECTION 832
489 a. Only splice underground traffic control cable where loop detector wire and the home -run cable meet. Do not splice cables in junction wells or conduits.
bases, or on span wire at the signal head.
placement pending splicing. Paint cable ends with a sealing type of waterproof compound.
the cables and wires in the control box and at all splice locations.
the insulation.
unused) to their original configuration before the insulation was removed and then seal in accordance with Section 1074.
signal phase.
well only. Do not splice the home -run cable outside of the junction well.
aligned. ii. Twist the copper clockwise with pliers until a good mechanical connection is achieved. iii. Install and hand tighten a wire nut. iv. If necessary to cover all the copper, minor trimming is allowed.
vi. Ensure that no insulation is caught up in the copper area of the splice. vii. Ensure that the splice is kept dry.
ii. Prepare the splice for taping after joining all conductors. iii. Place the cables in a butt position and position all wires and wire nuts to ensure that no shorts exist and that the splice area is reduced to as small a diameter as possible. iv. Begin taping with rubber tape 2 -inches over the intact sheath.
tape width until reaching a point 2 -inches on the other cable sheath. vi. Repeat taping in the other direction starting 1 tape width wider than the previous wrap. ELECTRIC AND ITMS CABLE AND SPLICING SECTION 832
490 vii. Increase overlapping where necessary to cover all areas of the splice. viii. Place at least 4 layers of rubber tape, 2 fully overlapped passes deep for every area of the splice. ix. Cover the rubber tape with plastic tape applied in the same fashion.
splice. ii. Remove the sheath of the branch cable a distance of 4 -inches. iii. Separate out and cut the through cable conductors planned for joining to the conductors of the branch cable. iv. Do not cut any other conductors for any purpose.
1 of the through cables. The Department will allow splicing of the through cable or doubling back of the through cable so that the parts of the through cable and the branch cable are placed side by side. vi. Prepare the splice for taping after joining conductors. vii. Place the cables in the approximate final position and inspect the cables for shorts. viii. After positioning all wire nuts and wires, begin taping on the through cable 2 -inches from the end of the sheath. ix. Wrap the tape around the splice proceeding with a 1/2 -inch width overlap across the splice area and onto the other through sheath for a distance of 2 -inches.
sheath for a distance of 1 -inch. xi. Wrap the tape back from the end point on the branch cable back to the main cable. xii. Tape the remaining part of the splice in the same manner. xiii. Provide rubber tape at least 4 layers, 2 fully overlapped passes deep for every area of the splice. xiv. Place the cables in the final position and tape with 2 fully overlapped passes of plastic tape in the same fashion. xv. Do not use the plastic tape to cover the interior areas covered by the rubber tape. xvi. Place the splice so that the branch cable enters the splice from below to prevent water from flowing along the branch cable into the splice area.
Ii. Wrap each individual cable with rubber tape. iii. Bundle and re -tape with vinyl tape. iv. Coat with waterproofing compound.
ELECTRIC AND ITMS CABLE AND SPLICING SECTION 832
491 i. Remove sufficient insulation of the triplex service cable and other service cables to expose the conductor. ii. Connect each of the 3 wires using a compression connecter with an approved compression tool in accordance with the manufacturer’s installation instructions.
spliced per D.3. below. ii. Apply compression type by means of a compression tool. iii. Wrap compression connector in 2 layers of vinyl tape and 2 layers of rubber tape. Half -lap tape around connector.
Install connector kits in conformance with the manufacturer’s recommendations.
preferred for all sizes of conduit.
from conduit.
between the pulling grip and the pulling medium, unless industry standards require less:
ii. 150-pounds for all pulls up through 12 pair communications cable. iii. 300-pounds for all larger cables.
the wire or cable is:
ii. Pulled without the use of a strain release element. iii. Pulled using methods that may, or did, result in pulling forces in excess of those set forth above or prescribed by industry standards.
ii. Remove the wire or cable by hand and replace the weather head cover.
conduit or steel pole. The number of electrical wires or cables pulled from a conduit may exceed 1. ELECTRIC AND ITMS CABLE AND SPLICING SECTION 832
492 832.4 Method of Measurement.
and pulled through conduits either underground, in mast arms, or in poles, or installed on a span wire, and accepted.
as part of this item.
feet of electrical wire or cable removed by pulling through a conduit or a steel pole.
pulled 1 wire at a time.
832.5Basis of Payment.
placed on a span wire at the contract unit price per linear foot of the applicable pay item. Price and payment constitute full compensation for:
4 splicing; and
the contract unit price per linear foot of the applicable pay item. Price and payment constitute full compensation for all cable removal work.
conduits or poles when used as a fish wire to pull in new wire or cable. ITEM DESCRIPTION UNIT 832001 PROVIDE AND INSTALL 1 -CONDUCTOR #4/0 AWG STRANDED COPPER, TYPE USE -2 LF 832002 PROVIDE AND INSTALL 1 -CONDUCTOR #3/0 AWG STRANDED COPPER, TYPE USE -2 LF 832003 PROVIDE AND INSTALL 1 -CONDUCTOR #2/0 AWG STRANDED COPPER, TYPE USE -2 LF 832004 PROVIDE AND INSTALL 1 -CONDUCTOR #1/0 AWG STRANDED COPPER, TYPE USE -2 LF 832005 PROVIDE AND INSTALL 1 -CONDUCTOR #1 AWG STRANDED COPPER, TYPE USE -2 LF 832006 PROVIDE AND INSTALL 1 -CONDUCTOR #2 AWG STRANDED COPPER, TYPE USE -2 LF 832007 PROVIDE AND INSTALL 1 -CONDUCTOR #4 AWG STRANDED COPPER, TYPE USE -2 LF 832008 PROVIDE AND INSTALL 1 -CONDUCTOR #6 AWG STRANDED COPPER, TYPE USE -2 LF 832009 PROVIDE AND INSTALL 1 -CONDUCTOR #8 AWG STRANDED COPPER, TYPE USE -2 LF 832010 PROVIDE AND INSTALL 1 -CONDUCTOR #10 AWG STRANDED COPPER, TYPE USE -2 LF